Construction Updates for Enumclaw High School

September 11 - September 15

  • September 11 - September 15 EHS construction
  • September 11 - September 15 EHS construction
  • September 11 - September 15 EHS construction
  • September 11 - September 15 EHS construction
  • September 11 - September 15 EHS construction

Phase 1A: Gymnasium: Boys Locker and Athletic Offices Phase 1: New Construction Classroom Wings

Phase 1A/Gymnasium:

Main Gym Interior
Divider Curtain installation is scheduled for completion by Friday, September 15th.

Men’s Locker Room
Lockers have been installed.
Metal locks for lockers are scheduled for installation by Thursday, September 14th.

Gym Lobby Addition
Display Cases are scheduled to be installed by Friday, September 15th.

New Gym Hallway
Completed for Student Access to Gym Door 901.

Next Week:
Lobby and Gym Exterior Walls will be wrapped; Furring, Rigid Insulation and Siding Installation will begin.

Phase 1/New Construction:
Deliveries:
V-Lux Skylights

Area 2
Early Wall Rough-In is ongoing.
2nd Floor Framing and Sheathing is ongoing.
Electrical Rough-In Level 1 is ongoing.
Low Roof Framing/Sheathing/Parapet Walls is ongoing.
Mechanical Mezzanine Wall Framing has begun and is ongoing.

Next Week:
2nd Floor Wall Framing, NLB/Pickup.
Sound Insulation/Pre-Rock.
Plumbing/Fire Sprinkler Rough-In at Level 2.

Area 3
2nd Floor Framing/Sheathing and Wall Plating is ongoing.

Area 4-A
Wall Framing/Sheathing of 1st Floor is ongoing.

Area 4-B
Wall Framing and Sheathing of 1st floor is ongoing.


Click the dates below to view previous construction updates:

September 4 - September 8

  • September 4 - September 8 EHS construction
  • September 4 - September 8 EHS construction
  • September 4 - September 8 EHS construction
  • September 4 - September 8 EHS construction
  • September 4 - September 8 EHS construction

Phase 1A: Gymnasium: Boys Locker and Athletic Offices Phase 1: New Construction Classroom Wings

Phase 1A/Gymnasium:
Main Gym Interior
The Main Gymnasium Interior is complete.

Men’s Locker Room
Lockers are scheduled to be installed the weekend of September 9th - 10th.
Benches, Doors/Hardware and painting are complete.

Staff Bathroom 903J and North Locker
Staff Bathroom 903J and North Lockers are complete.

Gym Lobby Addition
Gym Lobby is complete.

New Gym Hallway
Completed for Student Access to Gym Door 901.

Phase 1/New Construction:
Deliveries:
AHUs 201 - 206 have been delivered.

Area 2
Early Wall Rough-In is ongoing.
2nd Floor Framing and Sheathing is ongoing.
Plumbing/Piping Rough-In is complete.
Mechanical Platform Framing/Sheathing is complete.
Low Roof Framing/Sheathing/Parapet Walls is ongoing; scheduled to be completed by September 15th.

Next Week:
Mechanical Mezzanine Wall Framing Begins.

Area 3
2nd Floor Framing/Sheathing and Wall Plating is ongoing.

Area 4-A
Wall Framing/Sheathing of 1st Floor is ongoing.

Area 4-B
Wall Framing and Sheathing of 1st floor has begun and is ongoing.

August 21 - August 25

 

  • August 21 - 25  EHS construction
  • August 21 - 25  EHS construction
  • August 21 - 25  EHS construction
  • August 21 - 25  EHS construction
  • August 21 - 25  EHS construction
  • August 21 - 25  EHS construction
  • August 21 - 25  EHS construction
  • August 21 - 25  EHS construction

Phase 1A: Gymnasium: Boys Lockers and Athletic Offices
Phase 1: New Construction Classroom Wings
Phase 1A/Gymnasium:
Main Gym Interior
The Main Gymnasium Interior is nearly complete.
Bleachers are installed and operational!
Divider Curtain is scheduled to be delivered on September 14th, and installed on September 15th.
Exterior Infill Framing/Sheathing is ongoing.

Men’s Locker Room
Epoxy flooring has been poured and cured.
Doors and hardware scheduled to be installed and painted by August 29th.
Metal Lockers are scheduled to be delivered on Wednesday, August 30th.
Exterior Infill Framing/Sheathing is ongoing.
Rooftop Units (HVAC) are set and operational.

Next Week:
Staff Bathroom 903J and North Lockers
Owner occupancy is scheduled for Friday, September 1st!

Gym Lobby Addition
Lobby addition is nearly complete, with Back Punch scheduled for completion on Tuesday.
Exterior wall is wrapped!

New Gym Hallway
Work to be complete for Student Access to Gym Door 901 on Friday, September 1st!

Phase 1/New Construction:
Area 2
Early Wall Rough-In is ongoing.
2nd Floor Framing and Sheathing is ongoing.
Plumbing/Piping Rough-In is ongoing.
Pre-Rock Sound Insulation and Fire Tape installed as needed.
HVAC and Electrical Rough-Ins has begun and is ongoing.
Roof Framing/Sheathing began on Friday, August 25th, and is ongoing.

Area 3
Core Board Fire Separation Walls complete.
Erection of Red Iron/GLBs is complete.
2nd Floor Framing/Sheathing and Wall Plating is ongoing.

Area 4-A
Wall Framing/Sheathing of 1st Floor has begun and is ongoing

August 14 - August 18

  • August 14 - 18  EHS construction
  • August 14 - 18  EHS construction
  • August 14 - 18  EHS construction
  • August 14 - 18  EHS construction
  • August 14 - 18  EHS construction

Phase 1A: Gymnasium: Boys Lockers and Athletic Offices
Phase 1: New Construction Classroom Wings
Phase 1A/Gymnasium:
Main Gym Interior
The Main Gymnasium Interior is nearly complete. Bleachers are scheduled to be installed beginning Thursday, August 24th, and the divider being installed on Friday, August 25th.
Exterior Infill Framing/Sheathing is ongoing.

Men’s Locker Room
Epoxy flooring pour is ongoing and scheduled to be completed no later than August 28th.
Fire Alarm Testing occurred today, August 18th.
Exterior Infill Framing/Sheathing is ongoing.

Next Week:
Rooftop Units (HVAC) to be set and operational.

Staff Bathroom 903J and North Lockers
Electrical Trim completed.
Fire Alarm installation completed.
Plumbing Fixtures/Trim installation completed.

Next Week:
Toilet accessories to be installed on Monday, August 21st and occupancy scheduled by August 23rd!

Gym Lobby Addition
Lobby addition is nearly complete, with Back Punch scheduled for completion on Tuesday.
Fire Alarm Testing and Inspection occurred today, August 18th.

Next Week:
Occupancy scheduled for Monday, August 21st!

New Gym Hallway
Dry In/Roofing was completed this week.

Phase 1/New Construction:
Area 2
Early Wall Rough-In is ongoing.
2nd Floor Framing and Sheathing is ongoing.
Plumbing/Piping Rough-In is ongoing.
Pre-Rock Sound Insulation and Fire Tape installed as needed.
HVAC and Electrical Rough-Ins has begun and is ongoing.

Area 3
1st Floor walls is ongoing.
Erection of Red Iron/GLBs is ongoing.
2nd Floor Framing/Sheathing and Wall Plating is ongoing.

Area 4-A

Wall Framing/Sheathing of 1st Floor has begun and is ongoing.

July 31 - August 4

  • July 31 - August 4  EHS construction
  • July 31 - August 4  EHS construction
  • July 31 - August 4  EHS construction
  • July 31 - August 4  EHS construction
  • July 31 - August 4  EHS construction
  • July 31 - August 4  EHS construction

Phase 1A: Gymnasium: Boys Lockers and Athletic Offices Phase 1 : New Construction Classroom Wings

Phase 1A/Gymnasium:
Main Gym Interior
GWB Hang/Tape/Finish is complete.
Acoustical F-Sorb Ceiling Panels installed.
Painting of exposed structure/Conduit/HVAC/GWB/Tectum completed.
Doors/Hardware installation is ongoing.
Electrical Wire/Termination and Panelwork is complete.
Light Fixtures installed.
Court insert placement and pour has begun and scheduled to be completed by August 8th.
HVAC Startup/Operational

Next Week:
Scoreboard Installation.
Installation of Wall Pads/Backstops/Hoops/Volleyball Poles/etc.
Floor protection will be removed on August 9th.
Final Cleaning is scheduled for August 11th!

Men’s Locker Room
Electrical/HVAC/Fire Sprinkler Rough-In/Trim at Ceiling grid completed.
AV/Systems Cabling and Terminations is complete.
Ceramic Floor/Wall Tile is ongoing.
Fire Alarm/HVAC Trim complete.

Staff Bathroom 903J and North Lockers
Ceramic Floor Tile Installation is ongoing.
Electrical Trim complete.
Fire Alarm install complete.

Gym Lobby Addition
Painting of Walls/Soffits is ongoing.
Electrical Trim/Fire Alarm/IDF 6 Buildout/AV/Systems Cabling and Terminations ongoing and scheduled to be completed by August 7th.

Next Week:
Final Cleaning!

Athletic Offices
GWB-Hang/Tape/Finish is complete.
Painting/VWC Walls complete.
Electrical/Trim, Fire Sprinkler Rough-In, Trim at ceiling is ongoing and scheduled to be completed by August 7th.
Casework installation is ongoing and scheduled to be completed by August 8th.
Flooring installation is ongoing and scheduled to be completed by August 8th.

Next Week:
Final cleaning!

New Gym Hallway
Pour/Strip Footings completed.
Form Stemwalls complete.
Placement of Anchor/HD Bolts in Stemwalls completed

Next Week:
Slab Prep/SOG Re-inforcing.
Placement of SOG and Finish
Pre-Fab wall installs
Erection of Walls and Red Steel

Phase 1/New Construction:

Area 2
Early Wall Rough-In is ongoing.
2nd Floor Framing and Sheathing is ongoing.
Plumbing/Piping Rough-In is ongoing.
Pre-Rock Sound Insulation and Fire Tape installed as needed.
HVAC and Electrical Rough-Ins has begun and is ongoing.

Area 3
1st Floor walls is ongoing.
Erection of Red Iron/GLBs is ongoing.
2nd Floor Framing/Sheathing and Wall Plating is ongoing.

Area 4-A
Wall Framing/Sheathing of 1st Floor has begun and is ongoing.

July 24 - July 28

  • July 24 - 28  EHS construction
  • July 24 - 28  EHS construction
  • July 24 - 28  EHS construction
  • July 24 - 28  EHS construction
  • July 24 - 28  EHS construction

Phase 1A: Gymnasium: Boys Lockers and Athletic Offices Phase 1 : New Construction Classroom Wings

Phase 1A/Gymnasium:
Deliveries:
Tectum and Remainder of F-Sorb.
Doors with Hardware Installed.
Bleachers

Main Gym Interior
Wood Flooring Curing Period completed on July 25th.
Installation for backing for Sports Equipment completed.
Acoustical F-Sorb Ceiling Panel installation.
Painting of exposed structure/Conduit/HVAC/GWB/Tectum began on Friday, July 28th.
Doors/Hardware installation began.
Electrical Wire/Termination and Panel work is ongoing through August 4th.

Next Week:
Electrical Trim and Fire Alarm installation.
Placement/Pour of New Court Inserts will begin.
HVAC Startup/Operational.

Men’s Locker Room
GWB Hang/Tape/Finish was completed.
Painting of walls and ceiling is ongoing.
AV/Systems Cabling and Terminations.
Resilient Floor Tile installed.
Ceramic Floor/Wall Tile installation.
Fire Alarm Installation has begun and is ongoing.
Epoxy Flooring placement is ongoing and scheduled to be completed by August 4th.

Next Week:
HVAC Trim.

Staff Bathroom 903J and North Lockers
GWB Hang/Tape/Finish is complete.
Painting of Walls and Ceiling is complete.
Casework & FRL Wall Panels has begun.

Next Week:
Ceramic Floor Tile Installation.
Plumbing Fixtures/Trim
Electrical Trim.
Fire Alarm Installation.

Gym Lobby Addition
Setting of HM Door Frames and Vinyl Windows completed.
Building Wrap completed.
GWB Hang/Tape/Finish is ongoing.
Acoustical Ceiling Grid installed.
Electrical Trim, Fire Alarm, IDF 6 Buildout ongoing.

Athletic Offices
GWB-Hang/Tape is ongoing.

Next Week:
Painting/VWC Walls.
Acoustical Ceiling Grid.
Electrical/HVAC/Fire Sprinkler Rough-In/Trim at Ceiling Grid.

New Gym Hallway
Next Week:
Pour/Strip Footings.
Form Stemwalls
Placement of Anchor/HD Bolts in Stemwalls

Phase 1/New Construction:
Hardscape/site element demo continues

Area 2
Early Wall Rough-In is ongoing.
2nd Floor Framing and Sheathing is ongoing.
Plumbing/Piping Rough-In is ongoing.
Pre-Rock Sound Insulation and Fire Tape installed as needed.
HVAC and Electrical Rough-Ins has begun and is ongoing.

Next Week:
Plumbing/Piping Rough-In at Grids E1 and E2
Fire Sprinkler Rough-In

Area 3
Core Board Fire Separation Walls was completed.
2nd Floor Framing/Sheathing and Wall Plating is ongoing and scheduled to be completed by August 4th.

Next Week:
2nd Floor Framing/Sheathing and Wall Plating.

Area 4-A
Place/Finish/Sofcut Control Joints, SOG/Cure completed on Friday, July 28th.

Next Week:
Erection of Red-Iron and Glulam Beam
Wall Framing/Sheathing of 1st Floor
Core Board Fire Separation Walls

July 10 - 14

  • July 10 - 14 EHS construction
  • July 10 - 14 EHS construction
  • July 10 - 14 EHS construction
  • July 10 - 14 EHS construction
  • July 10 - 14 EHS construction
  • July 10 - 14 EHS construction

Phase 1A/Gymnasium:
Main Gym Interior
HM Door Jamb installation completed on July 11th.
Wood Floor installation is ongoing and is scheduled to be completed by July 17th.
Wood Floor Sand/Seal/Striping/Finish is ongoing through July 20th.
Floor Mural Painting began on July 13th and is ongoing through July 18th.

Next Week:
Wood Flooring Curing Period begins July 20th.

Men’s Locker Room
GWB Hang/Tape/Finish is ongoing through July 21st.
Mechanical Insulation and Cover Inspection was completed on July 11th.
Hardlid Framing was completed on July 11th.
HVAC Rough-In at Hardlid was completed on July 11th.
Electrical Rough-In at Hardlids and cover inspection occurred on July 14th.

Next Week:
Paint Walls and Ceiling.
Fire Alarm Installation (continuing through July 19th).
Acoustical Ceiling Grid placement.
Electrical/HVAC/Fire Sprinkler Rough-In/Trim @ceiling grid.
AV Systems Cabling and Terminations.

Staff Bathroom 903J and North Lockers
GWB Hang/Tape/Finish is ongoing through July 19th.
SOG placed July 13th.
Electrical Wall/Ceiling Rough-In completed on July 11th.

Next Week:
Painting of Walls and Ceiling.

Gym Lobby Addition
Pour/Strip Footings/Stemwalls completed on July 14th (pour on Jul 13th).
Re-Steel Inspection occurred on July 12th.
Perimeter Rigid Insulation install and Damproof Prep of Stemwalls completed on July 14th.
MEP Wall/Soffit Rough-In continues through July 20th.
Exterior/Interior Wall/Soffit Framing/Sheathing is ongoing through July 21st.

Next Week:
Setting of HM Door Frames and Vinyl Windows.
GWB Hang/Tape/Finish begins.

Athletic Offices
Wall Framing completed on July 12th.
MEP Rough-In completed on July 14th.
HM Door/Window Frames set on July 14th.

Next Week
GWB Hang/Tape.

New Gym Hallway
Over excavation of footings and structural fill to grade completed on July 11th.
Form Footings placed on July 13th.
Re-steel of Footings/Stemwalls.

Next Week:
Pour/Strip Footings.

Phase 1/New Construction:
Hardscape/site element demo continues

Area 2
Early Wall Rough-In is ongoing.
Erection of Red-Iron/GLBs completed on July 6th.
2nd Floor Framing and Sheathing is ongoing.
Plumbingh/Piping Rough-In is onging.
Core Board and Fire Walls at South side of 100 Bldg., Grid EA, completed on July 14th.
Wall infills/re-frame of South Wall of 100 Bldg. completed on July 5th.

Area 3
Framing of new openings in South Wall Commons completed.
Erection of Red Iron/GLBs completed.
Wall framing/sheathing of 1st floor continues through July 21st.

Next Week:
2nd Floor Framing/Sheathing and Wall Plating.

Area 4-A
Deliveries:
Area 4 GL Beams scheduled to be delivered.

Underslab Electrical completed.

Next Week:
SOG Reinforcing.
6” Cap Break placement.
Slab prep.

July 3 - July 7

  • July 3 - 7 EHS construction
  • July 3 - 7 EHS construction
  • July 3 - 7 EHS construction
  • July 3 - 7 EHS construction
  • July 3 - 7 EHS construction

Phase 1A/Gymnasium:
Deliveries:
Court Inserts scheduled to be delivered on July 10th
Toilet Partitions scheduled to be delivered on July 10th

Main Gym Interior
HM Door Jamb installation completed on July 5th.
GWB Hang/Tape/Finish behind bleachers completed on July 5th.
Electrical Trim is ongoing through July 14th.
Fire Alarm installation is ongoing through July 19th.
Wood Floor installation is ongoing and is scheduled to be completed by July 17th.

Next Week:
Wood Floor Sand/Seal/Striping/Finish (scheduled to be completed by July 20th)
Floor Mural Painting beginning on July 13th.

Men’s Locker Room
GWB Hang/Tape/Finish is ongoing through July 14th.

Next Week:
Installation of Doors and Hardware.
Fire Alarm Installation (continuing through July 19th).

Staff Bathroom 903J and North Lockers
GWB Hang/Tape/Finish is ongoing through July 13th.

Next Week:
Painting of Walls and Ceiling.

Gym Lobby Addition
Next Week:
GWB Hang/Tape/Finish begins and will be ongoing through July 18th.

Athletic Offices
HM Door/Window Frame setting completed on July 7th.
Paint/VWC Walls completed on July 7th.

Next Week:
Installation of Acoustic Ceiling Grid.
Electric/HVAC/Fire Sprinkler Rough-In/Trim at Ceiling Grid.
AV/Systems Cabling and Terminations.

New Gym Hallway
Next Week:
Over excavation of footings and structural fill to grade.
Re-steel of Footings/Stemwalls

Phase 1/New Construction:
Hardscape/site element demo continues

Area 2
Wall Framing/Sheathing of 1st floor completed on July 6th.
Early Wall Rough-In is ongoing.
Erection of Red-Iron/GLBs completed on July 6th.
2nd Floor Framing and Sheathing is ongoing.
Core Board and Fire Walls at South side of 100 Bldg., Grid EA, completed on July 7th.
Wall infills/re-frame of South Wall of 100 Bldg. completed on July 5th.

Area 3
Framing of new openings in South Wall Commons completed on July 6th.
Erection of Red Iron/GLBs completed on July 6th.
Wall framing/sheathing of 1st floor continues through July 14th.

Next Week:
2nd Floor Framing/Sheathing and Wall Plating.

Area 4-A
Deliveries:
Area 4 GL Beams scheduled to be delivered in July 10th.

1. Underslab Plumbing completed on July 3rd
2. Underslab Electrical completed on July 7th.

Next Week:
SOG Reinforcing.
Concrete (SOG) pour scheduled for Thursday, July 13th.

June 25 - June 30

  • June 25 - 30 EHS construction
  • June 25 - 30 EHS construction
  • June 25 - 30 EHS construction
  • June 25 - 30 EHS construction
  • June 25 - 30 EHS construction
  • June 25 - 30 EHS construction

Work Description: Please note: Activities may change and are weather dependent
Phase 1A: Gymnasium, Boys Lockers, Girls Lockers, and Athletic Offices

Phase 1: New Construction Classroom Wings

Phase 1A/Gymnasium:
Deliveries: Roof Top Units and Vinyl Windows delivered June 26th.
Toilet Accessories delivered on June 30th.

Main Gym Interior
Painting is scheduled to begin on July 13th.
Hardwood material is onsite.
Divider curtain will be delivered July 20th/21st.
Flooring finishes are expected to be completed by August 2nd.
Scoreboard installation will occur on July 31st.
Bleachers scheduled to be delivered on July 27th.
Wood floor sanding, finishing and painting will be done over the next two weeks.
Mural will ready July 13th for painting of court lines.
Structural Steel installed at New Drinking Fountain on June 29th.
New opening for Drinking Fountain was completed on June 30th.
Insulation at Tectum Wall panels occurred on June 26th.
HM Door Jamb installation began on June 30th and is scheduled to be completed by July 5th.
GWB Hang/Tape/Finish behind bleachers is ongoing through July 5th.
HVAC Diffusers installation completed on June 26th.
AV/Stems Cabling and Terminations was completed on June 30th.
Electrical Trim, Fire Alarm installation is ongoing.
Stock/Acclimation of Wood Flooring occurred on June 26th and 27th.
Wood Floor installation is ongoing and is scheduled to be completed by July 16th.

Men’s Locker Room
Mechanical, Plumbing, Electrical, HVAC, Fire Sprinkler rough in began June 26th and is ongoing.
Door jambs arrived and are ready for installation.
Insulation installed June 26th through June 28th.
Installation of HM Door Jambs began on 29th and is scheduled to be completed by July 5th.
GWB Hang/Tape/Finish began on June 27th and is scheduled to be completed by July 7th.
Fire Alarm installation is ongoing through July 19th.
Casework and benches installation will begin week of July 17th.

Staff Bathroom 903J and North Lockers
Sawcut and demolition of slab occurred on June 28th.
Selective Restroom demolition occurred on June 26th.
Underslab/Wall Plumbing Rough-In occurred June 26th through 30th.

Next Week:
Backfill/Prep for Slab On Grade
Placement and Finish of Slab On Grade (concrete pour)
Electrical Wall and Ceiling Rough-In
HVAC Rough-In
GWB Hang/Tape/Finish begins and is scheduled to be completed by July 13th.

Gym Lobby Addition
North Wall - Exterior Wall Framing/Sheathing occurred on June 26th and 27th.
West Wall - 2” H Stud Core Board Wall installed June 26th and 27th.
West Wall Frame/Sheet was completed on June 30th.
Setting of HM Door Frames and Vinyl Windows began on June 28th and is scheduled to be completed by July 6th.
Metal Roof Pan Deck installed on June 28th.
Interior Wall/Soffit Framing - IDF and AV ongoing through July 5th.
MEP Wall/Soffit Rough-In began June 30th and is scheduled to be completed by July 7th.
Excavation of remaining footings occurred on June 26th.
Re-steel of Footing and Stemwalls occurred on June 27th.
(Pour) 28th
Pour of Strip Footings and Stemwalls occurred on June 28th.
Perimiter Rigid Insulation installed June 29th.
12” Sub Base placement occurred June 29th.
6” Cap Break placement on June 29th.
Slab Prep and SOG reinforcement completed June 30th.
Place/Finish/Sofcut of control joints for SOG on 30th

Next Week:
Dampproofing of Stemwalls.
Exterior/Interior Wall/Soffit Framing/Sheathing.
Setting of HM Door Frames and Vinyl Windows.
MEP Wall/Soffit Rough-In.

Athletic Offices
GWB Hang/Tape completed on June 30th.

Next Week:
Setting of HM Door/Window Frames
Paint/VWC Walls - ongoing

Gym Hallway
Over excavation of footings and structural fill to grade completed on June 28th.
Form Footings completed on June 30th.
Re-steel of Footings/Stemwalls began on June 30th and scheduled to be completed by July 3rd.

Locker Room Roof
Parapet/2X Nailer/Framing/installation completed on June 26th.
Selective Siding Demolition on West Side completed on June 26th.
Roofing is ongoing.

Coaches’ Office Roof
Demolition completed on June 28th.
Parapet/2X Nailer/Fire Ply Framing/Installation completed on June 30th.
Dry in roof completed on June 30th.

Next Week:
Roofing scheduled to begin July 7th.

Phase 1/New Construction:
Deliveries:
Area 3 2nd floor bar joists delivered
Area 4 A/B structural steel delivered.

Hardscape/site element demo continues
Area 2 continuing framing of structural walls at the North side. Floor joints will be placed Friday. HVAC / Fire Sprinkler and plumbing rough will start July 10th.
Area 3/South wall of commons in progress. Doors will be removed and infilled. Wall in front will be constructed ongoing.
Sprinkler Riser Room will be stubbed up the first week of July.
4A slab is scheduled for July 13th.
4B concrete installed June 29th.
NE Corner Counseling is occurring June 26th. Windows will be removed and siding will be removed. The window will be removed and framed in tomorrow. It will be finished prior to August.
Trusses being delivered 6/28 for Area 2.
Truss additional delivery will be mid July.
FDC work outside of entry of HS work is ongoing. FDC re-route is underway.  Cold patch will be done immediately, concrete will ultimately be done prior to school starting.

Area 2
Concrete poured June 29th.
Wall framing/sheathing of 1st floor completed on June 28th.
Erection of Red Iron/GLBs completed on June 30th.
Floor Joints placed on June 30th.
2nd floor framing/sheathing and wall plating continues and is scheduled to be completed by 7/14.
Early wall Rough-In is continuing.
Core board fire walls of s side of bldg. 100 installed as ready beg on 6/29 stbcb 7/7
Select demolition at South Wall of 100 Bldg. completed on June 30th.
Wall infills and re-frame of South Wall of 100 Bldg. began June 29th and is scheduled to be completed by July 5th.

Next Week:
Framing of Sprinkler Riser Room.
HVAC/Fire Sprinkler and Plumbing Rough-In will begin July 10th.

Area 3
Framing of new openings at South Wall began on June 28th and continues through July 5th.
Wall framing/sheathing of 1st floor began on June 28th and should be completed by July 14th.

Next Week:
Erection of Red Iron and GLBs
Core Board Fire Separation Wall installation

Area 4-A
Pour/strip stemwalls and remainder of footings completed on June 26th.
Perimeter Rigid insulation install completed on June 27th.
12” Sub Base placement completed June 29th.
Underslab plumbing began June 28th and is scheduled to be completed by July 3rd.
Underslab electrical placement began June 28th and is scheduled to be completed by July 7th.
Preparation and damproofing of stemwalls was completed on June 27th.

Area 4-B
6” cap break placed on June 26th
SOG Reinforcing on June 28th.
Stemwalls prep and dampproofing completed on June 27th.

June 19 - 23

  • June 19 - 23 EHS construction
  • June 19 - 23 EHS construction
  • June 19 - 23 EHS construction

Work Description: Please note: Activities may change and are weather dependent
Phase 1A: Gymnasium, Boys Lockers, Girls Lockers, and Athletic Offices

Phase 1: New Construction Classroom Wings
Sitework: Fire Department Connection (FDC) re-route will occur on June 26th in front of the school entryway. On Monday, June 26th, access to the HS Admin will be closed off and will be diverted to the Staff Lounge or another route.

South wall of Admin Counselor Offices scheduled for demo on June 26th.

Phase 1A/Gymnasium:
Main Gymnasium:
Painting is ongoing; painting of exposed trusses and ducts is complete.
South and East walls: Cover inspection cleared and completed.
North and West walls: GWB at the walls and the really high locations are being completed.
CMU infills were completed on Friday, June 23rd. Lobby framing will occur this week, including the AV and IDF. Formation of South Lobby footings begins after school is out.
Hardwood material is onsite. Hardwood install will occur the 27th. Sand, finish coats, painting lines occurring the seal coat (three days). Mural will be done at this time (27, 28th). Divider curtain being delivered July 20/21th. The flooring finishes are expected to be completed August 2nd.
Owner Furnished items coordinated July 26th/27th through the 30th. Scoreboard delivered on Thursday, June 22nd.
Roof stripped and being stocked and protected on June 21st.
Gym lobby slab on grade is partially completed; remaining areas will be constructed after June 26 (after school is out).

Locker Rooms:
Locker Room: Mechanical and fire sprinkler work is ongoing. Scaffolding was removed on June 21st to make way for the epoxy flooring prep.
Gym: Roof stripped/being stocked and protected today.

Phase 1/New Construction:
Area 2:
Science floor framing/floor sheathing begins this week. HVAC and Fire Sprinkler rough in will begin the week of July 10th.

Area 3:
South wall of commons in progress. New sheathing for existing wall in progress. Coreboard install at this wall will occur on July 5th.
Sprinkler Riser Room will be stubbed up the first week of July.

Area 4:

Area 4B inspection occurred on Friday, June 23rd.
Concrete pour will occur on Thursday, June 29th.
Area 4A stem walls and footings will be completed by Friday the 30th. This will complete the stem walls and footing concrete for Phase 1!
NE Corner Counseling is occurring June 26th. Counseling will move out. Windows will be removed and infilled.

Site Work:
Area 4B will be going to subgrade currently. Prep for pour on June 29th.
Sewer line extension. Locates began on the June 23rd.

June 12 - 16

  • June 12 - 16 EHS construction
  • June 12 - 16 EHS construction
  • June 12 - 16 EHS construction
  • June 12 - 16 EHS construction
  • June 12 - 16 EHS construction

Work Description: Please note: Activities may change and are weather dependent
*Phase 1A: Gymnasium: Boys Lockers: Girls Lockers and Athletic Offices

*Phase 1: New Construction Classroom Wings
*
Sitework: Fire Department Connection (FDC) re-route - occur June 26h (after school). It will be in front of the entry of the school.South wall of Admin Counselor demo June 26th


 

 

 

 

 

 

Hardscape/Site Elements Demo is ongoing as needed.

Phase 1A/Gymnasium:
Painting of exposed Structural/Electrical Conduit/HVAC was completed.
Installation of Acoustical F-Sorb Ceiling Panels has begun and will continue through next week.
GWB Hanging, Taping and Finish is still ongoing; scheduled to be completed by June 20th.
Doors and Hardware installation began this week; scheduled to be completed by June 20th.

Next Week:
Installation of Acoustical Tectum Wall Panels.
Wall painting begins.
Installation of HVAC Diffusers
Installation of AV/Systems Cabling and Terminations begins.
Install of Electrical Trim, Fire Alarm
Acclimation of Wood Flooring scheduled to begin, as well.

Phase 1A/Gym Lobby Addition
2” H Stud Core, Board Wall, Framing and Sheet completed on West Wall.
Interior Wall/Soffit Framing and IDF completed.

Next week:
HM Door Frames and Vinyl Window installation.
MEP Wall/Soffit Rough-In scheduled.

Phase 1A/Athletic Offices
MEP Rough Wall Rough continues.

Phase 1/A Mens Locker Room
CMU Infills and new walls completed.
Plumbing, electrical and HVAC
Rough-In completed.
Fire Sprinkler Rough-In completed.
Insulation completed.
GWB Hanging/Taping/Finish began and is ongoing through next week.
Doors/Hardware installation began, scheduled to be completed by June 20th.

Phase 1/New Construction:
Contractor is continuing to excavate for footings and foundations. Pouring concrete in Area 4A approx. June 29th.
Area 2 is poured out. Area 3 pour is complete.
Framing of first floor continues in Area 2 and is nearly complete.
Red-Iron/GLBs erected in Area 2 and Area 3.
Strip Stem Walls poured in Areas 4A and 4B.
Rigid insulation around perimeter installed in Area 4B.
12” Sub Base placed in Area 4B

Next Week:
Underslab plumbing and electrical.
Additional Strip Stemwalls scheduled to be poured on June 21st, with rigid insulation for same to be installed thereafter.
Wall Framing/Sheathing of 1st floor in Area 3.

Site Work:
New FDC (fire department connection) at the NE corner of the building, (South side/near counselor office). This work service won’t be done until after school is out the week of the 26th.

June 2 - 9

  • June 2 - 9 EHS CMU grouting
  • June 2 - 9 EHS area 4a forms
  • June 2 - 9 EHS gym interior
  • June 2 - 9 EHS gym lobby
  • June 2 - 9 EHS framing walls

Work Description: Please note: Activities may change and are weather dependent
*Phase 1A: Gymnasium: Boys Lockers: Girls Lockers and Athletic Offices

*Phase 1: New Construction Classroom Wings
*
Sitework: Fire Department Connection (FDC) re-route - occur June 26h (after school). It will be in front of the entry of the school.South wall of Admin Counselor demo June 26th

Phase 1A/Gymnasium
Fire Sprinkler Rough In was completed. Test of entire system will be done later, but testing of Gym occurring this week.
HVAC Rough In was completed.
GWB Hang/Tape/Finish is ongoing; should be completed by June 20th.
Plumbing and Electrical Rough In is ongoing; should be completed next week.
Painting is ongoing.
East and West walls: Framing is done, prepped for acoustical ceiling material.
Bleachers furring is occurring.
Locker Room: Roof stripped and protected today.
Gym: Roof stripped/being stocked and protected today.
Bleachers will be delivered July 20th. Hardwood install will occur the 27th. Sand, finish coats, painting lines occurring the seal coat (three days). Mural will be done at this time. The flooring finishes is expected to be completed August 2nd.
Owner Furnished items coordinated July 26th/27th through the 30th. Scoreboard is being delivered on Thursday.

Phase 1A/Gym Lobby Addition
North Wall - Exterior Wall Framing/Sheathing was completed.
Metal Roof Deck was completed.
Gym lobby slab on grade is scheduled to partially complete June 6th, remaining area will be constructed after June 26 (after school is out).

Phase 1A/Athletic Offices
Slab-On-Grade re-steel completed.
Vapor Barrier installed.
H-Stud Core Board Wall - Level 1 - is ongoing; should be completed next week.
Framing is complete
MEP Rough Wall Rough In began on June 8th and is ongoing through June 19th.
Structural slab and footing rebar being doweled in. Friday, June 9th, footings are scheduled to be poured.

Phase 1/A Mens Locker Room
Structural grout of CMU is ongoing.
Roof stripped and protected today.
Gym: Roof stripped/being stocked and protected today.
Gym lobby slab on grade is scheduled to partially complete June 6th, remaining area will be constructed after June 26 (after school is out).
Athletic office structural slab and footing rebar being doweled in. Friday, June 9th, footings are scheduled to be poured.

Phase 1/New Construction
Contractor is continuing to excavate for footings and foundations. Pouring concrete in Area 4A approx. June 29th.
Area 2 is poured out. Area 3 is almost complete for concrete pours.
Framing of first floor continues in Area 2.
Strip Stem Walls poured in Areas 4A and 4B.
North side of existing wall of Commons is underway for framing of the new openings.
Electrical duct bank is complete.

Site Work
New FDC (fire department connection) at the NE corner of the building, (South side/near counselor office). This work service won’t be done until after school is out the week of the 26th.

May 29 - June 2

  • May 22 - 26 EHS construction slab poured
  • May 22 - 26 EHS construction elevator pit dampproofed and backfilled
  • May 22 - 26 EHS construction gym hallway
  • May 22 - 26 EHS construction framing prep
  • May 22 - 26 EHS construction stem wall prep and duct bank placed

Work Description: Please note: Activities may change and are weather dependent

Phase 1A: Gymnasium: Boys Lockers: Girls Lockers and Athletic Offices

Phase 1A:
Court Inserts were delivered on Wednesday, May 31st.

Main Gymnasium:
CMU Infills completed this week.
Structural Steel install completed.
Framing and Furring of Walls and Ceiling completed.
Backing for equipment/bleachers/etc. installed.
New openings (demo) made
Electrical rough-in completed.
Fire Sprinkler and HVAC rough-in began on Tuesday, May 30th; should be completed by Friday, June 9th.
Insulation installed on Tuesday and Wednesday of this week.

Men’s Locker Room
Structural Framing Upgrades/GluLam Beam install began on May 29th, completed on Friday, June 2nd.
Red Iron installation completed.
Plumbing and Electrical rough-in completed at CMU wall locations.
Interior Wall Framing/Sheetrock prep completed.
CMU Infill and New Walls began May 30th; should be completed by Monday, June 12th.
Plumbing, Electrical, HVAC and Fire Sprinkler rough-in began on May 30th; should be completed by Monday, June 12th.
HM Door Dams installed.

Gym Lobby
Slab prep, Slab on Grade Reinforcing completed on Friday, June 2nd.

Athletic Offices
Existing MEP and Fire Sprinklers removed from West Side Wall.
Slab sawcut and removed for new footings.
Excavation for new footings/Slab on Grade completed.

Next Week:
Vapor Barrier install, Slab on Grade Placement and Finishing, Framing, and MEP rough-in in Athletic Offices.
Scoreboard scheduled to be delivered on June 5th!


Phase 1/New Construction:

Hardscape/Site Elements Demo is ongoing.

Area 2:
Wall Framing/Sheathing for first floor continues through June 16th.
Erection of Red Iron and GLBs began on June 1st.
Placement of forms for footings in 4A began this week and is ongoing. Pouring for these footings scheduled for approximately June 2nd.
Elevator pit and walls have been completed. Back fill is complete.
Damp proofing and footing drains are ongoing. All areas are being backfilled.

Area 4A/4B:
Placement of forms for footings began last week and should be completed by June 8th
Re-Steel of Footings and Stemwalls scheduled to be completed by June 7th.
Strip Footings were poured on Tuesday, June 30th.

Next Week:
Framing in Area 2 continues. Stemwalls in Area 4A scheduled for re-steeling on June 5th and 6th.

May 22 - May 26

  • May 22 - 26 EHS construction slab poured
  • May 22 - 26 EHS construction elevator pit dampproofed and backfilled
  • May 22 - 26 EHS construction gym hallway
  • May 22 - 26 EHS construction framing prep
  • May 22 - 26 EHS construction stem wall prep and duct bank placed

Work Description: Please note: Activities may change and are weather dependent

Phase 1A: Gymnasium: Boys Lockers: Girls Lockers and Athletic Offices
Phase 1: New Construction Classroom Wings
Phase 1A/Gymnasium:
Structural steel is ongoing.
Electrical and plumbing rough-in has begun.

Phase 1/New Construction:
Contractor is continuing to excavate for footings and foundations.
Slab pours occurred on May 22nd in Area 2.
Footings over-excavated and filled to grade.
Wall framing has begun in Area 2.
Electrical duct bank work is ongoing.
Placement of forms for footings in 4A began this week and is ongoing.
Pouring for these footings scheduled for approximately June 2nd.
Elevator pit and walls have been completed. Back fill is complete.
Damp proofing and footing drains are ongoing. All areas are being backfilled.

Next Week:
More over-excavation and fill, footings pour, and framing of first floor rooms!

May 23 - 31

  • May 23 - 31 EHS construction
  • May 23 - 31 EHS construction
  • May 23 - 31 EHS construction
  • May 23 - 31 EHS construction
  • May 23 - 31 EHS construction
  • May 23 - 31 EHS construction
  • May 23 - 31 EHS construction

Work Description: Please note: Activities may change and are weather dependent

Phase 1A: Gymnasium: Boys Lockers: Girls Lockers and Athletic Offices
Phase 1: New Construction Classroom Wings

Phase 1A/Gymnasium:
Structural steel is ongoing. Mechanical work and the rooftop mechanical units scheduled after school starts.
Gym sheet rock is being installed. The furring strips are being placed on top of the existing tile and will have new acoustical tile on top of the furring strips.
Epoxy floor is scheduled for July 19th.
Fire Sprinkler work is starting May 30th.
Electrical and plumbing rough-in has begun.
Gym lobby slab on grade is scheduled to partially complete June 1st, remaining area will be constructed after June 26th (after school is out).
Gym floor is scheduled at the end of June 21st, to be delivered and installed on June 27th.
Owner furnished items June 26th - June 30th including new scoreboard, divider curtain, etc. Bleachers are scheduled to be installed on July 25th.
Technology install (i.e., projection screens) will be installed the end of July.

Phase 1/New Construction:
Contractor is continuing to excavate for footings and foundations.
Concrete pours are continuing to be scheduled. Slab pour in Area 2 occurred on Friday, May 19th and Monday, May 22nd.
Glulams (beams) for Area 2 have arrived. Area 3 Glulams will be following.
Wall framing has started at Area 2.
Electrical duct bank is ongoing.
Forming of the footings for 4A is ongoing. Pouring for these footings is scheduled for approximately June 2nd.
Elevator pit and walls have been completed. Back fill is complete.
Dampproofing and footing drains are ongoing. All areas are ready for backfill.

Site Work:
New FDC (fire department connection) at the NE corner of the building, (South side/near counselor office). This work service won’t be done until after school is out.
Water line has been cut and capped.
Storm work (South and East side) was completed. This will complete the access road at Area 2.

May 15 - 19

  • May 15 - 19 EHS gym furring
  • May 15 - 19 May 15 - 19 EHS gym entryway
  • May 15 - 19 EHS locker room SOG poured
  • May 15 - 19 EHS elevator pit damp proofing
  • May 15 - 19 EHS excavation
  • May 15 - 19 EHS foundation

Work Description: Please note: Activities may change and are weather dependent

Phase 1A: Gymnasium: Boys Lockers: Girls Lockers and Athletic Offices
Phase 1: New Construction Classroom Wings

The construction access road along the West side of Area 4 has been completed.

Phase 1A/Gymnasium:Concrete/Seismic and Framing
Slab on grade completed in locker rooms.
Framing and furring along East and West walls is ongoing.
Seismic upgrades, including diaphragm blocking along East and West is occurring.
Electrical rough-in is being completed where possible. Electrical feeders to be planned the week after May 16th.
Lobby footings prep is nearly complete.
Structural steel delivered on May 15th.
CMU infills are nearly complete.

Phase 1/New Construction:
Contractor is excavating for footings and foundation.
Footings all drilled, ready for epoxy dowels.
Capillary break (6" Cap) placement on May 12th and 15th.
Additional concrete pours are scheduled for May 19th.
Footing pour on May 26th.
Additional slab on grade re-enforcement continues through May 18th

April 24 - 28

  • April  24 - 28 men's locker room at EHS
  • April  24 - 28 SOG prep and locker bases at EHS
  • April  24 - 28 gym furring and framing at EHS
  • April  24 - 28 inderslab plumbing done in men's locker room at EHS
  • April  24 - 28 footings construction work at EHS
  • April  24 - 28 strip footings construction work at EHS
  • April  24 - 28 foundation construction work at EHS
  • April  24 - 28 excavation fill to grade footings construction work at EHS
  • April  24 - 28 foundation different angle construction work at EHS

Work Description:
Please note: Activities may change and are weather dependent

Phase 1A: Gymnasium: Boys Lockers: Girls Lockers and Athletic Offices

Phase 1: New Construction Classroom Wings

Demolition:
Demo of hardscape and site elements continues.

Phase 1A/Gymnasium:
Cutting of new roof openings is ongoing.
Preparation for slab-on-grade concrete continues through Monday, May 1st.
CMU infills continuing through the first two weeks of May.
Wall and Ceiling framing and furring is ongoing.
Roof Panel Blocking was completed.

Men's Locker Room:
Preparation and reinforcing for slab-on-grade concrete continues
CMU walls and infill is ongoing.

Gym Lobby Addition
Forms for footings were placed.
Re-steeling of stemwalls was completed.

Phase 1/New Construction:
Layout footings were poured.
Over-excavation of finished footings and fill to grade continues.
Underslab plumbing and electrical were installed.
12" sub-base was completed on Monday.
Wall pre-fabs began and will continue.
Additional strip footings were poured on Tuesday.
Stemwall re-steeling was completed.

Next Week:
Stemwall damproofing begins and installation of new water lines and hydrant.

April 17 - 21

  • April  17 - April 21 construction work at EHS
  • April  17 - April 21 construction work at EHS
  • April  17 - April 21 construction work at EHS
  • April  17 - April 21 construction work at EHS
  • April  17 - April 21 construction work at EHS
  • April  17 - April 21 construction work at EHS
  • April  17 - April 21 construction work at EHS
  • April  17- April 21 construction work at EHS

Work Description:
Please note: Activities may change and are weather dependent

Phase 1A: Gymnasium: Boys Lockers: Girls Lockers and Athletic Offices

Phase 1: New Construction Classroom Wings

Demolition:
Demo of the old sanitary sewer and storm system is now continuing through next week.

Phase 1A/Gymnasium:
Backfill around footings and shotcrete walls is complete.
Cutting of new roof openings is ongoing.
Roof panel blocking was completed.
Saw cutting at the new exterior opening of the gym was completed.
Wall and Ceiling framing and furring is ongoing.
Walkway canopy has been removed.

Phase 1/New Construction
Underslab MEP was completed.
12" sub base was placed.
Additional footings and stem walls were poured on Thursday, April 20th.
New stem wall forms are being placed.
Finished footings were overexcavated and filled to grade.

April 10 - 14

  • April  10 - April 14 construction work at EHS
  • April  10 - April 14 construction work at EHS
  • April  10 - April 14 construction work at EHS
  • April  10 - April 14 construction work at EHS
  • April  10 - April 14 construction work at EHS
  • April  10 - April 14 construction work at EHS
  • April  10 - April 14 construction work at EHS

Work Description:
Please note: Activities may change and are weather dependent

Phase 1A: Gymnasium: Boys Lockers: Girls Lockers and Athletic Offices

Phase 1: New Construction Classroom Wings

Overall:
With the heavy rains over the last week, Forma has done an excellent job of keeping the construction site safe and dry, with grading and moisture control.

Demolition:
Demo of the old sanitary sewer and storm system is scheduled to be completed by Friday, April 14th.

Phase 1A/Gymnasium:
Footing Prep/Concrete
Forms for interior footings (shear walls) were completed in the Gym and Athletic Locker areas, with rebar/steel placed. Concrete was poured on Tuesday, April 4th.
* Shotcrete Stemwalls were poured
* Strip footings poured.
* CMU infills were completed.
* Excavation for underslab plumbing continues.
* Wall, ceiling framing and wood stud furring has begun.

Phase 1/New Construction:
Storm system installation continues through next week. Underslab MEP continues.

April 3 - April 7

  • April  3 - April 7 batter board construction work at EHS
  • April  3 - April 7 sewer demo construction work at EHS
  • April  3 - April 7 staging area 2construction work at EHS
  • April  3 - April 7 staging area 3construction work at EHS
  • April  3 - April 7 staging area construction work at EHS
  • April  3 - April 7 strip footings construction work at EHS
  • April  3 - April 7 steeling shear wall construction work at EHS

Work Description:
Please note: Activities may change and are weather dependent

Phase 1A: Gymnasium: Boys Lockers: Girls Lockers and Athletic Offices

Phase 1: New Construction Classroom Wings

Demolition:
Demo of the old sanitary sewer and storm system is scheduled to be completed by Friday, April 14th.

AG Bathrooms:
The AG bathrooms are nearing completion.
Toilet accessories have been installed.
The final mechanical and building inspections occurred this week, and the temporary fence near the AG building is being removed shortly.
The partitions between the stalls are scheduled to be delivered in two weeks. In lieu of placing a temporary partition, we will wait to open the AG Bathrooms after the final one is delivered and installed.

Phase 1A/Gymnasium:
Footing Prep/Concrete:
Forms for interior footings (shear walls) were completed in the Gym and Athletic Locker areas, with rebar/steel placed. Concrete was poured on Tuesday, April 4th.
Shotcrete wall was re-steeled.
CMU infills should be completed by April 14th.
Excavation for underslab plumbing began on Thursday, April 6th.
Wall, ceiling framing and wood stud furring begins next week.

Phase 1/New Construction:
The staging/laydown area was completed this week.
The re-route of the sanitary sewer will be completed today.
Storm system installation continues through next week.
Strip footings were poured on Tuesday, with footings for stem walls being poured on Friday.
Underslab MEP began on Wednesday.
The building Pre-Fab Deck will be finished by Tuesday, April 11th.
The batter boards go up today!
Next week: Pre-Fab wall installation begins.

March 27 - March 31

  • March  27 - March 31 construction work at EHS
  • March  27 - March 31 construction work at EHS
  • March  27 - March 31 construction work at EHS
  • March  27 - March 31 construction work at EHS

Work Description:
Please note: Activities may change and are weather dependent

Phase 1A: Gymnasium: Boys Lockers: Girls Lockers and Athletic Offices
Phase 1: New Construction Classroom Wings

Demolition:
The majority of the exterior demolition is complete. There are smaller areas that will continue including some of the outdoor canopies as project progresses.

AG Bathrooms:
The AG bathrooms are nearing completion. Tile complete. Wall FRP will be installed Monday next week. Toilet partitions will have temporary partitions installed until the final partitions will be delivered. Toilet partitions are a long lead time. It will be open for use in mid-April!

Phase 1A/Gymnasium:
Demolition:
Roof work will be coordinated with demolition at the roof. Cleanup of gymnasium demolition is complete. Men’s locker room is complete. Saw cutting complete in locker room.

Footing Prep:
Gym and Athletic Locker Area interior footings are being excavated for shear walls.
Rebar/steel placement is ongoing. Concrete is tentatively scheduled to be placed March 24th.

Concrete:
Resteel delivery is expected on Friday.
Glue Lams will be delivered April 10th.
Shotcrete placement for many of the interior walls will start to occur first week in April.

Phase 1/New Construction
Removal of hardscape is complete. Contractor is excavating for footings and foundation. Footings all drilled, ready for epoxy dowels. Concrete placement is scheduled for the week of March 27 through 31st. Concrete shotcrete is planned for April 10th.
Forma will start excavating for utility work.
CMU wall infills scheduled for week of March 27th through 31st.
Walls will start to be framed horizontally starting mid May. Shortly thereafter, they will be vertical.

March 24 - April 7

  • March 24 - April 7 construction work at EHS

  • March 24 - April 7 construction work at EHS
  • March 24 - April 7 construction work at EHS
  • March 24 - April 7 construction work at EHS
  • March 24 - April 7 construction work at EHS
  • March 24 - April 7 construction work at EHS

Work Description:
Please note: Activities may change and are weather dependent

Phase 1A: Gymnasium, Boys Lockers, Girls Lockers and Athletic Offices

Phase 1: New Construction Classroom Wings

Demolition:
Some of the exterior canopies are still to be demolished as project progresses.

AG Bathroom: Almost complete! Planning on be open the week of April 10th!

Phase 1A/Gymnasium:
Main Gymnasium:
Ceiling Demo completed. Old roof framing has been removed and reframed to match the existing roof framing. Concrete floor has been sawcut for new court inserts.

Men's Locker Room:
The lockers and selected walls have been removed from the Men's Locker Room. Concrete has been removed and preparation for new footings and underslab for plumbing has begun.

Gym Lobby and Hallway:
Selected demolition has been completed in this area. Excavation done and forms for new wall footings have been laid.

Phase 1/New Construction:
The contractor has been busy placing footing forms and rebar placed.
Footing and foundation concrete was poured Friday!!

Phase 0/Closeout:
Flooring has been completed along the Cyclorama Wall in the video editing area (Green Room).
HVAC motor has been replaced and balancing of the system ongoing.
Ongoing work is needed for the controls for lighting and heat.

March 1 - March 31

  • March 1 - 30 construction work at EHS

  • March 1 - 30 construction work at EHS
  • March 1 - 30 construction work at EHS
  • March 1 - 30 construction work at EHS

Work Description:
Please note: Activities may change and are weather dependent


Phase 1A: Gymnasium: Boys Lockers: Girls Lockers and Athletic Offices

Phase 1: New Construction Classroom Wings

Site Set Up:
Forma Construction has done a great job keeping the construction area safe, secure and separate from kids. We know the construction is an impact and the students, staff and community have been amazing!

Demolition:
The majority of the exterior demolition is complete. There are smaller areas that will continue including some of the outdoor canopies as project progresses.

AG Bathrooms:
The AG bathrooms are nearing completion. We are expecting lighting to arrive at the end of the month and remaining finishes. The District invested in a long-term solution to support the kids in the future. In lieu of providing temporary bathrooms, the District invested in upgrading the existing bathrooms in the AG. It will be open for use in mid-April!

Phase 1A/Gymnasium:
*
Demolition
Gym interior demolition is complete. Interior Locker Room demolition is ongoing. The District Technology Staff and Forma Construction have done a great job to disengage existing systems from the demolition work. It is a process for a large campus which is fully occupied! Nice job Forma.

* Footing Prep
Gym and Athletic Locker Area interior footings are being excavated for shear walls. Rebar/steel placement is ongoing. Concrete is tentatively scheduled to be placed March 24th.

* Concrete
Shotcrete placement for many of the interior walls will start to occur first week in April.

Phase 1/New Construction
Removal of hardscape is complete. Contractor is excavating for footings and foundation. The week of the 27th, Forma is tentatively planning for utility prep / underground electrical and plumbing.

January 20 - February 6

  • January 20 - February 6 construction work at EHS
  • January 20 - February 6 construction work at EHS
  • January 20 - February 6 construction work at EHS
  • January 20 - February 6 construction work at EHS
  • January 20 - February 6 construction work at EHS
  • January 20 - February 6 construction work at EHS
  • January 20 - February 6 construction work at EHS

High School Phase 0 (Portables and Building 1000)
Work Description by Neeley Construction

Move In and Continuing:
Thank you for your patience! We can’t thank staff and faculty enough for their patience.

Culinary Arts Room is wrapping up and we start this week to provide inspections from all of the related departments and jurisdictions.

Punchlist is ongoing and a very detailed and specific list of items has been sent to the General Contractor to be fixed. It will take time, but each item will be addressed properly.

Controls:
The automatic controls of the lighting and heat. It is controllable currently, but the automatic DDC based controls is up and working and we are fine tuning it currently.

High School Renovation and Addition
Work Description by Forma Construction:
Schedule:
Construction trailers are set up, furnished, power, stairs and connected to internet. Vault work is completed. Phase 1 demo has started. Phase 1A will start mid-February. More detail on Phase 1A schedule next week.

AG building bathroom improvements the District has been planning. Temporary bathrooms have been set up to support the AG building remodel. We will start the bathroom improvements on the 30th. Temporary bathrooms will be ongoing until end of February.

Commons space:
Thursday after school at 3pm additional work at the commons wall.

Demo:
Monday! Building 100 will be removed on Monday. Typically, the demo and haul off of the material takes a week. Starting the following Monday, February 6th, building 200 will commence demolition. Building 300 will follow as well. Demo for the courtyard area is tentatively scheduled for February 13th.

Abatement:
Building 300 ongoing.

Systems Work Ongoing:

  • Trench work and data/fiber installation ongoing.
  • Fire Alarm work is being coordinated. It is being rerouted so that the Buildings 100, 200 and 300 are taken off line. That work has been ongoing this week in preparation for Monday’s demolition.

January 6 - January 20

  • January 6 - 20. classroom move in work at EHS
  • January 6 - 20. classroom move in work at EHS
  • January 6 - 20. classroom move in work at EHS
  • January 6 - 20. classroom move in work at EHS

High School Phase 0 (Portables and Building 1000)
Work Description by Neeley Construction
Move In:
We have moved in to all areas except for the Culinary Arts and Cyclorama Green Room. Thank you for your patience! We could not have done it without the dedication of the entire high school staff - especially of Jill Burnes, Pete French and the entire Technology Team. Thank you!

Controls:
The lighting and mechanical control work will be set up and commissioned starting Monday January 16th. It will take another few weeks to completely tie in with all of the controls.

Continuing Work:
Culinary hood coordination is the most intensive with multiple trades involved.

High School Renovation and Addition
Work Description by Forma Construction
Schedule:
As you can see, fencing is up, construction trailers are up and prep for abatement and demolition of the 100, 200 buildings is starting!

The largest impact to the high school is the construction wall to be constructed in the commons. It will be completed in sections, with the largest section to be constructed on January 16th. This will be an exciting time for everyone and will be a transition!

Next Thursday and Friday, there will be an auger drill between the existing portables and North of the AG Building. It will have fencing around it and will be removed Friday. It is the infiltration monitoring used for the project.

Work ongoing:
Trench work and data/fiber installation ongoing. Fire Alarm work is being coordinated.

December 15 - January 2, 2017

  • photo of November 18 - December 2 work at EHS
  • photo November 18 - December 2  work at EHS
  • photo of November 18 - December 2 work construction work at EHS
  • photo of November 18 - December 2  work construction work at EHS

Work Description by Neeley Construction
Finishes:
Casework install complete in many of the classrooms. Flooring complete in Photo Classroom 1005. Flooring scheduled for remaining spaces. Culinary Room, Video, Sound Classroom has casework installed. Paint ongoing. Ceiling tiles scheduled over break.

Site/Underground Work:
Prep for sidewalks not complete. Temperature has been too low for asphalt install.

Portables:
Power is up on the portables! Data connections are being scheduled.

Move In:
Contractor cleanup is occurring. Various classrooms are moving over break starting on December 21st - January 2nd.
Transition:
Neeley Construction will be completing their scope of the High School remodel work in December. Over December break, Enumclaw School District will be partnering with with Forma Construction for the overall High School Expansion and Renovation.

High School Renovation and Addition
Construction Activities for December

Work Description by Forma Construction:
Move Schedule:
December 19th evening movers will commence in the Admin area.
December 21st and 22nd and 23rd movers will continue and expect to be completed.

Forma Construction:
Forma is on campus starting Wednesday, December 21st. We are extremely excited to be working closely with Forma Construction who has extensive school experience on an occupied campus.

Work during December:
Trench work and data/fiber installation

EHS trench plan smaller size

EHS site plan smaller

November 18 - December 2

  • photo of November 18 - December 2 work at EHS
  • photo November 18 - December 2  work at EHS
  • photo of November 18 - December 2 work construction work at EHS
  • photo of November 18 - December 2  work construction work at EHS

Work Description:
Framing:
Interior wall framing is complete.
Insulation and gypsum board is ongoing.
Mechanical equipment is ongoing.
Casework mock up complete.

Site/Underground Work:
Completing the electrical and vault work is weather dependent.
Path for sidewalks are complete.

Overall Schedule:
West side of 1000 to be complete at the end of November.
Culinary Room will be complete in December.

Transformers:
Transformers arrived. Install to include a shut down over a weekend. To be scheduled.

Panel Replacement:
November 22/23 are the tentative switch over dates.


High School Renovation and Addition
Construction Activities for November and December

Move Schedule:
Staff Packing is ongoing currently. Boxes have arrived!
December 19th evening movers will commence in the Admin area.
December 21st - 23rd movers will continue and expect to be completed.

More scheduling information will be updated as we start working closely with Forma Construction. Forma will start work including fencing and courtyard infrastructure work December 21st. Forma will mobilize January 9th, 2017!

November 10 - November 23

  • photo of November 10 - 12 work at EHS
  • photo of November 10 - 12 work work at EHS
  • photo of November 10 - 12 work construction work at EHS
  • photo of November10 - 12 work construction work at EHS
  • photo of November 10 - 12 work construction work at EHS

Work Description:
Framing
Interior wall framing is complete.
Insulation in the walls is ongoing.
Gypsum board (except Culinary Room) is ongoing. (West side).
Mechanical equipment is ongoing.
Casework mock up complete.

Site/Underground Work
Completing the electrical and vault work is weather dependent.
Transformer delivery is expected any day.
Contractor will place the transformer over a weekend or a no school day.
Path for sidewalks is complete.

Overall Schedule
West side of 1000 to be complete at the end of November.
Culinary Room will be complete in December.

High School Renovation and Addition
Construction Activities for November

Welcome Forma Construction! We are happy to have Forma Construction partnering with Enumclaw School District for the High School Renovation and Addition. www.formacc.com

More scheduling information will be updated as we start working closely with Forma.

November 3 - November 17

  • photo of November 3 - 17 portable work at EHS
  • photo of November 3 - 17 portable work at EHS
  • photo of November 3 - 17 construction work at EHS
  • photo of November 3 - 17 construction work at EHS
  • photo of November 3 - 17 construction work at EHS
  • photo of November 3 - 17 construction work at EHS

High School Phase 0
Work Description:
Framing
Rough in in the framing for electrical and plumbing is ongoing.
Insulation in the walls has started.
Gypsum Board will begin to be hung (West side).
Mechanical equipment is ongoing.

Site/Underground Work
Electrical vault and replacement is ongoing.
Completing the electrical and vault work is weather dependent.
Prep for sidewalks are completed for the portables pathways.
Asphalt is scheduled in two weeks and weather dependant.

October 13 - October 21

  • photo of October 13 - 21 construction work at EHS
  • photo of October 13 - 21 construction work at EHS
  • photo of October 13 - 21 construction work at EHS
  • photo of October 13 - 21 construction work at EHS
  • photo of October 13 - 21 construction work at EHS
  • photo of October 13 - 21 construction work at EHS

High School Phase 0
Work Description:
Site
Asphalt work complete.
Fire lane work and access (for electrical vault and conduit placement) is ongoing.

Framing
Framing is near complete.
Rough in in the framing for electrical and plumbing has started. Insulation will start after rough in complete.
Gypsum Board will begin to be hung (West side).
Beams will be replaced at mezzanine.
Truss joist replacement for the mechanical mezzanine/equipment is ongoing.

Site/Underground Work
Electrical vault and replacement is ongoing. Vaults will be placed this week.

October 6 - October 13

  • photo of October 6 - 13 construction work at EHS
  • photo of October 6 - 13 construction work at EHS
  • photo of October 6 - 13 construction work at EHS
  • photo of October 6 - 13 construction work at EHS
  • photo of October 6 - 13 construction work at EHS

High School Phase 0
Work Description:

Site/Grease Interceptor:
Asphalt around the road work this week.

Fire lane work and access will be complete by the end of the October.

Concrete/Framing:
Concrete pour complete October 5th - Great milestone!

Shear wall and hold down inspection complete.

Framing inspection is ready.

Gypsum Board will begin to be hung next week (West side).

Shoring occurring next week for mezzanine floor. Beams will be replaced.

Truss joist replacement for the mechanical mezzanine/equipment over the next two weeks.

Site/Underground Work:
Electrical vault and replacement is ongoing. Vaults will be placed this week.

September 28 - October 6

  • photo of September-October 6 construction work at EHS
  • photo of September-October 6 construction work at EHS
  • photo of September-October 6 construction work at EHS
  • photo of September-October 6 construction work at EHS
  • photo of September-October 6 construction work at EHS

High School Phase 0
Work Description:

Grease Interceptor:
Commencing this week. Inspection next week. Concrete sidewalk will be replaced in approx. 10 days. North access will be open by September 30th.

Portables near Tennis Courts:
To be placed on September 29th/30th.

Culinary Arts/1000:

     * Concrete slab infill occurring next week.

     * Wall framing will be complete September 27th and insulation placement will commence after. Hollow metal door frames will be placed September 28th.

Mezzanine:
Structural upgrades will commence the 28th for the mezzanine floors.

September 14 - September 30

  • photo of September work at EHS 1000 building construction
  • photo of September work at EHS 1000 building construction
  • photo of September work at EHS 1000 building construction
  • photo of September work at EHS 1000 building construction

 

Grease Interceptor:
Commencing during this time frame and inspection will also occur. Concrete sidewalk will be replaced. Access to the north will be open by September 30th.

Portables near Admin:
Portables to be placed and jointed September 29th-30th.

Portables near Tennis Courts:
To be placed on September 29th-30th.

Culinary Arts/1000:
Concrete slab infill occurring during this time frame, starting approximately September 21st. Wall framing will be complete September 27th and insulation placement will commence after. Hollow metal door frames will be placed September 28th.

Mezzanine:
Structural upgrades will commence the 28th for the mezzanine floors.

Badges:
Neeley Construction has created lanyards with names to indicate construction crew on campus.


September 9 - September 16

Enumclaw High School - Phase 0

Work Description:

Sitework and Portables:
Final placement of the North portables will be placed the week of the 19th
The trenching from the North to the South will commence this month. This will take approx. three weeks for trenching/conduit placement and backfill.

Building 1000:
Footings and underfloor plumbing ongoing. Rebar is being placed to prep for concrete placement.
Grease Interceptor work will be ongoing for three weeks (at North entry).
Electrical underground work ongoing.
CMU infill is completed.

Parking & Access:
Parking around the fire lane will be continued to be closed off.

August 24 - September 7, 2016

  • photo of prep work for portables behind District Office
  • photo of portables in EHS parking lot
  • photo of underfloor work at EHS 1000 building
  • photo of underfloor work at EHS 1000 building
  • photo of relocation of structural walls at EHS 1000 building
  • photo of relocation of structural walls at EHS 1000 building

High School Phase 0

Work Description:

Work is focused on the site work for the southern portables.

Portables stored in the SE gravel parking lot
South portables will be placed the first week of school and likely be ready for use in October
Other portables will be placed but some will remain in the parking area for a few weeks

Interior Work

Footings and underfloor plumbing still being installed.
Structural walls are being relocated with temporary support.

Parking & Access

Parking for the Autoshop caged area will not be available
Parking around the fire lane will be closed off
Parking will be routed to the overflow Gravel Parking next to the tennis courts

July 18 - July 29, 2016

  • EHS demolition
  • EHS demolition
  • EHS demolition
  • EHS demolition
  • EHS demolition
  • EHS demolition

High School Phase 0

Thank you for your patience while we clarify access for safety and security!

Work Description:

* Demolition is nearing completion

* Slab removal is ongoing and almost ready for underground rough in

* Erosion control will start soon

* Electrical, Mechanical, Plumbing and Fire Sprinkler rough in and framing will start next week

* Utility trenching will start the 27th and access will be impacted

Changes to Access:

* Parking for the Autoshop caged area will not be available

* Parking around the Fire Lane will be closed off

* Parking will be routed to the Overflow Gravel Parking next to the tennis courts

June 28, 2016

  • BDE portable moves to EHS

  • BDE portable placed at EHS

Enumclaw High School Phase 0

In preparation of the remodel and additions at the High School campus, we are completing some utility and upgrades inside and outside.

Neeley Construction is onsite helping complete the work that includes: utility trenching, mechanical upgrades, electrical upgrades, renovation of Building 1000, and the placement of all of the portables. The portables will provide temporary classrooms for students during the Construction Project at the High School.

The portables will be set and ready for student occupancy at the beginning of the 2016-2017 school year. The remodeled 1000 Building will be ready for student use after October 31st.


Enumclaw High School Phase 1 and 2

NAC Architects are continuing the design, permitting and planning required for the High School Addition and Modernization.

Architectural Renderings

Virtual Tour - Most devices and computers will work for viewing; however we recommend you view it using the Google Chrome browser because it didn’t work using Internet Explorer 11 on a couple computers we tested. Use your mouse to scroll through or a mobile device to view in virtual reality (FYI - the opening image may be the floor so move your mouse or phone up).