Construction Updates for Black Diamond Elementary School

August 16 - 31

The contractor will continue to work on the Building to completion for the First Day of School on September 5th, 2017!

Furniture and General Move In:
Furniture has been set up and will continue to deliver the missing pieces.
If there are items that you notice in your room or furniture that is missing or needed, please email liz@alliancemanagemt.com.

Framing, Windows, Finishes:
Railings at the exterior are continued to be installed. The railing at the Library is ongoing.
Toilet partitions materials have arrived and will start to be installed this week.
White board/magnetic wall at the Shared Learning Areas are scheduled. Date to be determined. We will paint the areas prior to school starts if for some reason the white board/magnetic wall is not in place.
Flagpole will be in place today and tomorrow.
Reader board is being stained and will be hooked up this week.
Library blinds / roller shades will start to be installed either Thursday or Friday the 17th/18th.
Exterior gates and remaining fencing will be done Saturday, August 16th.

Exterior of Building:
The exterior canopy at the South side is ongoing and small amounts of roofing / siding is ongoing. Exterior siding at the Covered Play is scheduled for this week.

Gym and Stage:
Motorized shades installation is ongoing and will start again Thursday and Friday the 17th/18th. Game lines will be installed Friday and Saturday (18th and 19th). Operable partition is scheduled to be installed August 28th.

Mechanical and Tech:
Mechanical commissioning process is going really smoothly, we are close to being completed, which is ahead of schedule. We are starting an evening flushing/purging to bring in cooler outside air.

Site/Underground Work:
Street paving along Baker and Second is done! Landscaping walkthrough on the 23rd. Any items will be itemized in a punch list. Striping will be occurring between August 21st and 25th. We will try to have the work done after hours.

Click the dates below to view previous construction updates:

July 28 - August 9

  • July 28 - ugust 9, 2017 BD construction
  • July 28 - ugust 9, 2017 BD construction
  • July 28 - ugust 9, 2017 BD construction
  • July 28 - ugust 9, 2017 BD construction
  • July 28 - ugust 9, 2017 BD construction

Please join us for a Community Dedication of the New Black Diamond Elementary School.
The District wanted to have the Community have the first tour as we finalize the construction progress.

The contractor will continue to work on the Building to completion; First Day of School is September 5th, 2017!

Furniture:
Furniture will continue to be set up through August 7th.
There are pieces that the manufacturer has missed and those missing pieces are in the process of being tracked down.

Framing, Windows, Finishes:
Railings at the exterior are continued to be installed.
Flooring at the stairs is complete!
Interior tackable surface will start to be installed next week at the Shared Learning Areas in the main hallyways (4 locations). It will not be installed for the Dedication.
Toilet partitions materials are delayed and will be installed in mid August. We will have temporary installation in place for the August 7th Dedication.
White board and teaching interactive white board installation is complete.
Wood ceiling is continued to be installed in the Shared Learning Areas for the next few weeks. At areas not complete, we have installed a temporary charcoal ceiling for the August 7th Dedication.
Final school interior signage is installed!
Final cleaning is ongoing as work progresses.

Exterior of Building:
The exterior canopy at the South side is ongoing and small amounts of roofing is ongoing. Exterior siding is installed.

Gym and Stage:
Motorized shades installation is ongoing.

Mechanical and Tech:
Mechanical commissioning process will take 4 to 6 months and we are meeting every two weeks to verify progress.

Site/Underground Work:
Street paving along Baker is being prepped and material removal 7/26 and 7/27.
Asphalt overlay will be completed on August 12th.
Construction Fencing has been removed.
Fencing installation is ongoing.
The play ground equipment will be delivered possibly the first two weeks after school starts. It may be delivered August 28th which would be a great surprise.
The landscaping crews' area almost complete. Misc planting still needs to be in place.
School sign is almost complete.
The trail and path to the North park is ongoing.

July 21 - 28

  • July 21 - July 28, 2017 BD construction
  • July 21 - July 28, 2017 BD construction
  • July 21 - July 28, 2017 BD construction
  • July 21 - July 28, 2017 BD construction
  • July 21 - July 28, 2017 BD construction

Construction Activities for July 21st through July 28th

Furniture:
Furniture delivery is ongoing. Will continue to be set up through August 4th.

Framing, Windows, Finishes:
Railings have been installed.
Flooring at the stairs will be complete this week. That will complete all of the flooring work!
Toilet partitions materials are delayed and will be installed in mid August. We will have temporary installation in place for the August 7th dedication.
White boards installation is ongoing.
Wood ceiling is continued to be installed in the Shared Learning Areas for the next few weeks.
Exterior door key pad/final security installation is ongoing. Contractor security system is still in place.
Final school interior signage will be installed starting the week of 7/31.
Hallway cleaning is scheduled for 7/28 and ongoing for the remaining portion of the project. Final cleaning is scheduled for 8/8.

Exterior of Building:
The exterior canopy at the South side is ongoing and small amounts of roofing is ongoing. The siding material arrived and the installation is occurring now. Siding is expected to be completed this week through 7/31.

Gym and Stage:
Motorized shades will be in place by 8/4. Game lines will be painted 8/8.

Mechanical and Tech: Mechanical commissioning process will take 4 to 6 months and we are meeting every two weeks to verify progress.

Site/Underground Work:
Street paving along Baker is being prepped and material removal 7/26 and 7/27. Asphalt overlay will be completed on August 3rd.
Fencing will be installed over the weekend and next week.
The play ground equipment will be delivered possibly the first two weeks after school starts. It may be delivered August 28th which would be a great surprise.
The landscaping crews have completed planting. Hydroseeding and bark installation will occur 7/28 through 7/31.
School sign will start to be installed the first of next week.
The trail and path to the North park will be completed the week of 7/31.

June 21 - July 7

  • June 21 - July 7, 2017 BD construction
  • June 21 - July 7, 2017 BD construction
  • June 21 - July 7, 2017 BD construction
  • June 21 - July 7, 2017 BD construction
  • June 21 - July 7, 2017 BD construction
  • June 21 - July 7, 2017 BD construction
  • June 21 - July 7, 2017 BD construction

Work Description: Note: Activities are dependent on weather.

Framing, Windows, Finishes:
South Area and North Area:
Ceramic tile hallway is ongoing and will be completed by June 30th. The specialty reception circulation desk is complete and library desk installation is ongoing.
Railings are being fabricated currently.
Toilet partitions are being delivered this week and will installed next week.
Electrical Low Voltage Ceiling and trim is ongoing.
Wood ceiling is continued to be installed in the Shared Learning Areas for the next few weeks.
Carpet installation is complete on the second floor. Resilient flooring is being installed on the second floor. Carpet is ongoing on the first floor and resilient flooring will follow thereafter.

Exterior of Building:
Exterior siding is ongoing at the South and West side. The last area will be the NW loading dock area. The work will continue over the next two to three weeks, expected to be complete by first week of July. The exterior canopy at the South side is ongoing and roofing is ongoing. The expansion joint is being installed this week and gutters are being installed next week.

Gym and Stage:
The acoustical material on the walls and painting will be completed this week.
The salvaged glu lams are installed around the stage. See the pictures, they really warm up the space!
The Gym flooring prepping is complete. The Gym flooring will be installed June 26th.
Basketball backstops will be shipped June 29th.

Mechanical and Tech:
Mechanical commissioning process will take 4 to 6 months and we are meeting every two weeks to verify progress. All equipment and building is completely locked.

Site/Underground Work:
The sidewalk areas are being prepped and some areas have been poured. This is weather dependent. There will be one concrete pour June 14th.
The North area has been prepped and hydro seeded. The landscaping crews are ongoing. Irrigation is ongoing.

June 14 - 30

  • June 14 - 30, 2017 BD construction
  • June 14 - 30, 2017 BD construction
  • June 14 - 30, 2017 BD construction
  • June 14 - 30, 2017 BD construction
  • June 14 - 30, 2017 BD construction
  • June 14 - 30, 2017 BD construction
  • June 14 - 30, 2017 BD construction
  • June 14 - 30, 2017 BD construction
  • June 14 - 30, 2017 BD construction

Work Description: Note: Activities are dependent on weather.

Framing, Windows, Finishes:
South Area and North Area
Ceramic tile hallway is ongoing.
Casework just about complete. The specialty circulation desk and library desk installation has started. It looks great! Railings are being fabricated currently.
Interior blinds are being installed.
Trim for mechanical and electric plates is ongoing.
Wood ceiling is continued to be installed in the Shared Learning Areas for the next few weeks.
Carpet installation is complete on the second floor. Ongoing on the first floor.

Exterior of Building:
Exterior siding is ongoing at the South and East side. The work will continue over the next two to three weeks, expected to be complete by end of June. The exterior canopy at the South side is ongoing and roofing will be done next week. The “Vegetation Screen”, which will be placed at the East side of the Building Elevation will be installed in July.

Gym and Stage: Kitchen equipment install is ongoing through the end of the project. The acoustical material on the walls have been installed and painting will occur the next few days.
The salvaged glu lams from the original school will be installed June 15th and 16th at the stage.
The Gym flooring will be prepped and down June 12th through end of June. Basketball backstops will be shipped June 29th.

Mechanical and Tech:
Mechanical system startup is ongoing. Commissioning process will take 4 to 6 months and we are meeting every two weeks to verify progress.
District technology is being installed on site starting Friday. All equipment and building is completely locked.

Site/Underground Work:
The sidewalk areas are being prepped. This is weather dependent. There will be one concrete pour June 14th.
The landscaping crews are on site and are prepping the area of the North field today.
Hydro seed this area of the North will occur by June 16th.
The landscape crews will move around the site after completing the North side.

May 31 - June 7

  • May 31 - June 7, 2017 BD construction classroom cabinets
  • May 31 - June 7, 2017 BD construction hallway
  • May 31 - June 7, 2017 BD construction courtyard
  • May 31 - June 7, 2017 BD construction ceiling work
  • May 31 - June 7, 2017 BD construction kitchen appliances
  • May 31 - June 7, 2017 BD construction gym

Work Description: Note: Activities are dependent on weather.

Framing, Windows, Finishes:
South Area:
Ceramic tile hallway is ongoing.
Casework plumbing fixture finish/placing sinks will be completed this week.
Trim for mechanical and electric plates is ongoing.
Wood ceiling is being installed in the Shared Learning Areas
Carpet will be installed this week and next week.
The “Vegetation Screen” which will be placed at the East side of the Building Elevation. The material has arrived.

North Area:
Casework is almost complete. The second floor boxes are set. Should be complete next week.
Ceramic Tile is ongoing. Vinyl Wall Covering and painting is ongoing.
Carpet will start June 5th.
Cleaning ongoing.

Exterior of Building:
Exterior siding is ongoing at the North and East side. The work will continue over the next four weeks. The exterior canopy at the South side is currently being framed. It looks great! Exterior doors will be placed next week.

Gym:
Painting is complete with the exception of the two Gym ends. MDF panel board is complete. Kitchen flooring cove is complete. All of the kitchen equipment is placed! The Gym flooring will be laid down June 12th.

Rough In:
Mechanical system startup is ongoing. Commissioning process will take 4 to 6 months and will be ongoing.

Site/Underground Work:
The asphalt at the South area is scheduled for Wednesday, May 30th and 31st.
The landscaping crews will start to mobilize this week.

May 25 - June 2

  • May 25 - June 2, 2017 BD construction
  • May 25 - June 2, 2017 BD construction
  • May 25 - June 2, 2017 BD construction
  • May 25 - June 2, 2017 BD construction
  • May 25 - June 2, 2017 BD construction

Work Description: Note: Activities are dependent on weather.

Framing, Windows, Finishes:
South Area:
Ceramic tile hallway is ongoing and will be completed this week.
Door hardware is being completed this week.
Casework plumbing fixture finish/placing sinks will be completed this week.
Painting is ongoing.
Trim for mechanical and electric plates is ongoing.
Carpet has been installed.

North Area:
Casework is ongoing.
Ceramic Tile is ongoing. Vinyl Wall Covering and Painting is ongoing.
Carpet will start June 5th.

Exterior of Building:
Exterior siding is ongoing at the North side. The work will continue over the next four weeks. The exterior canopy at the South side is currently being framed. It looks great!

Gym:
Painting is complete. Kitchen flooring is complete. Kitchen equipment will arrive in May. The stainless steel is scheduled to be installed May 24th. The flooring will be installed June 12th. The operable partition install coordination is ongoing.

Rough In:
Boiler start up is completed and numerous other equipment start up is ongoing. Commissioning process will take 4 months and will be ongoing.

Site/Underground Work:
The asphalt at the South area is scheduled for Wednesday, May 30th and 31th.
The landscaping crews will start to mobilize is May 30th.

May 17 - 31

  • May 17 - 31, 2017 BD construction
  • May 17 - 31, 2017 BD construction
  • May 17 - 31, 2017 BD construction
  • May 17 - 31, 2017 BD construction
  • May 17 - 31, 2017 BD construction
  • May 17 - 31, 2017 BD construction
  • May 17 - 31, 2017 BD construction

Work Description: Note: Activities are dependent on weather.

Framing, Windows, Finishes:
South Area:
Ceramic tile hallway area has some accent tile that is being waited on. All other tile complete.

Casework plumbing fixture finish/placing sinks will be complete this week.

Wood doors are being hung and is ongoing. Hardware install will follow. Aluminum doors have arrived. Install will occur this month.

Cleaning occurring this week so can startup of the mechanical equipment.
17 - 3117

North Area:
Casework is ongoing. Remainder of material delivery has arrived this week. Ceiling grid is ongoing. Ceramic Tile is ongoing.

Storefront glass install is just about complete. The small remaining glass area will be finalized the next two weeks.

Diffuser and mechanical trim will be installed this week.

Cleaning occurring this week so can start up mechanical equipment.

Elevator install ongoing - no work.

Exterior of Building:
Exterior siding is ongoing at the North side. The work will continue over the next four weeks. The exterior canopy at the South side is currently being framed.

Gym:
Painting will occur on Monday. Kitchen flooring scheduled for next week. Kitchen equipment will arrive in May. The stainless steel is scheduled to be installed May 24th. The coiling doors at the opening is scheduled to be installed on May 26th. The operable partition install coordination is ongoing.

Rough In:
Boiler start up is scheduled for this week and next week. Commissioning is scheduled to occur after.

Site/Underground Work:
The asphalt at the South area is scheduled for Wednesday, May 24th. This is weather dependent and we need a week of good weather.
The landscaping crews will start to mobilize is May 22nd.

May 10 - 24

  • front of building May 10 - 24, 2017 BD construction
  • back of building May 10 - 24, 2017 BD construction

Work Description: Note: Activities are dependent on weather.

Framing, Windows, Finishes:
South Area:
Ceramic tile hallway area is ongoing and will be complete at the end of the week.
Casework plumbing fixture finish/placing sinks is ongoing.
Wood doors are being hung and is ongoing through May 19th.

North Area:
Casework is ongoing. Ceiling grid is ongoing.
MDF panels is complete with the exception of the display cabinet areas.
Storefront glass install is just about complete. We expect this to be complete this Friday. The small remaining glass area will be finalized the next two weeks.
Painting and Vinyl Wall Covering - will be complete this week.
Elevator install ongoing - will be complete this week!

Exterior of Building:
Exterior siding is ongoing at the West side. The work will continue over the next four weeks.

Gym:
Gypsum wall board is complete and currently taping is ongoing. Painting will occur on Monday. Mechanical ducting is beginning. Kitchen equipment will arrive in May. The operable partition install coordination is ongoing.

Rough In: Boiler start up is scheduled for May 18th. Commissioning is scheduled to occur after.

Site/Underground Work: The asphalt at the South area is scheduled for Wednesday, May 17th. This is weather dependent and we need a week of good weather.
Pour for the walk at the South area is complete. The large concrete entry steps is scheduled after the asphalt placement.
The apron at the East side/public alley access is scheduled for next week.

May 3 - May 19

  • front of building May 3 - 19, 2017 BD construction
  • driveway of building May 3 - 19, 2017 BD construction
  • inside of building by big glass window May 3 - 19, 2017 BD construction
  • red painted courtyard of building May 3 - 19, 2017 BD construction
  • gray painted courtyard walls of building May 3 - 19, 2017 BD construction
  • interior ceiling beams of building May 3 - 19, 2017 BD construction

Work Description: Note: Activities are dependent on weather.

Roofing:
Roofing install is complete.

Framing, Windows, Finishes:
South Area:
Ceramic tile is complete except for the hallway area.

Casework install is completed and countertops are being installed currently.

Wood doors will start to be installed May 6th.

Carpet install is occurring next week!

Storefront install is complete and glazing is almost complete.

Plumbing fixtures have been delivered and will start to be installed.

North Area:
Casework is ongoing. Ceiling grid is ongoing.

MDF panels are being installed along the wall ongoing,

Gyp crete flooring is complete.

Storefront install ongoing. We expect this to be complete mid May.

Elevator install ongoing - will be complete the next few weeks.

Exterior of Building:
Building wrap is complete. Exterior siding is complete in the interior courtyard and ongoing at the exterior.

Gym:
Kitchen equipment will arrive in May. Hood for the Kitchen is complete.

Rough In:
Mechanical commissioning will start at May 15th. Boiler start up is scheduled for May 18th.

Site/Underground Work:
The asphalt at the South area is scheduled for Tuesday, May 9th.
Prepping for the walk at the South area is complete. Pour for this area is May 5th through 11th.

April 19 - May 5

  • photo of April  19 - May 5, 2017 BD construction
  • photo of April  19 - May 5, 2017 BD construction
  • photo of April  19 - May 5, 2017 BD construction
  • photo of April  19 - May 5, 2017 BD construction
  • photo of April  19 - May 5, 2017 BD construction
  • photo of April  19 - May 5, 2017 BD construction
  • photo of April  19 - May 5, 2017 BD construction

Work Description: Note: Activities are dependent on weather.

Roofing:
Roofing install at the Gym will be ongoing the month of April.

Framing, Windows, Finishes:
South Area:
Ceramic tile is ongoing through the end of the month.
Casework is being installed.
MDF wainscot is being installed.
Hollow metal doors has arrived the wood interior doors are scheduled for May 5th.
Elevator is arriving on Thursday this week!

North Area:
Gypsum wall board and taping complete. Paint to follow after.
Vinyl wall covering is ongoing.
Flooring gypcrete is scheduled for May 1st on the 2nd floor.
Casework is to be delivered May 8th.

Exterior of Building:
Building wrap is complete except at the Gym.Exterior flashing and exterior siding is ongoing. The siding has started in the courtyard.

Gym:
Dry-in ongoing. Kitchen equipment will arrive in May. Insulation in the roof is ongoing. Gypsum wall board is scheduled for April 24th.

Rough In:
Mechanical commissioning will start next month. Detail schedule will be provided next week. Power/main transformer will be up on April 27th. Gas meter will be installed/gas up on April 25th.

Site/Underground Work:
Concrete curbs are complete.
Ongoing parking area.

April 8 - April 21

  • photo of April  8 - April 21, 2017 BD construction
  • photo of April  8 - April 21, 2017 BD construction
  • photo of April  8 - April 21, 2017 BD construction
  • photo of April  8 - April 21, 2017 BD construction
  • photo of April  8 - April 21, 2017 BD construction
  • photo of April  8 - April 21, 2017 BD construction

Work Description: Note: Activities are dependent on weather.

Roofing:
Roofing install at the Gym will be ongoing the month of April.

Framing, Windows, Finishes:
South Area:
Ceiling grid is completed.
Ceramic tile is ongoing.
Painting at the Library is complete.
Casework is delivered in the Library and the South Classrooms!
MDF wainscot is scheduled for April 10th. Material was delivered on 4/5/17.
Hollow metal doors to arrive April 17th.
Set up to install glass within the storefront is ongoing the month of April.

North Area:
Gypsum wall board complete. Taping following. Paint to follow after.
Vinyl wall covering is ongoing.
Casework is to be delivered May 8th.

Exterior of Building:
Building wrap is complete. Exterior flashing and louvers installation is ongoing. Exterior siding will start the week of April 10th.

Gym:
Dry-in ongoing. Kitchen equipment will arrive in May. Insulation in the roof is ongoing.

Rough In:
Mechanical commissioning will start next month. Electrical and Mechanical and Low Voltage ongoing. Elevator will be placed the first part of May.

Site/Underground Work:
Concrete curbs were placed last week for the South Parking Lot and the Entry Plaza. Some seat walls and smaller areas are continued to be formed.

March 29 - April 14

  • photo of  March 29 - April 14, 2017 BD construction
  • photo of MArch 29 - April 14, 2017 BD construction
  • photo of March 29 - April 14, 2017 BD construction
  • photo of March 29 - April 14, 2017 BD construction
  • photo of March 29 - April 14, 2017 BD construction
  • photo of March 29 - April 14, 2017 BD construction
  • photo of March 29 - April 14, 2017 BD construction
  • photo of March 29 - April 14, 2017 BD construction

Work Description: Note: Activities are dependent on weather.

Roofing:
Roofing install is ongoing through April.

Framing, Windows, Finishes:
South Area:
Ceiling grid is completed.
Gypcrete topping slab is complete on the second floor.
Ceramic tile is starting to be installed next week.
Painting at the Library is scheduled for next week.
Casework is on schedule for the delivery is April 6th.
MDF wainscot is scheduled for April 10th.
Storefront arrived! Will start to be installed.

North Area:
Gypsum wall board hanging on 2nd floor is complete.
Gypsum wall board hanging 1st floor almost complete.
Taping of gypsum wall board ongoing.
Ceiling grid on the second floor is continuing.
Casework is to be delivered May 8th
Storefront will continue to be installed around the building.

Exterior of Building:
Building wrap is complete. Exterior flashing and louvers installation is ongoing. Exterior siding will start first week of April.

Gym Wall Framing:
Gymnasium blocking is ongoing to prepare for the roof sheathing. April 5th is scheduled for roofing installation.

Rough In:
Electrical and mechanical equipment is continuing as well as low voltage/data. Cable trays have been continuing.

Site/Underground Work:
Concrete for the exterior seat walls and small walk areas is formed and concrete will be placed this week. North area curbs will be placed the next two weeks. Front/South area is continuing to be prepped for asphalt through mid-April.

March 23 - April 14

  • photo of  March 23 - April 14, 2017 BD construction
  • photo of MArch 23 - April 14, 2017 BD construction
  • photo of March 23 - April 14, 2017 BD construction
  • photo of March 23 - April 14, 2017 BD construction
  • photo of March 23 - April 14, 2017 BD construction
  • photo of March 23 - April 14, 2017 BD construction

 

Work Description: Note: Activities are dependent on weather.

Roofing:
Roofing install is ongoing through April.

Framing, Windows, Finishes:
Gypcrete topping slab is complete!

South Area:
Ceiling grid is completed.
Ceramic tile is starting to be installed next week.
Painting at the Library is scheduled for next week.
Casework is scheduled to be delivered April 6th.
MDF wainscot is scheduled for April 10th.
Storefront shipped. Will take a few weeks. Expected in April.

North Area:
Gypsum wall board hanging on 2nd floor is ongoing. It will move to the 1st floor next.
Casework is to be delivered May 8th.

Exterior of Building:

Building wrap is complete. Exterior flashing and louvers installation is ongoing. Exterior siding will start first week of April.

Gym Wall Framing:
Gymnasium blocking is ongoing to prepare for the roof sheathing. April 5th is scheduled for roofing installation.

Rough In:
Electrical and mechanical equipment is continuing as well as low voltage/data. Mechanical boiler room equipment is continuing.

Site/Underground Work:
Concrete for the exterior seat walls and small walk areas is scheduled for this week.
Concrete at the loading dock and sidewalk adjacent to Bus Turn Around is complete.

March 16 - 31

  • photo of  March 9 - 24, 2017 BD construction
  • photo of March 9 - 24, 2017 BD construction
  • photo of March 9 - 24, 2017 BD construction
  • photo of March 9 - 24, 2017 BD construction
  • photo of March 9 - 24, 2017 BD construction
  • photo of March 9 - 24, 2017 BD construction

 

Work Description:
Note: Activities are dependent on weather.

Roofing:

Roofing install is ongoing until mid March.

Framing, Windows, Finishes:
Gypcrete topping slab on the second floor is scheduled for March 22nd and 23rd.
South Area:
Gypcrete topping slab April 27 and April 28 for the remaining areas.
First floor South and North Side:
* Taping gypsum board, painting and vinyl wall covering is complete.
* Ceiling grid complete.
* Ceramic tile is scheduled to start March 23rd.
* Lights arrive this week!
* Casework is on target to be delivered April 6th. All field measurements have been confirmed.
* MDF wainscot (located in hallways) is scheduled for April 10th.
Second floor North side:
* Insulation is ongoing on the North side and second floor.
* Taping and painting and vinyl wall covering is progressing.
* Ceiling grid is ongoing
* Windows complete on the second floor.
* Casework schedule for May 5th for this area.
Gym and Kitchen Area:
*
Wood blocking ongoing.
* Building dry out will start April 27th after roofing complete.

Exterior of Building:
Building wrap is complete. Exterior flashing, louvers and trim installation is ongoing.
Exterior siding will start mid-March and continue through end of April. Storefront glass will arrive middle of April.

Rough In:
Electrical and mechanical equipment is continuing. Mechanical boiler room equipment is continuing.

Site/Underground Work:
Survey on site this week. Site lighting starting this week.
Concrete steps poured next at the existing Play Shed.
Soil material being moved from the South to North to allow for work on the South side.
Seat walls prep is ongoing. Excavate the curbs this week.  Concrete pour scheduled for the week of 27th.

March 9 - 24

  • photo of  March 16 - 31, 2017 BD construction
  • photo of March 16 - 31, 2017 BD construction
  • photo of March 16 - 31, 2017 BD construction
  • photo of March 16 - 31, 2017 BD construction
  • photo of March 16 - 31, 2017 BD construction
  • photo of March 16 - 31, 2017 BD construction

 

Work Description:
Note: Activities are dependent on weather.

Roofing:
Roofing install is ongoing until mid March.

Framing, Windows, Finishes:
Gypcrete topping slab is scheduled for March 22nd and 23rd.
South Area:
Taping gypsum board, painting and vinyl wall covering is continuing!
Ceiling grid is ongoing.
Ceramic tile is scheduled for March 23rd.
Casework is scheduled to be delivered April 6th.
MDF wainscot is scheduled for April 10th.

Exterior of Building:
Building wrap almost complete. Exterior flashing and louvers installation is ongoing.
Exterior siding will start mid-March and continue through end of April.

Gym Wall Framing:
Gymnasium framing moving forward, it looks great! Gym roof trusses have been delivered and are being set.

Rough In:
Electrical and mechanical equipment is continuing. Mechanical boiler room equipment is continuing.

Site/Underground Work:
Concrete curb, stair and walks is ongoing.
Bus turn around/hard play area is being completed.
Site lighting prep is complete and will be set on the South side March 15th.
Asphalt, first lift, has been completed!

February 23 - March 10

  • photo of February 23 - March 10, 2017 BD construction
  • photo of February 23 - March 10, 2017 BD construction
  • photo of February 23 - March 10, 2017 BD construction
  • photo of February 23 - March 10, 2017 BD construction

 

Work Description:
Note: Activities are dependent on weather

Roofing:
Roofing install is ongoing until mid-March.

Framing, Windows, Finishes:
Window install is ongoing in the North section continuing February 20th.
South Area:
Taping gypsum board is ongoing and painting has started! It will move around to the North as the work progresses. Storefront (large glass areas) will be installed approx. March 20th.
Acoustical ceiling scheduled the first week of March.
Painting of the interior will start in March.
Vinyl wall covering scheduled in March.
Casework is scheduled to be delivered approx. April 6th.

Exterior of Building:
Building wrap almost complete. Exterior flashing and louvers installation is ongoing.
Exterior siding will start March 8th.

Gym Wall Framing:
Gymnasium framing moving forward. Gym roof trusses to be delivered March 8th.

Rough In:
Electrical and mechanical equipment and rough in is continuing in the mezzanine.
Mechanical mezzanine painting has started.

Site/Underground Work:
Site lighting install is ongoing.
Excavate for the curbs complete.
Survey for the curbs will occur this week.
Concrete work including stairs/curb has started and will be ongoing for three weeks.

February 16 - March 3

  • photo of February 16 - March 3, 2017 BD construction
  • photo of February 16 - March 3, 2017 BD construction
  • photo of February 16 - March 3, 2017 BD construction
  • photo of February 16 - March 3, 2017 BD construction
  • photo of February 16 - March 3, 2017 BD construction

  • photo of February 16 - March 3, 2017 BD construction

 

Work Description:
Note: Activities are dependent on weather

Roofing:
Sheathing installation is ongoing for the North side and will be completed February 21st. Roofing install is ongoing until mid March.

Framing, Windows, Finishes:
Window install is ongoing in the North section continuing February 20th.
South Area:
Storefront (large glass areas) will be installed approx. March 20th.
Hollow metal frames for the doors is ongoing.
Acoustical ceiling scheduled the first week of March.
Painting of the interior will start in March.
Vinyl wall covering scheduled in March.
Casework is scheduled to be delivered approx. April 6th.

Exterior of Building:
Exterior siding will start end of February/first of March.

Gym Wall Framing:
Gymnasium framing moving forward. Gym roof trusses to be delivered March 8th.

Rough In:
All rough in for all trades is ongoing. Mechanical equipment is placed in the mezzanine.
The access for the mechanical equipment in the mezzanine allows to get to all equipment from all sides and is full height for future maintenance.
Ongoing mechanical mezzanine gypsum board install planned for February 24th.
Mechanical mezzanine painting planning on first of March.

Site/Underground Work:
Site lighting layout is done.
Excavate for the curbs complete.
Survey for the curbs will occur this week.
Concrete work including stairs/curb starting the 23rd through mid March.

February 10 - 24

  • photo of February 10 - 24, 2017 BD construction
  • photo of February 10 - 24, 2017 BD construction
  • photo of February 10 - 24, 2017 BD construction
  • photo of February 10 - 24, 2017 BD construction
  • photo of February 10 - 24, 2017 BD construction

  • photo of February 10 - 24, 2017 BD construction

  • photo of February 10 - 24, 2017 BD construction

  • photo of February 10 - 24, 2017 BD construction

  • photo of February 10 - 24, 2017 BD construction

  • photo of February 10 - 24, 2017 BD construction

  • photo of February 10 - 24, 2017 BD construction

 

Work Description:
Note: Activities are dependent on weather
Roofing:

Sheathing is completely installed on the South side of the new trusses. Sheathing installation is ongoing for the North side. Roofing installation ongoing.

Framing South Area:
Window wrap/prep for windows is ongoing.
Window install is ongoing.
Hollow metal frames for the doors is ongoing.
Main entry stairs are complete.
Painting of the interior will start in March.

Exterior of Building:
Exterior siding will start February 22nd.

Gym Wall Framing:
Gymnasium framing will go vertical next week. The contractor is moving framing crews around the building and the Gym is the remaining item.

Rough In:
All rough in for all trades is ongoing. Mechanical equipment is placed in the mezzanine.
Fire sprinkler install is ongoing.

Site/Underground Work:
Site lighting layout is ongoing. Placement of site lights will start February 20th.
Fire lane curb line is being formed starting February 20th.

February 2 - 17

  • photo of February 2 - 17, 2017 BD construction

  • photo of February 2 - 17, 2017 BD construction

  • photo of February 2 - 17, 2017 BD construction

  • photo of February 2 - 17, 2017 BD construction

  • photo of February 2 - 17, 2017 BD construction

  • photo of February 2 - 17, 2017 BD construction

  • photo of February 2 - 17, 2017 BD construction

 

Work Description:
Note: Activities are dependent on weather

Roofing:
Roofing install is ongoing. South Area (Area A) is complete, North Area (Area B) is progressing with wood sheathing, membrane and roofing through middle of February.

Framing South Area:
Window install is ongoing, windows look great! Flashing occurring simultaneously.
Hollow metal frames for the doors is ongoing.
Main entry stairs steel frame is set - wood infill is ongoing.

Framing North Area:
Roof trusses install complete. Gym area will follow after the framing is complete. Truss insulation will continue through the 17th.

Gym Wall Framing:
Gymnasium framing commences February 8th.

Rough In:
Mechanical RI on the 1st and 2nd floor ongoing.
Electrical RI on the 1st and 2nd floor ongoing.
Mechanical AHU placed February 1st.

Site/Underground Work:
Light pole layout is ongoing. Site lighting rough in occurring through February 10th.
Playshed improvements have started.

January 26 - February 10

  • photo of January 26 - February 10, 2017 BD construction
  • photo of January 26 - February 10, 2017 BD construction
  • photo of January 26 - February 10, 2017 BD construction
  • photo of January 26 - February 10, 2017 BD construction
  • photo of January 26 - February 10, 2017 BD construction
  • photo of January 26 - February 10, 2017 BD construction
  • photo of January 26 - February 10, 2017 BD construction

 

Work Description:
Note: Activities are dependent on weather. Contractor has been working Saturdays.
Roofing:
Roofing install is ongoing.

Framing South Area:
Window wrap/prep for windows is ongoing.

Windows have been delivered! Install will start Friday the 27th.

Hollow metal frames for the doors is ongoing.

Main entry stairs steel frame is set - wood infill is almost complete.

Insulation placement is ongoing and gypsum board will be hung after in each space.

Framing North Area:
Roof trusses have been set. Building wrap (white wrap) will start now on the North exterior.

Gym Wall Framing:
Gymnasium framing has started. Lifting in place will occur next week.

Rough In:
Mechanical RI on all areas is ongoing.
Electrical RI on the 1st and 2nd floor ongoing.

Site/Underground Work:
Excavation for the exterior light poles/electrical work will start next week.

Storm water system is complete until tie in.

January 6 - January 20

  • photo of January 6 - 20, 2017 BD construction
  • photo of January 6 - 20, 2017 BD construction
  • photo of January 6 - 20, 2017 BD construction
  • photo of January 6 - 20, 2017 BD construction
  • photo of January 6 - 20, 2017 BD construction

Work Description:
Note: Activities are dependent on weather.

Roofing:
Single ply roofing installation is ongoing. Completed last week.
Vent install ongoing and roofing will be started after the vent is installed.

Framing South Area:
Library area complete.
North classrooms walls on the first floor complete.
Window wrap/prep for windows is ongoing.
Windows are planned to be delivered January 16th.
Hollow metal frames for the doors is ongoing.
Main entry stairs are being framed/steel being set.

Gym Wall Framing:
Gymnasium framing has started.
They are framing the walls on the ground and hoisting them vertical starting January 16th.

Rough In:
Mechanical RI on the 1st and 2nd floor ongoing through the 13th.
Electrical RI on the 1st and 2nd floor ongoing through the 13th.
Fire sprinkler install is ongoing.

Site/Underground Work:
Wetland detention vault will be delivered January 17th.
Storm water system will be completed by January 20th.

December 29, 2016 - January 13, 2017

  • photo of December 29 - January 13 BD construction
  • photo of December 29 - January 13 BD construction
  • photo of December 29 - January 13 BD construction
  • photo of December 29 - January 13 BD construction
  • photo of December 29 - January 13 BD construction
  • photo of December 29 - January 13 BD construction
  • photo of December 29 - January 13 BD construction
  • photo of December 29 - January 13 BD construction

Work Description:
Note: Activities are dependent on weather.

Roofing: 
Roof vent installed.
Building continues to be dried in and heat is ongoing. 
Roofing installation will start the week of January 2.

Mechanical mezzanines: 
Gypsum board was delivered and continues to be hung, including the second floor.

Framing South Area: 
Framing of the Library roof is completed.
Rigid insulation for the Library roof area is starting.
Window wrap and prep for windows is ongoing.
Windows are planned to be delivered on site December 30 - January 6.
The entry stair is starting to be set.
Steel stringer is being prepped.

Gym Wall Framing: 
Gymnasium framing has started.
They are framing the walls on the ground and hoisting them vertical. 
The classrooms spaces behind the gym have been erected.

Rough In: 
Mechanical, Electrical and Fire Sprinkler rough in ongoing.
BNCC is consistently making a lot of progress each week.

Site/Underground Work: 
Wetland detention vault will be delivered January 17.
Gas trench and installation of line is complete.

December 15 - 30

  • photo of December 8 - 23 BD construction
  • photo of December 8 - 23 BD construction
  • photo of December 8 - 23 BD construction
  • photo of December 8 - 23 BD construction with rainbow
  • photo of December 8 - 23 BD construction
  • photo of December 8 - 23 BD construction
  • photo of December 8 - 23 BD construction

Work Description:
Note: Activities are dependent on weather.


Roofing:
Roof sheathing in the South area has started and will continue depending on weather.
Roofing to be installed starting December 12th depending on weather.
Library roof framing ongoing this week!
Building is continued to be dried in - heat ongoing.

Mechanical mezzanines: Gypsum board was delivered this week and started to be hung.

Framing South Area:
Framing of the Library area roof is ongoing.
Window wrap/prep for windows is ongoing.
Windows are planned to be delivered December 30 - January 3rd.

Gym Wall Framing: Gymnasium framing has started this week!

Rough In: Mechanical, Electrical and Fire Sprinkler rough in ongoing.
There has been a lot of progress!

Site/Underground Work: Wetland detention vault will be delivered January 17th. Water tie in and fire system testing is ongoing this month. Gas trench will be complete this week.

December 8 - 23

  • photo of December 8 - 23 BD construction
  • photo of December 8 - 23 BD construction
  • photo of December 8 - 23 BD construction
  • photo of December 8 - 23 BD construction with rainbow

Work Description:
Note: Activities are dependent on weather.

Framing South Area:
Roof sheathing in the South area has started and will continue depending on weather.
Roofing to be installed starting December 12th depending on weather.
Framing of the Library area roof is ongoing.
Exterior walls are continuing being dried out.
Window wrap/prep for windows scheduled for December 12th.
Windows are planned to be delivered January 3rd.
Facia and vent panels will start to be installed December 13th.

Gym Wall Framing:
Scheduled to start December 12th.
This area will be balloon framed.

Rough In:
Mechanical and Electrical and Fire Sprinkler Rough In ongoing.

Site/Underground Work:
Wetland detention vault will be delivered January 17th.
Water tie-in and fire system testing scheduled for next week.
Asphalt work is on hold until warmer temperatures.
Prep slab on grade at the play shed scheduled for December 9th.

November 17 - November 25

  • photo of November 17 - November  25 BD construction

  • photo of November 17 - November  25 BD construction

  • photo of November 17 - November  25 BD construction

  • photo of November 17 - November  25 BD construction with rainbow

Work Description:
Framing:

Sheathing the floor will commence November 15th and will be ongoing.
Roof trusses in the classrooms (South area) are started! They are already complete already on November 9th.
Roof trusses in the Library will be set after Thanksgiving.
Roof sheathing has started and will continue in South area to North.
Roofing to be installed starting December 1st or 2nd or the 5th.

Site/Underground Work:
Footing drains are complete.
Water quality vault install is installed.
Storm System work is continuing and is being installed in the courtyard. Work for the storm system will continue to be installed through the first week in December.

November 10 - November 23

  • photo of November 3 - November  17 BD construction

  • photo of November 3 - November  17 BD construction

  • photo of November 3 - November  17 BD construction

  • photo of November 3 - November  17 BD construction

  • photo of November 3 - November  17 BD construction

Work Description:
Framing:
Second floor joists (TJI's) install is ongoing/framing at the second floor / Library (above the Admin) is ongoing.
Floor sheathing will commence November 15th and will be ongoing.
Roof trusses in the classrooms (South area) are started! They are complete already on November 9th. Roof trusses in the Library are will be set after Thanksgiving.
Roof sheathing has started and will continue from the South area to North.
Fall protection anchors will be framed/set November 17th.

Site/Underground Work
Footing drains are continuing to be placed and will be completed by November 11th.
Water line /fire sprinkler line is ongoing and will continue through November 11th.
Water quality vault install will be completed on November 15th. Storm
System work is continuing and will be ongoing for the month of November.

November 3 - November 17

  • photo of November 3 - November  17 BD construction

  • photo of November 3 - November  17 BD construction

  • photo of November 3 - November  17 BD construction

  • photo of November 3 - November  17 BD construction

  • photo of November 3 - November  17 BD construction

  • photo of November 3 - November  17 BD construction

  • photo of November 3 - November  17 BD construction

Work Description:
Framing
Second floor joists (TJI’s) install is ongoing.
Second floor walls ongoing!
Roof trusses are scheduled to be set November 8th.
Roof sheathing will be installed November 10th.
Fall protection anchors will be framed/set November 17th.

Site/Underground Work
Footing drains are continuing to be placed.
Water line /fire sprinkler line is ongoing and will continue through November 11th.
Storm System work will commence during the week of November 7th.

October 13 - October 28

  • photo of October BD construction

  • photo of October BD construction

  • photo of October BD construction

  • photo of October BD construction

  • photo of October BD construction

  • photo of October BD construction

Work Description:

Footing & Stem Wall:
Forming, prep, steel placement, enforcement, strip formwork is ongoing.

Slab on Grade:
Vapor barrier and other slab preparation is ongoing. BNCC completed the first slab pour ahead and schedule and the remaining slab is scheduled to be poured on October 20th depending on weather.

Framing:
At the South end of the project, the truss joists are being set! Wall framing is complete at the South and moving North. Great to see classroom spaces! Second floor framing is starting. Gym walls are scheduled to be framed October 24th. Roof trusses are expected to be set the first of December.

Site/Underground Work:
Footing drains are continuing to be placed.
Water line and the fire sprinkler line will start the week of October 18th to the 28th. Water line work will be completed at the East side of the site in the Right of Way/Alley and we will outreach to immediate neighbors when we know specific dates, most likely will occur between the 21st and 28th.

October 6 - October 20

  • photo of October BD construction

  • photo of October BD construction

  • photo of October BD construction

  • photo of October BD construction

  • photo of October BD construction

  • photo of October BD construction

  • photo of October BD construction


Work Description:
Detention Vault:

Backfill complete.

Footing & Stem Wall:
Forming, prep, steel placement, enforcement, strip formwork is ongoing.

Slab on Grade:
Vapor barrier and other slab preparation is ongoing. BNCC completed the first slab pour ahead and schedule and the two remaining slab pours for the building footprint are scheduled for October 12th and October 20th.

Framing:
At the South end of the project, the walls are being framed. The second floor joists will be set/installed on Thursday October 6th. Floor framing will continue North.

Site/Underground Work:
Footing drains are continuing to be placed.
Storm line at the North is almost complete.
Water line and the fire sprinkler line will start the week of October 12th to the 25th.
Water line work will be completed at the East side of the site in the Right of Way/Alley and we will outreach to immediate neighbors when we know specific dates.


September 30 - October 14

  • photo of late September BD construction
  • photo of late September BD construction
  • photo of late September BD construction
  • photo of late September BD construction

Work Description:
Detention Vault:

Backfill almost complete around the vault this week.

Footing & Stem Wall:
Prepping for the slab on grade is ongoing, with steel placement and preparing enforcement for shear walls. Forming, concrete placement for walls, striping and backfilling for walls ongoing for the north area.

Slab on Grade:
First slab pour is done! Great job BNCC and thank you for all of your hard work!

Framing:
Walls are being framed!

Site/Underground Work:
Storm line at the North side of the building is continuing.
Communication trenching across to the West ongoing.
Water line and the fire sprinkler line will start the week of October 3rd. Waterline work in the East alley will occurring in October and the exact dates will be communicated to neighbors.

 

September 15 - September 30

  • photo of late September BD construction
  • photo of late September BD construction
  • photo of late September BD construction
  • photo of late September BD construction
  • photo of late September BD construction
  • photo of late September BD construction

Work Description
Detention Vault:
Backfill to subgrade and drainage installation will continue through September 16th.

Electrical Vault:
Work complete.

Footing & Stem Wall:
Stem wall forming and retaining wall placement is continuing for the next few weeks.
Concrete slab on grade will begin to be prepared approximately September 21st and pour will be on the 27rd.

Site/Underground Work:
Mechanical, Electrical and Plumbing underground is ongoing.
PSE vault work will be completed next week.
Sewer install is almost complete.
Storm water line location surveyed and started to be installed.
Placement will continue through the 30th.

September 8 - September 21

  • photo of September BD construction
  • photo of underfloor work at EHS 1000 building
  • photo of underfloor work at EHS 1000 building

Work Description:
Detention Vault

Vault lid has been delivered and installed! Backfill to subgrade will continue through September 16th.

Grease Interceptor
To be installed beginning September 8 - 12th.

Footing & Stem Wall
Footing pour is complete. Form stripping should be complete this week. Stem wall forming and retaining wall placement is continuing for the next few weeks.
Waterproofing the elevator and retaining walls is ongoing. Stripping the forms has started and will continue.
Concrete slab on grade will begin to be prepared approximately September 21st.

Site/Underground Work
Mechanical, Electrical and Plumbing underground is ongoing.
PSE vault work will be completed next week.
Sewer install is almost complete.

August 24 - September 7, 2016

  • photo of portables in EHS parking lot
  • photo of underfloor work at EHS 1000 building
  • photo of underfloor work at EHS 1000 building
  • photo of relocation of structural walls at EHS 1000 building
  • photo of prep work for portables behind District Office

Work Description:

Focus is on underground work such as vaults, utilities and footings

Detention Vault

Stem wall pouring in progress. Vault lid will be delivered September 1st - 2nd.

Grease Interceptor

To be installed beginning August 31.

Footing & Stem Wall

Footing pour is complete. Form stripping should be complete this week
Stem wall forming and concrete pouring is in progress through September 2nd
Stripping the forms for stem walls scheduled to begin September 8th.

Site/Underground Work

Mechanical, Electrical and Plumbing underground is ongoing.
Water lines install is 29th through September 2nd.
Sewer install is continuing

August 15 - August 26, 2016

Detention Vault
Excavation is complete.
Concrete will continue to be placed.
Vault lid will be delivered September 1st - 2nd.

Grease Interceptor
Prepping for work August 25th - 30th

Footing Forming/Concrete
Placing rebar and tying in place is ongoing. Concrete pour scheduled for 22nd - 23rd.
Stripping the form walls scheduled to begin September 2nd.
Site wall forming walls is continuing through August 24th - September 2nd.

Site/Underground Work
Mechanical, Electrical and Plumbing underground is ongoing.
Water lines install is 29th through September 2nd.
Sewer install is continuing
Storm lines to start after August 18th

July 10 - July 20, 2016

  • BDE demolition
  • BDE demolition
  • BDE demolition
  • BDE demolition
  • BDE demolition

Construction Activities for July 20th and following weeks:

We invite you to attend "Meet the Contractor and Project Team" with Enumclaw School District on Monday, July 25th from 5:30 - 6:30 pm at Black Diamond Bakery. Thank you to all the community members who visited the site during demolition. It was an emotion-filled process that brought the community together. We look forward to making more connections with everyone as the building takes shape!

Demolition
Building is demolished, haul off of material is ongoing
Contractor is separating material for recycling

Site Work
Excavation of Detention Vault is ongoing and almost complete
Grading for footings will start and continue for 3 weeks

Concrete Forming
Rebar for vault was delivered
Placing rebar and tying in place will start this week
Vault and concrete footings will start and continue for 3 to 4 weeks
Electrical and plumbing rough in and underground work is scheduled to start in 3 weeks

June 27 - July 8, 2016

  • BDE fencing around front
  • BDE fencing showing the side
  • BDE showing play area

Site work and erosion control efforts have begun in earnest. General Contractor, BNCC Inc., placed a trailer on site to use as an office. Additional site work and erosion control measures will continue throughout the week, including moving of the last portable to the EHS site.

Abatement and demolition efforts began Tuesday. All State and L&I permits have been obtained to complete air quality and testing inspections. Demolition is scheduled for July 13th -22nd.

Surveying is also happening during this time. Utilities and all line locations will be identified so that BNCC Inc. can disconnect gas and water. Power is scheduled to be turned off next week to prepare for demolition of the building.

June 28, 2016

  • BDE school bus at JJ
  • BDE classroom at JJ with blue rug
  • BDE library staff at JJ library
  • BDE portable moving to JJ

Well done Black Diamond! We completed our move to JJ Smith, our home for the 2016-2017 school year while the new school is built. Thank you staff, teachers, principal, technology crew and facilities technicians along with everyone else who worked through the weekend of June 25 to finalize the well orchestrated move.

Enumclaw School District teams have worked efficiently to relocate portables via trailers from the Black Diamond site to the gravel student lot at Enumclaw High School. To be most efficient with the budget, we are moving the existing Black Diamond portables to be used as classrooms at EHS through the construction process.

The District is excited to welcome General Contractor BNCC to Black Diamond this week. Mobilization efforts include fencing around the perimeter and adding several trailers for construction purposes. Please check back for photos and weekly updates.