Construction Updates for Enumclaw High School

October 22 - 26

Phase 1A: Gymnasium, Men’s Lockers, Gym Hallway and Lobby Addition
Phase 1B: Auxiliary Gymnasium Remodel
Phase 1C: Existing School Exterior Finishes
Phase 1: New Construction Classroom Wings
Phase 2A: Demo Old Library, 400 & 600 Buildings; New Construction Music and Health/PE Addition

Initial Sitework & Building Demolition - Building Demolition Begins October 29th!

  • Mobilize has begun.
  • Library Building Abatement has begun and is ongoing.
  • Building 400 Abatement has begun and is ongoing.
  • Walkway Canopies Safed Off for Demo.
  • Re-routing of Fire Alarm prior to 400 Building Demo has begun and is ongoing.

Phase 2/New Construction:
Area 5

  • Layout and Excavation for Footings begins November 19th!

 

Click the dates below to view previous construction updates:

October 15 - October 19

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition
Phase 1B: Auxiliary Gymnasium Remodel
Phase 1C: Existing School Exterior Finishes
Phase 1: New Construction Classroom Wings
Phase 2A: Demo Old Library, 400 & 600 Buildings; New Construction Music and Health/PE Addition

Initial Sitework & Building Demolition - Building Demolition Begins October 29th!
TESC Measures in Place.
Construction Entrance and Temporary Road Complete
Buildings Cleaned Out and Safed Off for Abatement.
Walkway Canopies Safed Off for Demo.
Re-routing of Fire Alarm prior to 400 Building Demo has begun and is ongoing.

Next Week:
MOBILIZE!
Library Building Abatement.
Building 400 Abatement.

Phase 2/New Construction:
Area 5
Layout and Excavation for Footings begins November 19th!

October 1 - October 5

  • October 1 - 5, 2018 EHS construction photos
  • October 1 - 5, 2018 EHS construction photos
  • October 1 - 5, 2018 EHS construction photos
  • October 1 - 5, 2018 EHS construction photos
  • October 1 - 5, 2018 EHS construction photos
  • October 1 - 5, 2018 EHS construction photos
  • October 1 - 5, 2018 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1B: Auxiliary Gymnasium Remodel

Phase 1C: Existing School Exterior Finishes

Phase 1: New Construction Classroom Wings

Phase 2 work begins October 15th!

Deliveries:
Commons Courtyard Gates
Residential Appliances
Owner Furnishings - Majority
Classroom Tables
Soft Seating for Flex Spaces
New Wing Misc. - Bookcases, Stations, Etc.
Owner Furnish Appliances

Phase 1 MDF/IDF:
Owners continue their work.

Phase 1B:
All Areas Now Occupied by Staff and Students.
Area 1 - All materials removed from building; all areas ready for final cleaning; all areas ready for Ribbon Cutting.
Existing Commons/Area 3
Painting of Steel Guardrails complete.
Wall Finishes - Wainscot/Chair Rail/Etc. - Complete

Phase 1/New Construction:Delivery and Installation of Owner Provided Furnishings (Tables, Soft Seating, etc.) is complete.
Electrical Inspection is complete.
Health Re-Inspection was completed on October 4th (passed!)
Signage is complete.

Area 2
Complete Punch is ongoing.
Stair Covering installation is complete.
Final Cleaning is complete.

Area 3
Pre-Punch is ongoing.
Stair Covering installation is complete.
Complete Punch is ongoing.
Final Cleaning is complete.

Areas 4-A and 4-B
Pre-Punch is complete.
Complete Punch is ongoing.
Final Cleaning will be completed by Monday, October 8th.

Building Perimeter and Commons Plaza
Mortar Set Paver installation is complete.
Patch Paving at East Drive is complete.
Landscaping and Hydroseeding is scheduled to be completed by Friday, October 12th.
Commons Fence Fabric installation is complete.
Site Furnishing installation is scheduled to be completed by Monday, October 8th.
Light Pole Installation is complete.
Hardscape Expansion Joint Caulking is scheduled to be completed by Monday, October 8th.
Phase 1B Sitework - N. Courtyard - Courtyard Fence Gate Installation is complete.

September 17 - September 21, 2018

  • September 17 - 21, 2018 EHS construction photos
  • September 17 - 21, 2018 EHS construction photos
  • September 17 - 21, 2018 EHS construction photos
  • September 17 - 21, 2018 EHS construction photos
  • September 17 - 21, 2018 EHS construction photos
  • September 17 - 21, 2018 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1B: Auxiliary Gymnasium Remodel

Phase 1C: Existing School Exterior Finishes

Phase 1: New Construction Classroom Wings

Phase 2 work begins October 15th!

Deliveries:
Owner Furnished Appliances
Classroom Furnishings - Virco
Classroom Furnishings - McDowell Craig

Phase 1 MDF/IDF: Owners continue their work.

Phase 1B:
All Areas Now Occupied by Staff and Students.

Phase 1/New Construction:
Final Inspection for Occupancy - Health - occurred on Friday, September 21st.
Delivery and Installation of Owner Provided Furnishings (Tables, Teachers Desks, Chairs, etc.) has begun,
with the majority of remaining items being delivered and installed on Monday, September 24th.

Area 2
Complete Punch is ongoing.
AV Installation is complete.
Stair Covering installation has begun and is ongoing.
Final Cleaning/Window Washing has begun and is ongoing.

Area 3
Pre-Punch is ongoing.
Stair Covering installation has begun and is ongoing.
Complete Punch is ongoing.
Final Cleaning/Window Washing has begun and is ongoing.

Areas 4-A and 4-B
Pre-Punch is ongoing.
Complete Punch is ongoing.
Final Cleaning/Window Washing has begun and is ongoing.

Building Perimeter and Commons Plaza
Irrigation installation is complete.
Landscaping is ongoing.
Courtyard Fence Fabric/Gate Install is ongoing.
Hardscape Expansion Joint Caulking is complete.
Grading for Remainder of Hardscape has been delayed by Operators Strike.

Phase 1 Mechanical/Electrical Testing and Checks - All Scheduled for Completion by September 28th.
Balancing is ongoing.
Commissioning, TAB and Func. Performance Testing is ongoing.
Electrical & LV Systems Testing is ongoing.

September 10 - September 14

  • September 10 - 14, 2018 EHS construction photos
  • September 10 - 14, 2018 EHS construction photos
  • September 10 - 14, 2018 EHS construction photos
  • September 10 - 14, 2018 EHS construction photos
  • September 10 - 14, 2018 EHS construction photos
  • September 10 - 14, 2018 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1B: Auxiliary Gymnasium Remodel

Phase 1C: Existing School Exterior Finishes

Phase 1: New Construction Classroom Wings

Phase 2 work begins October 15th!

Deliveries:
Site Guardrails/Handrails
Roof Ladders
Additional White Boards
The Correct Aux GYM Wall Pads

Phase 1 MDF/IDF:
Owners continue their work.

Phase 1B:
All Areas Now Occupied by Staff and Students.
Auxiliary Gym/Hallway, 920A & C
Correct Wall Pads installed.
Painting of remaining CFB Siding and Parapet Caps is complete.

Phase 1/New Construction:
Area 1
Installation of Flooring at Stage/Ramp/Steps is complete.

Area 2
Handrails installation is complete.
Complete Punch is ongoing.

Next Week:
Completion of AV Installation.
Stair Covering Installation.
Final Inspection for Occupancy - Health.

Area 3
Pre-Punch is ongoing.
Installation of SS Handrails is complete.
Complete Punch is ongoing.

Next Week:
Final Inspection for Occupancy - Health.

Areas 4-A and 4-B
Installation of SS Handrails is complete.
Pre-Punch is ongoing.
Final Clean - Rooms - is ongoing.

Next Week:
Final Clean - Commons Areas.
NAC Electrical, NAC Back and Complete Punch.
Final Inspection for Occupancy - Health.

Building Perimeter and Commons Plaza
Irrigation installation is ongoing.
Landscaping is ongoing.
Courtyard Fence Fabric/Gate Install is ongoing.
Hardscape Expansion Joint Caulking has begun and is scheduled for completion by September 21st.
Grading for Remainder of Hardscape has been delayed by Operators Strike.

Phase 1 Mechanical/Electrical Testing and Checks - All Scheduled for Completion by September 28th.
Balancing is ongoing.
Commissioning, TAB and Func. Performance Testing is ongoing.
Electrical & LV Systems Testing is ongoing.

September 4 - September 7

  • September 4 - 7, 2018 EHS construction photos
  • September 4 - 7, 2018 EHS construction photos
  • September 4 - 7, 2018 EHS construction photos
  • September 4 - 7, 2018 EHS construction photos
  • September 4 - 7, 2018 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1B: Auxiliary Gymnasium Remodel

Phase 1C: Existing School Exterior Finishes

Phase 1: New Construction Classroom Wings

Phase 2 work begins October 15th!

Deliveries:
Two Remaining Colley Sleeve Covers (correct covers received)

Phase 1 MDF/IDF: Owners continue their work.

Phase 1B:
All Areas Now Occupied by Staff and Students.
Auxiliary Gym/Hallway, 920A & C
1. Correct Wall Pads installed.
2. CFB Siding - East and South Elevation Upper Walls is complete.
3. CFB Siding - Painting is complete.
4. Parapet Cap installation is complete.

Phase 1/New Construction:
Area 1
Installation of Flooring at Stage/Ramp/Steps is ongoing.

Area 2
Handrails installation is ongoing.
Floor Coverings - RFT & Carpet Installation at Level 1 Common areas is complete.
Complete Punch is ongoing.

Area 3
Pre-Punch is ongoing.
Installation of SS Handrails is ongoing.
Complete Punch is ongoing.

Next Week:
Final Clean.

Areas 4-A and 4-B
Installation of SS Handrails is ongoing.
Installation of MDF at Stairwells and commons is ongoing.
Painting of MDF at Stairwells and Commons has begun and is ongoing.
Pre-Punch is ongoing.

Next Week:
Final Clean - Rooms.

Building Perimeter and Commons Plaza
Irrigation installation is ongoing.
Landscaping is ongoing.
Courtyard Fence Fabric/Gate Install is ongoing.
Grading for Remainder of Hardscape has been delayed by Operators Strike.

Phase 1 Mechanical/Electrical Testing and Checks
Mechanical Start-Up in Areas 2, 3 and 4A is ongoing.
Balancing is ongoing.
Commissioning, TAB and Func. Performance Testing is ongoing.
Electrical & LV Systems Testing is ongoing

August 27 - August 31

  • August 27 - 31, 2018 EHS construction photos

  • August 27 - 31, 2018 EHS construction photos

  • August 27 - 31, 2018 EHS construction photos

  • August 27 - 31, 2018 EHS construction photos

  • August 27 - 31, 2018 EHS construction photos

  • August 27 - 31, 2018 EHS construction photos

  • August 27 - 31, 2018 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1B: Auxiliary Gymnasium Remodel

Phase 1C: Existing School Exterior Finishes

Phase 1: New Construction Classroom Wings

Deliveries:
Steel/SS Handrails - Area 1
Site Guardrails/Handrails
Pavers
Two Remaining Colley Sleeve Covers
Phase 1 Signage

Phase 1 MDF/IDF:
Owners continue their work.

Phase 1B:
Auxiliary Gym/Hallway, 920A & C
Scoreboard/Shotclock/All Complete for School Run.
Demo and Installation of New Walkoff Mat is complete.
GWB Repair/Finishes in Hallway 920A & B is complete.
Finish Carpentry/MDF & Wood Trim is complete.

Women’s Locker Room
Final Clean is complete.
Complete Punch is ongoing.
NAC Back-Punch has begun and is ongoing.

Phase 1C:
Sealing Existing CMU is complete.

Phase 1/New Construction:
Area 1
New & Existing CMU at East & South Face - Sealed.
Installation of 3/4" AC Plywood at Stage and Steps is complete.
Installation of Steel Guardrails and Handrails in Commons.
Painting of Steel Guardrails is complete.
Installation of Flooring at Stage/Ramp/Steps is ongoing.
Pre-Punch is complete.
NAC Punch is ongoing.
Complete punch is complete.

Area 2
Handrails installation is ongoing.
Painting of MDF at Stairwells is complete.
Floor Coverings - RFT & Carpet Installation at Level 1 Common areas is ongoing.
Completion of Electrical and HVAC Trim at Linear Ceilings is complete.
NAC Architectural, Electrical and Complete Punch is ongoing.

Area 3
Installation and painting of MDF at Stairwells is complete.
Exterior Window Caulking is complete.
Pre-Punch is ongoing.
Installation of SS Handrails is ongoing.
Complete Punch is ongoing.

Next Week:
Final Clean.

Areas 4-A and 4-B
Installation of SS Handrails is ongoing.
Installation of Acoustical Linear Wood at Level 1 is complete.
Installation of Acoustical Linear Wood at Level 2 is complete.
Floor Coverings - RFT/SV and Carpet at Level 1 is complete.
Installation of MDF at Stairwells and commons is ongoing.
Pre-Punch is ongoing.
Elevator is Operational!

Next Week:
Paint MDF at Stairwells and Commons.

Building Perimeter and Commons Plaza
Irrigation installation is ongoing.
Landscaping is ongoing.
Swales at East and West is complete.
Courtyard Fence Fabric/Gate Install is ongoing.

 

Phase 1 Mechanical/Electrical Testing and Checks
Mechanical Start-Up in Areas 2, 3 and 4A is ongoing.
Balancing is ongoing.
Commissioning, TAB and Func. Performance Testing is ongoing.
Electrical & LV Systems Testing is ongoing.

August 20 - August 24

  • August 20 - 24, 2018 EHS construction photos
  • August 20 - 24, 2018 EHS construction photos
  • August 20 - 24, 2018 EHS construction photos
  • August 20 - 24, 2018 EHS construction photos
  • August 20 - 24, 2018 EHS construction photos
  • August 20 - 24, 2018 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1B: Auxiliary Gymnasium Remodel

Phase 1C: Existing School Exterior Finishes

Phase 1: New Construction Classroom Wings

Deliveries:
Steel/SS Handrails - Area 1
HM Frames & Doors w/Hardware - Area 1
Doors w/Hardware - Area 1, 4A & 4B - Level 2, Area 9 Phase 1B
Displacement Grilles
Remainder of Linear Wood Ceiling Panels
Pavers
Phase 1B Signage

Phase 1 MDF/IDF:
Owners continue their work.

Phase 1B:
Auxiliary Gym/Hallway, 920A & C
Fire Alarm Device Installation and Programming is complete.
Phase 1B Final Inspections for TCO - Electrical, Fire and Building - Complete.
Exterior CFB Siding Installation at Aux. Gym is complete.
Parapet Cap Installation at Aux. Gym is complete.
Demo and Re-Roof Aux Gym is ongoing.
Plumbing trim is ongoing.
GWB Repair/Finishes in Hallway 920A & B is ongoing.
Finish Carpentry/MDF & Wood Trim is ongoing.
Installation of Acoustical Ceiling Tile is complete.
Flooring in Hallway 920A & C is complete.

Women’s Locker Room
Fence Gates at Gas Meter (Women’s Locker Rm) is complete.
Electrical/Mechanical/Fire Trim is complete
Complete Punch has begun is ongoing.

Next Week:
NAC Back-Punch.

Phase 1C:
Sealing Existing CMU is ongoing.
Generator Startup occurred on August 22nd.

Phase 1/New Construction:
Area 1
Acoustical Wall Panel installation is complete.
Pre-Punch is ongoing.
Final Clean is complete
NAC Punch has begun and is ongoing.
Complete punch has begun and is ongoing.

Next Week:
Install Steel Guardrails & Stainless Handrails.
Paint Steel Guardrails.

Area 2
Exterior Window Caulking is complete.
Handrails installation is ongoing.
Floor Coverings - RFT & Carpet Installation at Level 1 Common areas is ongoing.
Completion of Electrical and HVAC Trim at Linear Ceilings is ongoing.
Fire Alarm Device programming is complete.
NAC Architectural, Electrical and Complete Punch is ongoing.

Area 3
AV Install is complete.
Exterior Window Caulking is ongoing.
Pre-Punch is ongoing.
Installation of SS Handrails is ongoing.
Complete Punch is ongoing.
Fire Alarm Device programming is complete.

Next Week:
Final Clean.
Install MDF at Stairwells

Areas 4-A and 4-B
Exterior Window Caulking is complete.
Acoustical Linear Wood Installation at Level 2 is complete
Installation of SS Handrails is ongoing.
Pre-Punch is ongoing.
Fire Alarm Programming is complete.
Elevator Inspection occurred on Friday, August 24th.

Next Week:
Acoustical Linear Wood at Level 1.
Elevator Operational.

Building Perimeter and Commons Plaza
Complete East Side Area 2 Grubbing for Landscape is complete.
Grade for Hardscape is complete
F/P/S Concrete Hardscape is complete
Complete Site Light Pole Standards & Electrical is complete.
Rock Swales placement is complete
Irrigation installation is ongoing.
Landscaping is ongoing.
F/P/S Concrete Hardscape at N. Courtyard is complete.
Landscaping - Topsoil/Hydroseed at N. Courtyard is complete.
Courtyard Fence Fabric/Gat Install has begun and is ongoing.
Temp Fencing has been reconfigured at S. Courtyard.
Painting of South and West Side of Area 9 is complete.

Phase 1 Mechanical/Electrical Testing and Checks
Mechanical Start-Up in Areas 2, 3 and 4A is ongoing.
Balancing is ongoing.
Commissioning, TAB and Func. Performance Testing is ongoing.
Electrical & LV Systems Testing is ongoing.
AHU for Areas 4A and 4B is ON and Moving Air.

August 13 - August 17

  • August 13 - 17, 2018 EHS construction photos
  • August 13 - 17, 2018 EHS construction photos
  • August 13 - 17, 2018 EHS construction photos
  • August 13 - 17, 2018 EHS construction photos
  • August 13 - 17, 2018 EHS construction photos
  • August 13 - 17, 2018 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1B: Auxiliary Gymnasium Remodel

Phase 1C: Existing School Exterior Finishes

Phase 1: New Construction Classroom Wings

Deliveries:
Steel/SS Handrails - Area 1
Roof Ladders
Remainder of Linear Wood Ceiling Panels
Window Treatments - Metal Blinds
Pavers
Aux Gym Wall Pads and 2 Remaining Volley Sleeves
Window Treatments - Roller Shades

Phase 1 MDF/IDF:
Owners continue their work.

Phase 1B:
Auxiliary Gym/Hallway, 920A & C
Exterior CFB Siding at Auxiliary Gym is complete.
Demo and Re-Roof Aux Gym is ongoing.
Plumbing trim is ongoing.
GWB Repair/Finishes in Hallway 920A & B is ongoing.
Finish Carpentry/MDF & Wood Trim is ongoing.
Installation of Acoustical Ceiling Grid and Trim in Hallways 920 A & C has begun and is ongoing.
Installation of Acoustical Ceiling Tile has begun and is ongoing.
Wall Pad Installation is complete.
Electrical Trim is complete.
Flooring in Hallway 920A & C has begun and is ongoing.

Women’s Locker Room
Exterior Painting - New and Existing - is complete.
Pre-Punch is complete.
Final Clean is complete.
NAC Punch is complete.
Complete Punch has begun and is ongoing.

Next Week:
NAC Back-Punch.

Boiler Room
Boiler Room Equipment Installation and Buildout is complete.
Boiler started up.

Phase 1C:
Exterior Painting is complete.
Sealing Existing CMU is ongoing.
Rough-In and Life Safety is complete.

Phase 1/New Construction:
Area 1
Taping required for Acoustical Wall Panels is complete.
Acoustical Wall Panel installation has begun and is ongoing.
Flooring Installation at Stage/Ramp/Steps is complete.
Pre-Punch has begun and is ongoing.

Next Week:
Install Steel Guardrails & Stainless Handrails.
Paint Steel Guardrails.

Area 2
Exterior Window Caulking is ongoing.
Handrails installation is ongoing.
Window Treatments installed.
Floor Coverings - RFT & Carpet Installation at Level 1 Common areas is ongoing.
Pre-Punch and Final Cleaning is complete.
Completion of Electrical and HVAC Trim at Linear Ceilings is ongoing.
Fire Alarm Device installation is complete.
NAC Architectural, Electrical and Complete Punch is ongoing.

Next Week:
Fire Alarm Programming.

Area 3
Window Treatments installed.
Exterior Window Caulking is ongoing.
Re-installation of Acoustical Ceiling Tiles is complete.
Pre-Punch is ongoing.
Installation of SS Handrails is ongoing.
NAC Architectural and Electrical Punch complete.
Complete Punch has begun and is ongoing.
Fire Alarm Device Installation is complete.

Next Week:
Final Clean of corridors.
Fire Alarm Programming.

Areas 4-A and 4-B
Exterior Window Caulking is ongoing.
Floor Coverings - RFT & Carpet at Level 1 and 2 is complete.
Finish Carpentry/MDF and Wood Trim installation is ongoing.
Installation of SS Handrails is ongoing.
Pre-Punch is ongoing.
Final Clean of Rooms is complete.
Window Treatments installed.
Electrical Trim Installation is complete.

Next Week:
Fire Alarm Programming.
Completion of AV Install.

Building Perimeter and Commons Plaza
Rock Swales are complete.
Concrete Weir Walls poured on August 3rd.
Irrigation installation is ongoing.
Landscaping is ongoing.
Courtyard Fence Post Installation is complete.
Grading for remainder of hardscape is complete.
Clean Up - Dirt Piles removed.
Grading for New Temp Walking Paths is complete.
Temp Cold Patch Paths placement is complete.

Next Week:
Re-configure Temp Fencing

Phase 1 Mechanical/Electrical Testing and Checks
Mechanical Start-Up in Areas 2, 3 and 4A is ongoing.
Balancing is ongoing.
Commissioning, TAB and Func. Performance Testing is ongoing.
Electrical & LV Systems Testing is ongoing.
AHU for Areas 2 and 3 is ON and Moving Air.

Next Week:
AHU for Areas 4A and 4B ON and Moving Air.

August 6 - August 10

  • August 6 - 10, 2018 EHS construction photos
  • August 6 - 10, 2018 EHS construction photos
  • August 6 - 10, 2018 EHS construction photos
  • August 6 - 10, 2018 EHS construction photos
  • August 6 - 10, 2018 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1B: Auxiliary Gymnasium Remodel

Phase 1C: Existing School Exterior Finishes

Phase 1: New Construction Classroom Wings

Deliveries:
HM Frames & Doors w/Hardware - Area 1
Doors w/Hardware - Area 9 Phase 1B
Doors w/Hardware - Area 4A and 4B Level 2
Window Treatments - Metal Blinds

Owner Furnished Item
Existing Commons/Cafeteria Chairs
Science Tables

Phase 1 MDF/IDF:
Owners continue their work.

Phase 1B:
Auxiliary Gym/Hallway, 920A & C
Exterior CFB Siding at Auxiliary Gym is ongoing.
Demo and Re-Roof Aux Gym is ongoing.
Plumbing trim is ongoing.
Drinking Fountain Alcove Wall Tile is complete.
GWB Repair/Finishes in Hallway 920A & B is ongoing.
Finish Carpentry/MDF & Wood Trim is ongoing.
Installation of Acoustical Ceiling Grid and Trim in Hallways 920 A & C has begun and is ongoing.
Installation of Acoustical Ceiling Tile has begun and is ongoing.

Next week:
Flooring in Hallway 920A & C

Women’s Locker Room
Plumbing Trim is complete.
Electrical/Mechanical/Fire Trim is complete
Exterior Painting - New and Existing - is ongoing.
Casework Installation is complete.
Pre-Punch has begun and is ongoing.

Next Week:
Final Clean.
NAC Punch.
Complete Punch.

Boiler Room
Boiler Room Equipment Installation and Buildout is ongoing.
Hydronic Lines Filled.
Startup of Pumps occurred on August 7th.
Startup of Hot Water Tanks occurred on August 9th and 10th.
Startup of AHU 901 occurred on August 7th.

Next week:
Boiler Startup

Phase 1C:
Exterior Painting is complete.
Sealing Existing CMU is ongoing.
Rough-In and Life Safety has begun and is ongoing.

Phase 1/New Construction:
Area 1
Reinstallation of Acoustical Ceiling Tiles in Commons/Area 3 has been delayed by delivery.
Pre-Punch has begun and is ongoing.

Next Week:
Installation of Flooring at Stage/Ramp/Steps

Area 2
Exterior Window Caulking has begun and is ongoing.
Handrails have been delivered; installation is ongoing.
Acoustical Linear Wood installation at Levels 1 and 2 is complete
Floor Coverings - RFT & Carpet Installation at Level 1 Common areas is ongoing.
Pre-Punch and Final Cleaning is ongoing.
Completion of Electrical and HVAC Trim at Linear Ceilings is ongoing.
NAC Architectural, Electrical and Complete Punch is ongoing.

Next Week:
Completion of Fire Alarm Device Installation.
Window Treatments.

Area 3
Acoustical Ceiling Tile/Linear Wood installation at Levels 1 and 2 is complete.
Painting of South Wall & Soffit in Existing Commons is complete.
Exterior Window Caulking has begun and is ongoing.
Re-installation of Acoustical Ceiling Tiles is complete.
Installation of Acoustical Wall Panels is complete.
Patch Back Existing Acoustical Ceiling Grid is complete.
Pre-Punch is ongoing.
Installation of SS Handrails is ongoing.
Acoustical Wall Panel Panels in Existing Commons Area 3 is complete.
Door Lite Glazing is complete.
Final Clean of Rooms is complete.

Next Week:
Final Clean of corridors.
NAC Architectural, Electrical and Complete Punch.
Window Treatments.

Areas 4-A and 4-B
Exterior Window Caulking has begun and is ongoing.
Floor Coverings - RFT & Carpet at Level 1 and 2 is ongoing.
Finish Carpentry/MDF and Wood Trim installation is ongoing.
Installation of SS Handrails is ongoing.
Doors and Hardware at Levels 2 & 1 delayed by manufacturer.
Door Lite Glasing is complete.
Pre-Punch has begun and is ongoing.

Next Week:
Completion of Fire Alarm Device Installation.
Window Treatments.

Building Perimeter and Commons Plaza
East Side Area 2 Grubbing for Landscape is complete.
Concrete Weir Walls poured on August 3rd.
Irrigation installation is ongoing.
Landscaping is ongoing.
F/P/S of remainder of Concrete Hardscape is ongoing.
Placement of Rock Swales has begun and is ongoing.
Concrete Curb and Fence Line has been placed.

Next Week:
Grading for remainder of hardscape.
Clean Up/Removal of Dirt Piles
Grading for new Temp Walking Paths
Place Temp Cold Patch Paths
Paint South & West Side of Area 9

Phase 1 Mechanical/Electrical Testing and Checks
Mechanical Start-Up in Areas 2, 3 and 4A is ongoing.
Balancing is ongoing.
Commissioning, TAB and Func. Performance Testing is ongoing.
Electrical & LV Systems Testing is ongoing.

Next Week:
AHU for Areas 2 and 3 ON and Moving Air.

July 30 - August 3, 2018

  • July 30 - August 3, 2018 EHS construction photos
  • July 30 - August 3, 2018 EHS construction photos
  • July 30 - August 3, 2018 EHS construction photos
  • July 30 - August 3, 2018 EHS construction photos
  • July 30 - August 3, 2018 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1B: Auxiliary Gymnasium Remodel

Phase 1C: Existing School Exterior Finishes

Phase 1: New Construction Classroom Wings

Deliveries:
Phase 1 Finish Veneer Panels for Built-In Benches
Hardware Needed for Storefront Doors
Doors w/Hardware - A2 L2, A3 L2, A4a and 4b L2

Phase 1 MDF/IDF: Owners continue their work.

Phase 1B:
SUBSTANTIAL COMPLETION IS SCHEDULED AS OF 8/3/2018
Auxiliary Gym/Hallway, 920A & C
Exterior CFB Siding at Auxiliary Gym is ongoing.
Demo and Re-Roof Aux Gym has begun and is ongoing.
Plumbing trim has begun and is ongoing.
Drinking Fountain Alcove Wall Tile has begun and is ongoing.
GWB Repair/Finishes in Hallway 920A & B is ongoing.
Finish Carpentry/MDF & Wood Trim is ongoing.

Athletic Storage Room
Fencing is complete
Fence Gates installed.

Women’s Locker Room
CFB Siding Installation and Replacement of Existing Corner Trim is complete.
Exterior Painting - New and Existing - is ongoing.
Casework Installation is ongoing.
Epoxy Floor installation is complete.
Plumbing Trim is complete.
Toilet Partitions and Accessory installation is complete.
Pre-Punch has begun and is ongoing.

Next Week:
Final Clean.
NAC Punch.
Complete Punch.

Boiler Room
Boiler Room Equipment Installation and Buildout is ongoing.

Phase 1C:
Exterior Painting continues as areas become available.
Sealing Existing CMU Has begun and is ongoing.
Mech/Elec/Fire RI/Connections to Phase 1.

Phase 1/New Construction:
Area 1
GWB Hang/Tape/Finish all areas is ongoing.
Wall finishes are complete.
FRL Wall Finishes and New Sheet Vinyl Flooring in Restroom 178 is complete.
Plumbing Fixtures are reinstalled.
Reinstallation of Acoustical Ceiling Tiles in Commons/Area 3 has begun and is ongoing.

Next Week:
Pre-Punch

Area 2
Handrails have been delivered; installation is ongoing.
Acoustical Linear Wood installation at Levels 1 and 2 is ongoing.
Floor Coverings - RFT & Carpet Installation at Level 1 Common areas is ongoing.
Pre-Punch and Final Cleaning is ongoing.
Swing and Glaze Exterior Storefront Doors is complete.
Completion of Electrical and HVAC Trim at Linear Ceilings is ongoing.
Door Lite Glazing is complete.
NAC Architectural, Electrical and Complete Punch has begun and is ongoing.

Next Week:
Exterior Window Caulking.

Area 3
Acoustical Ceiling Tile/Linear Wood installation at Levels 1 and 2 is ongoing.
Painting of South Wall & Soffit in Existing Commons is ongoing.
Swing and Glaze Exterior Storefront Doors is complete.
Re-installation of Acoustical Ceiling Tiles is ongoing.
Installation of Acoustical Wall Panels is ongoing.
Patch Back Existing Acoustical Ceiling Grid is ongoing.
Pre-Punch has begun is ongoing.
Installation of SS Handrails is ongoing.
Acoustical Wall Panel Panels in Existing Commons Area 3 is ongoing.

Next Week:
Final Clean.
NAC Architectural, Electrical and Complete Punch.

Areas 4-A and 4-B
Installation of Toilet Partitions and Accessories is complete.
Floor Coverings - RFT & Carpet at Level 1 and 2 is ongoing.
Finish Carpentry/MDF and Wood Trim installation is ongoing.
Installation of SS Handrails is ongoing.
Door and Hardware installation at Levels 2 and 1 is complete.
Swing and Glaze Exterior Storefront Doors is complete.
Elevator Trim & Test is ongoing.

Next Week:
Door Lite Glazing.

Building Perimeter and Commons Plaza
FRPS Concrete Runnels - Remaining poured on July 30th.
Concrete Weir Walls poured on August 3rd.
Irrigation installation is ongoing.
Landscaping is ongoing.
F/P/S of remainder of Concrete Hardscape is ongoing.

Next Week:
Rock Delivery
Rock Swales
Place Concrete Curb at Fence Line

Phase 1 Mechanical/Electrical Testing and Checks
Mechanical Start-Up in Areas 2, 3 and 4A is ongoing.
Balancing is ongoing.
Commissioning, TAB and Func. Performance Testing is ongoing.

July 23 - July 27, 2018

  • July 23 - July 27, 2018 EHS construction photos
  • July 23 - July 27, 2018 EHS construction photos
  • July 23 - July 27, 2018 EHS construction photos
  • July 23 - July 27, 2018 EHS construction photos
  • July 23 - July 27, 2018 EHS construction photos
  • July 23 - July 27, 2018 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1B: Auxiliary Gymnasium Remodel

Phase 1C: Existing School Exterior Finishes

Phase 1: New Construction Classroom Wings

Deliveries:
Ship Ladders
Linear Wood Ceiling Panels
1000 Building Ductwork

Phase 1 MDF/IDF: Owners continue their work.

Phase 1B:
SUBSTANTIAL COMPLETION IS SCHEDULED AS OF 8/3/2018
Auxiliary Gym/Hallway, 920A & B
Exterior CFB Siding at Auxiliary Gym is ongoing.
Casework Installation is complete.
Plumbing trim has begun and is ongoing.
GWB Repair/Finishes in Hallway 920A & B is ongoing.

Women’s Locker Room
CFB Siding Installation and Replacement of Existing Corner Trim is ongoing.
Exterior Painting - New and Existing - is ongoing.
Casework Installation is ongoing.
Epoxy Floor installation is ongoing.
Locker Diamond Plate Endcaps installed.
Plumbing Trim is ongoing.
Toilet Partitions and Accessory installation has begun and is ongoing.
Electrical/Mechanical/Fire Trim installation is complete.

Next Week:
Pre-Punch.
Final Clean.
NAC Punch.
Complete Punch.

Boiler Room
Boiler Room Equipment Installation and Buildout is ongoing.

Phase 1C:
Exterior Painting continues as areas become available.
Backfill for remainder of Hallway 920 is complete.
SOG preparation and pour is complete.
Wall/Roof Framing has begun and is ongoing.

Next Week:
Mech/Elec/Fire RI/Connections to Phase 1.

Phase 1/New Construction:
Area 1
Replace/Install Exterior Hardie Siding at SE Corner is complete.
Exterior Painting at East and South Face is complete.
GWB Hang/Tape/Finish all areas is ongoing.
Painting of new GWB & HM is ongoing.

Area 2
Handrails have been delivered; installation is ongoing.
Metal Siding System at N is complete.
Acoustical Linear Wood has been delivered; installation at Levels 1 and 2 is ongoing.
Floor Coverings - RFT & Carpet Installation at Level 1 Common areas is ongoing.
Pre-Punch and Final Cleaning have begun and is ongoing.
Swing and Glaze Exterior Storefront Doors is ongoing.
Completion of Electrical and HVAC Trim at Linear Ceilings has begun and is ongoing.

Next Week:
NAC Architectural, Electrical and Complete Punch begins.


Area 3
Acoustical Ceiling Tile/Linear Wood installation at Level 2 is ongoing.
Painting of South Wall & Soffit in Existing Commons is ongoing.
Swing and Glaze Exterior Storefront Doors is ongoing.
Re-installation of Acoustical Ceiling Tiles is ongoing.
Installation of Acoustical Wall Panels is ongoing.
Patch Back Existing Acoustical Ceiling Grid is ongoing.
Pre-Punch has begun and is ongoing.
Installation of SS Handrails has begun and is ongoing.
Acoustical Wall Panel Panels in Existing Commons Area 3 has begun and is ongoing.

Next Week:
Final Clean.
Acoustical Ceiling Tile/Linear Wood installation at Level 1.

Areas 4-A and 4-B
Installation of Toilet Partitions and Accessories is ongoing.
Floor Coverings - RFT & Carpet at Level 1 and 2 has begun and is ongoing.
Finish Carpentry/MDF and Wood Trim installation is ongoing.
Installation of SS Handrails is ongoing.
Door and Hardware installation at Levels 2 and 1 is now scheduled to be completed by August 2nd.
Elevator Trim & Test is ongoing.

Next Week:
Swing and Glaze Exterior Storefront Doors.
Pre-Punch

Building Perimeter and Commons Plaza
FRPS Concrete Runnels - East Runnels poured on July 25th, remaining to be poured on July 30th.
F/P/S Concrete Hardscape at Courtyard is ongoing with pours on July 25th, 26th and 27th.
Irrigation installation is ongoing.
Landscaping is ongoing.
F/P/S of remainder of Concrete Hardscape is ongoing.
Grade for Remainder of Hardscape is complete.

Phase 1 Mechanical/Electrical Testing and Checks
Mechanical Start-Up in Areas 2, 3 and 4A is ongoing.
Balancing is ongoing.
Commissioning, TAB and Func. Performance Testing is ongoing.

July 16 - July 20

  • July 16 - July 20, 2018 EHS construction photos
  • July 16 - July 20, 2018 EHS construction photos
  • July 16 - July 20, 2018 EHS construction photos
  • July 16 - July 20, 2018 EHS construction photos
  • July 16 - July 20, 2018 EHS construction photos
  • July 16 - July 20, 2018 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1B: Auxiliary Gymnasium Remodel

Phase 1C: Existing School Exterior Finishes

Phase 1: New Construction Classroom Wings

Deliveries:
Ship Ladders
Linear Wood Ceiling Panels
Homosote Panels

Phase 1 MDF/IDF:
Owners continue their work.

Phase 1B:
SUBSTANTIAL COMPLETION IS SCHEDULED AS OF 8/3/2018
Auxiliary Gym/Hallway, 920A & B
Exterior CFB Siding at Auxiliary Gym is ongoing.
Electrical Trim is complete.
GWB Repair/Finishes in Hallway 920A & B is ongoing.
Core Drill & Install Equipment Sleeves is complete.

Women’s Locker Room
CFB Siding Installation and Replacement of Existing Corner Trim is ongoing.
Exterior Painting - New and Existing - is ongoing.
Casework Installation is ongoing.
Epoxy Floor installation is ongoing.

Next Week:
Elec/Mech/Fire Trim.
Install Locker Diamond Plate Endcaps
Complete Casework.
Plumbing Trim.
Toilet Partitions and Accessories.

Boiler Room
Boiler Room Equipment Installation and Buildout is ongoing.

Phase 1C:
Exterior Painting continues as areas become available.
Backfill for remainder of Hallway 920 is complete.
SOG preparation and pour is complete.
Wall/Roof Framing has begun and is ongoing.

Next Week:
Mech/Elec/Fire RI/Connections to Phase 1.

Phase 1/New Construction:
Area 1
New Masonry Veneer at SE Corner is complete.
GWB Hang/Tape/Finish all areas is ongoing.
Painting of new GWB & HM has begun and is ongoing.

Area 2
Handrails have been delivered; installation to begin week of July 23rd.
Doors and Hardware installation at Levels 1 & 2 is complete.
Acoustical Linear Wood has been delivered; installation at Levels 1 and 2 has begun and is ongoing.
Floor Coverings - RFT & Carpet Installation at Level 1 Common areas is ongoing.
Pre-Punch and Final Cleaning have begun and is ongoing.
Swing and Glaze Exterior Storefront Doors has begun and is ongoing.

Next Week:
Completion of Electrical and HVAC Trim at Linear Ceilings.

Area 3
Acoustical Ceiling Tile/Linear Wood installation at Level 2 is ongoing.
Painting of South Wall & Soffit in Existing Commons is ongoing.
Swing and Glaze Exterior Storefront Doors has begun and is ongoing.
Installation of Doors and Hardware at Levels 2 & 1 is complete.
Re-installation of Acoustical Ceiling Tiles has begun and is ongoing.
Installation of Acoustical Wall Panels has begun and is ongoing.
Patch Back Existing Acoustical Ceiling Grid has begun and is ongoing.

Next Week:
Installation of SS Handrails (delayed by supplier).
Pre-Punch.
Acoustical Ceiling Tile/Linear Wood installation at Level 1.

Areas 4-A and 4-B
Mechanical Mezzanine Buildout - Electrical/Control is complete.
Installation of Toilet Partitions and Accessories is ongoing.
Storefront Level 2 at South End of Area 4B is complete.
Finish Carpentry/MDF and Wood Trim installation has begun and is ongoing.
Installation of SS Handrails has begun and is ongoing.
Door and Hardware installation at Levels 2 and 1 is now scheduled to be completed by July 24th.
Elevator Trim & Test is ongoing.

Next Week:
Floor Coverings - RFT & Carpet at Level 1 and 2.
Swing and Glaze Exterior Storefront Doors.

Building Perimeter and Commons Plaza
Grading West Courtyard Swale has begun is complete.
F/P/S Concrete Hardscape at Courtyard is ongoing.
Irrigation installation is ongoing.
Landscaping has begun and is ongoing.
F/P/S of remainder of Concrete Hardscape is ongoing.

Phase 1 Mechanical/Electrical Testing and Checks
Mechanical Start-Up in Areas 2, 3 and 4A is ongoing.
Balancing is ongoing.
Commissioning, TAB and Func. Performance Testing is ongoing.

July 9 - July 13

  • July 9 - July 13, 2018 EHS construction photos
  • July 9 - July 13, 2018 EHS construction photos
  • July 9 - July 13, 2018 EHS construction photos
  • July 9 - July 13, 2018 EHS construction photos
  • July 9 - July 13, 2018 EHS construction photos
  • July 9 - July 13, 2018 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1B: Auxiliary Gymnasium Remodel

Phase 1C: Existing School Exterior Finishes

Phase 1: New Construction Classroom Wings

Deliveries:
SS Handrails

Phase 1 MDF/IDF: Owners continue their work.

 

Phase 1B:
SUBSTANTIAL COMPLETION IS SCHEDULED AS OF 8/3/2018
Auxiliary Gym/Hallway, 920A & B
Roof re-coat is complete.
Exterior CFB Siding at Auxiliary Gym is ongoing.
Wood Floor Finish Cure period is complete.
Installation of Doors and Hardware is complete.
Installation of Wall Pads in Auxiliary Gym is complete.
GWB Repair/Finishes in Hallway 920A & B is ongoing.
Finish Carpentry/MDF at New HM Door Frames is complete.
Painting of MDF & Wood Trim at New HM Door Frames is complete.
Auxiliary Gym is now reopened to foot traffic.

Next Week:

Core Drill and install equipment sleeves.

Women’s Locker Room
CFB Siding Installation and Replacement of Existing Corner Trim is ongoing.
Exterior Painting - New and Existing - is ongoing.
Casework Installation has begun and is ongoing.
Epoxy Floor installation has begun and is ongoing.

Boiler Room
Boiler Room Equipment Installation and Buildout is ongoing.

Phase 1C:
Exterior Painting continues as areas become available.

FRPS Remainder of Hallway 920 Footings - pour occurred on July 11th.
Underslab Plumbing installation is complete.

Next Week:

Backfill for remainder of Hallway 920
Prep and pour of SOG
Wall/Roof Framing.

Phase 1/New Construction:
Area 1
New Storage Room Selective Demo is complete.
GWB Hang/Tape/Finish all areas has begun and is ongoing.

Next Week:
Paint new GWB & HM.

Area 2
Handrail installation continues to be delayed and is scheduled to resume week of July 16th.
Doors and Hardware installation at Levels 1 & 2 has resumed.
Metal Siding System at N is complete.
Floor Coverings - RFT & Carpet Installation at Level 1 Common areas has begun and is ongoing.

Next Week:
Window Treatments.

Area 3
Acoustical Ceiling Tile/Linear Wood installation at Level 2 is ongoing.
Painting of South Wall & Soffit in Existing Commons is ongoing.
Metal Siding System Installation is complete.
Installation of Doors and Hardware at Levels 2 & 1 is ongoing.

Next Week:
Patch Back Existing Acoustical Ceiling Grid.
Installation of SS Handrails (delayed by supplier).
Re-installation of Acoustical Ceiling Tiles.
Acoustical Wall Panels.

 

Areas 4-A and 4-B
Mechanical Mezzanine Buildout - Electrical/Control is ongoing and scheduled to be completed by July 13th.
Installation of Toilet Partitions and Accessories is ongoing.
Elevator Trim & Test has begun and is ongoing.

Next Week:
Installation of Doors & Hardware (delayed by supplier).

Building Perimeter and Commons Plaza
F/P/S Concrete Hardscape at East Area 2 and West Area 4B is complete.
Grading West Courtyard Swale has begun and is scheduled to be completed by July 10th.
F/P/S Concrete Hardscape at Courtyard is ongoing.
F/P/S Concrete Runnel pour occurred on July 12th.
Irrigation installation is ongoing.
Landscaping has begun and is ongoing.
F/P/S of remainder of Concrete Hardscape is ongoing.

Phase 1 Mechanical/Electrical Testing and Checks
Mechanical Start-Up in Areas 2, 3 and 4A is ongoing.
Balancing is ongoing.
Commissioning, TAB and Func. Performance Testing is ongoing.

July 2 - July 6

  • July 2 - July 6, 2018 EHS construction photos
  • July 2 - July 6, 2018 EHS construction photos
  • July 2 - July 6, 2018 EHS construction photos
  • July 2 - July 6, 2018 EHS construction photos
  • July 2 - July 6, 2018 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1B: Auxiliary Gymnasium Remodel

Phase 1C: Existing School Exterior Finishes

Phase 1: New Construction Classroom Wings

Deliveries:
Light Pole Standards
Doors with Hardware for Areas 2, 3 and 4

Phase 1 MDF/IDF: Owners continue their work.

Phase 1B:
SUBSTANTIAL COMPLETION IS SCHEDULED AS OF 8/3/2018
Auxiliary Gym/Hallway, 920A & B
Roof re-coat is ongoing and is scheduled to be completed by July 13th.
Exterior CFB Siding at Auxiliary Gym has begun and is ongoing.
Wood Floor Finish Cure period is now scheduled to be completed on July 8th.
Installation of Doors and Hardware continues to be delayed by delivery.
Installation of Wall Pads in Auxiliary Gym continues to be delayed by delivery.
GWB Repair/Finishes in Hallway 920A & B is ongoing.

Auxiliary Gym is scheduled to be reopened to foot traffic on July 9th.

Next Week:
Installation of Doors and Hardware (delayed by delivery).
Finish Carpentry/MDF at New HM Door Frames (following HM Install).
Painting of MDF & Wood Trim at New HM Door Frames (following HM Install).
Installation of Wall Pads in Auxiliary Gym (delayed by delivery).

Women’s Locker Room
CFB Siding Installation and Replacement of Existing Corner Trim is ongoing.
Exterior Painting - New and Existing - is ongoing.
Casework Installation has begun and is ongoing.

Next Week:
Epoxy Floors.

Boiler Room
Roof Framing/Infill is complete.
Selective Roof Demo is complete.
Roofing has begun and is ongoing.
Boiler Room Equipment Installation and Buildout is ongoing.

Phase 1B Utility Work
New Gas Meter Installed.
New Domestic and Irrigation Water Meters Installed.

Phase 1C:
Exterior Painting continues as areas become available.
Boiler/Storage Room Abatement - Interior and Roof - is complete.
Demo of Boiler/Storage Room is complete.

Next Week:
Excavation for Footings for remainder of Hallway 920.
FRPS Remainder of Hallway 920 Footings.
Underslab Plumbing.

Phase 1/New Construction:
Area 1
Work began June 25th.
New Storage Room Pre-Demo Pre-Con completed on July 5th.
New Storage Room Selective Demo has begun and is scheduled to be completed by July 9th.
Selective Demo of Restroom 178 is complete.
Installation of new Door Frame and window replacement at 220 is complete.
Installation of new Rain Leaders in Corridor 100 is complete.

Next Week:
Demo/Replace HM Jambs and Doors at 100, 100A, 101, and 101B.
GWB Hang/Tape/Finish All Areas.

Area 2
Handrail installation continues to be delayed and is scheduled to resume week of July 9th.

Next Week:
Doors and Hardware at Levels 1 & 2 (delayed by supplier).
SS Handrail Installation (delayed by supplier).
Floor Coverings - RFT & Carpet - Level 1 Commons Areas.

Area 3
AV Installation has begun and is ongoing.
Acoustical Ceiling Tile/Linear Wood installation at Level 2 is ongoing.
Painting of South Wall & Soffit in Existing Commons is ongoing.
Metal Siding System Installation at N is ongoing and scheduled to be completed by July 12th.

Next Week:
Patch Back Existing Acoustical Ceiling Grid.
Installation of Doors and Hardware (delayed by supplier).
Installation of SS Handrails (delayed by supplier).

Areas 4-A and 4-B
Mechanical Mezzanine Buildout - Electrical/Control is ongoing and scheduled to be completed by July 13th.
Finish Carpentry/MDF & Wood Trim is complete.
Storefront Level 2 at South End in Area 4B is complete.
Installation of Toilet Partitions and Accessories has begun and is scheduled to be completed by July 11th.

Next Week:
Installation of Doors & Hardware (delayed by supplier).
Elevator Trim & Test.

Building Perimeter and Commons Plaza
F/P/S Concrete Hardscape at East Area 2 and West Area 4B is complete.
Grading West Courtyard Swale has begun and is scheduled to be completed by July 10th.
F/P/S Concrete Hardscape at Courtyard is ongoing.
F/P/S Concrete Runnel installation is ongoing.
Irrigation installation has begun and is ongoing.

Next Week:
Landscaping.
F/P/S of remainder of Concrete Hardscape.
Pour of Concrete Runnel is scheduled for July 12th.

Phase 1 Mechanical/Electrical Testing and Checks
Mechanical Start-Up in Areas 2, 3 and 4A is ongoing.
Balancing is ongoing.
Commissioning, TAB and Func. Performance Testing has begun and is ongoing.

June 18 - June 22

  • June 18 - June 22, 2018 EHS construction photos
  • June 18 - June 22, 2018 EHS construction photos
  • June 18 - June 22, 2018 EHS construction photos
  • June 18 - June 22, 2018 EHS construction photos
  • June 18 - June 22, 2018 EHS construction photos
  • June 18 - June 22, 2018 EHS construction photos

 

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1B: Auxiliary Gymnasium Remodel

Phase 1C: Existing School Exterior Finishes

Phase 1: New Construction Classroom Wings

Deliveries:
Light Pole Standards.
Remainder of Metal Siding for North Area 2 & 3.

Phase 1 MDF/IDF:
Owners continue their work.

Phase 1B:
SUBSTANTIAL COMPLETION IS SCHEDULED AS OF 8/3/2018
Auxiliary Gym/Hallway, 920A & B
Roof re-coat is ongoing (weather permitting).
.Existing Siding Demo work has begun and is scheduled to be completed by June 26th.
Installation of Wood Flooring in Auxiliary Gym is complete.
Wood Floor Finish Cure period begins Saturday, June 23rd.
Installation of Doors and Hardware continues to be delayed by delivery.
Installation of Wall Pads in Auxiliary Gym continues to be delayed by delivery.
GWB Repair/Finishes in Hallway 920A & B is ongoing.

Women’s Locker Room
Paint Walls/Ceilings/HM/Etc. has begun and is ongoing.
GWB Hang, Tape & Finish has begun and is ongoing.

Next Week:
CFB Siding Installation and Replacement of Existing Corner.
Floor/Wall Tile.

Boiler Room
GWB Hang, Tape & Finish is complete.
Selective Roof Demo has begun and is scheduled to be completed by June 26th.
Boiler Room Equipment Installation and Buildout is ongoing.

Phase 1B Utility Work
F/P/S Concrete Pad for New Gas Meter and Installation of Fence Posts are complete.

Next Week:
Installation of New Gas Meter.

Phase 1C:
Exterior Painting continues as areas become available.

Phase 1/New Construction:
Area 2

Storefront Glazing is complete.
AV Install is ongoing.
Handrail installation is delayed and scheduled to resume week of July 9th.
Metal Siding System at N has begun and is scheduled to be completed by July 29th.
Floor Coverings - RFT & Carpet at Level 1 and 2 is complete.
Field Measurement for Installation of Window Treatments is complete; Installation begins week of July 16th.

Next Week:

Toilet Partitions and Accessories.

Area 3

AV Installation has begun and is ongoing.
Acoustical Ceiling Tile/Linear Wood installation at Level 2 is ongoing.
Painting of South Wall & Soffit in Existing Commons is ongoing.
Field Measurement for Installation of Window Treatments is complete; Installation begins week of July 16th.
Temporary Wall has been removed!
Added Sprinkler Heads have been removed.
Floor Coverings - RFT & Carpet at Level 2 is complete.
Construction of ADA approved Ramp and Stage is complete.

Next Week:
GWB Hang/Tape Level South Wall and Stage Soffit.

Areas 4-A and 4-B

Electrical Trim Installation at Level 2 is complete.
Elevator Pre-Inspection Punch List Completion is complete.
Finish Carpentry/MDF & Wood Trim is ongoing.
Installation of Doors & Hardware is delayed by supplier.
Toilet Partitions and Accessory installation is ongoing.
Field Measurement for Installation of Window Treatments is complete; Installation begins week of July 16th.
AV Installation is complete.
Floor Coverings - RFT & Carpet in Classrooms at Levels 1 and 2 is complete.
Phone Line installation to elevator is complete.

Next Week:
Elevator Trim & Test.

Building Perimeter and Commons Plaza
Grading for Hardscape at Courtyard is ongoing.
F/P/S Concrete Hardscape at Courtyard is ongoing.
F/P/S Concrete Runnel installation has begun and is ongoing.

Next Week:
Irrigation installation has been rescheduled to week of July 2nd.
F/P/S Concrete Hardscape at East Area 2 and West Area 4B.

Phase 1 Mechanical/Electrical Testing and Checks
Mechanical Start-Up in Areas 2, 3 and 4A has begun and is ongoing.
Balancing has begun and is ongoing.

June 4 - June 8

  • June 4 - June 8, 2018 EHS construction photos
  • June 4 - June 8, 2018 EHS construction photos
  • June 4 - June 8, 2018 EHS construction photos
  • June 4 - June 8, 2018 EHS construction photos
  • June 4 - June 8, 2018 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1B: Auxiliary Gymnasium Remodel

Phase 1C: Existing School Exterior Finishes

Phase 1: New Construction Classroom Wings

Deliveries:
Projectors
Light Pole Standards
Auxiliary Gym Equipment

Phase 1 MDF/IDF:
Owners continue their work.

Phase 1B:
Auxiliary Gym/Hallway, 920A & B
Roof re-coat is ongoing (weather permitting).
Exterior CFB Siding continues.
Installation of Scoreboard and Shot Clocks, etc. in Aux Gym is complete.
Auxiliary Gym Equipment is complete.
Installation of Doors and Hardware is ongoing.
Acclimation of Wood Flooring for Aux Gym is complete; Installation has begun.
GWB Repair/Finishes in Hallway 920A & B has begun and is ongoing.

Women’s Locker Room
CFB Siding Installation is ongoing.
Framing of Suspended GYP Board Ceilings is complete.
Ceiling Rough-In is complete.

Next Week:
GWB Hang, Tape & Finish.

Wrestling Room
GWB Hang, Tape & Finish is ongoing.
Boiler Room Equipment Installation and Buildout is ongoing.
HVAC Rough-In is ongoing.

Phase 1C:
Exterior Painting has begun and continues as areas become available.

Phase 1/New Construction:
Area 2
AV Install is ongoing.
Handrail installation is ongoing.
GWB at Guardrails is complete.
Painting of Steel Stairs/Guardrails is complete.

Next Week:
Toilet Partitions and Accessories.
Floor Coverings - RFT & Carpet at Level 2.

Area 3
Acoustical Ceiling Tile/Linear Wood installation at Level 2 is ongoing.
Painting of South Wall & Soffit in Existing Commons is ongoing.
Floor Coverings - RFT & Carpet at Level 1 is ongoing.

Next Week:
TEMPORARY WALL WILL BE REMOVED AFTER SCHOOL IS OUT 6-22-2018.
AV Installation.
New ADA approved Ramp & Stage Construction.
Acoustical Wall Panels.

Areas 4-A and 4-B
Light Fixture Installation at Level 1 and Level 2 Grid Classrooms and commons is ongoing.
Electrical Trim Installation at Level 1 is ongoing.
Electrical Trim Installation at Level 2 is ongoing.
Casework/Cabinets & Countertop installation at Levels 2 and 1 is ongoing.
Acoustical Ceiling Tile installation in Level 2 Classrooms is complete; Level 1 Classrooms is ongoing.
Elevator Pre-Inspection Punch List Completion has begun and is ongoing.
Finish Carpentry/MDF & Wood Trim is ongoing.
Installation of Doors & Hardware is ongoing.
GWB at Guardrails is complete.
Painting of Steel Stairs/Guardrails and Stairs has begun and is ongoing.

Next Week:
Toilet Partitions and Accessories.

Building Perimeter and Commons Plaza
Grading for Hardscape at Courtyard is ongoing.
Irrigation Sleeving is ongoing.
F/P/S Concrete Hardscape at Courtyard is ongoing.
Light Pole Standards/Electrical has begun and is ongoing.

Next Week:
Grading for Hardscape/Landscape at E. Side of Area 2.
F/P/S Concrete Hardscape at East Area 2 and West Area 4B.

May 28 - June 1

  • May 28 - June 1, 2018 EHS construction photos
  • May 28 - June 1, 2018 EHS construction photos
  • May 28 - June 1, 2018 EHS construction photos
  • May 28 - June 1, 2018 EHS construction photos
  • May 28 - June 1, 2018 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1B: Auxiliary Gymnasium Remodel

Phase 1: New Construction Classroom Wings

Deliveries:
Casework for Area 4, Level 2
Areas 2 and 3 Exterior Glazing
Areas 4A and 4B Metal Ventilation Bases
Doors w/Hardware for Area 9 Phase 1B
Aux Gym Hardwood Flooring

Phase 1 MDF/IDF:
Owners continue their work.

Phase 1B:
Auxiliary Gym/Hallway, 920A & B

Roof re-coat is ongoing (weather permitting).
Exterior CFB Siding continues.
Painting of MDF & Wood Trim is complete.
Installation of Scoreboard and Shot Clocks, etc. in Aux Gym is ongoing.
Installation of Doors and Hardware has begun and is ongoing.
Stocking and Acclimation of Wood Flooring for Aux Gym has begun.

Next Week:
Installation of Wood Flooring in Aux Gym is scheduled to begin on June 7th.

Women’s Locker Room
CFB Siding Installation is ongoing.
Framing of Suspended GYP Board Ceilings has begun and is ongoing.

Next Week:
GWB Hang, Tape & Finish.
Ceiling Rough-In.

Wrestling Room
GWB Hang, Tape & Finish has begun and is ongoing.
Boiler Room Equipment Installation and Buildout is ongoing.
HVAC Rough-In is ongoing.

Next Week:
GWB Hang, Tape & Finish.

Phase 1C:
Exterior Painting has begun and continues as areas become available.

Phase 1/New Construction
Area 2
Exterior Storefront Glazing is complete.
Handrail installation is ongoing.
WhiteBoards, TackBoards, CGs installation is complete.
Doors and Hardware Installation and Levels 2 & 1 is complete.
GWB at Guardrails is complete.
Steel Stair Treads/Landing Concrete Pour/Finish is complete.

Next Week:
Toilet Partitions and Accessories.
Painting of Steel Stairs/Guardrails and Stairs.

Area 3
Remainder of Storefront Glazing (exterior) is complete.
Doors & Hardware at Levels 1 and 2 is complete.
Acoustical Ceiling Tile/Linear Wood installation at Levels 1 is complete; Level 2 is ongoing.
Installation of WhiteBoards, TackBoards, CGs, and etc. is complete.
Painting of South Wall & Soffit in Existing Commons is ongoing.
Floor Coverings - Library Level 2 is complete.
Floor Coverings - RFT & Carpet at Level 1 has begun and is ongoing.

Next Week:
TEMPORARY WALL WILL BE REMOVED AFTER SCHOOL IS OUT 6-22-2018.
New ADA approved Ramp & Stage Construction.

 

Areas 4-A and 4-B
CFB Siding at Penthouse is complete
Painting of Exterior Penthouse Siding is complete.
Light Fixture Installation at Level 1 and Level 2 Grid Classrooms and commons is ongoing.
Electrical Trim Installation at Level 1 is ongoing.
Electrical Trim Installation at Level 2 is ongoing.
Pour and Finish of Concrete at Steel Stair Treads and landing is complete.
Casework/Cabinets & Countertop installation at Levels 2 and 1 is ongoing.
Acoustical Ceiling Tile installation in Level 2 Classrooms has begun and is ongoing.
Elevator Pre-Inspection Punch List Completion has begun and is ongoing.
Finish Carpentry/MDF & Wood Trim is ongoing.
Installation of Doors & Hardware is ongoing.
Completion of GWB at Guardrails is ongoing.
Installation of Whiteboards/Tackboards/CGs/Etc. is complete.
GWB Hang/Tape/Finish of Elevator Fronts is complete.

Next Week:
Toilet Partitions and Accessories.
Painting of Steel Stairs/Guardrails and Stairs.
Acoustical Ceiling Tile at Level 1 Classrooms.

Building Perimeter and Commons Plaza
Grading for Hardscape at Courtyard is ongoing.
Irrigation Sleeving is ongoing.
F/P/S Concrete Hardscape at Courtyard is ongoing.

Next Week:
Grading for Hardscape/Landscape at E. Side of Area 2.
F/P/S Concrete Hardscape at East Area 2 and West Area 4B.

May 21 - May 25

  • May 21 - May 25, 2018 EHS construction photos
  • May 21 - May 25, 2018 EHS construction photos
  • May 21 - May 25, 2018 EHS construction photos
  • May 21 - May 25, 2018 EHS construction photos
  • May 21 - May 25, 2018 EHS construction photos
  • May 21 - May 25, 2018 EHS construction photos
  • May 21 - May 25, 2018 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1B: Auxiliary Gymnasium Remodel

Phase 1C: Existing School Exterior Finishes

Phase 1: New Construction Classroom Wings

Deliveries:
Light Fixtures for Areas 3, 4, 9
Guardrails for Areas 2, 3, 4
Area 4A Metal Ventilation Bases
Doors w/Hardware for areas 2, 3, 4A, 4B and 9
Phase 1 B Lockers

Phase 1 MDF/IDF:
Owners continue their work.

Phase 1B:
Auxiliary Gym/Hallway, 920A & B
Roof re-coat has begun and is ongoing (weather permitting).
Exterior CFB Siding continues.
Finish Carpentry/MDF & Wood Trim is complete.
Electrical, HVAC and Fire Sprinkler Rough-In in Hallway is complete.

Women’s Locker Room
CFB Siding Installation is ongoing.
Plumbing/Piping Rough-In is complete.
Interior Wall Framing/Pick-Up and Pre-Rock is complete.
Fire Sprinkler Rough-In is complete.
Electrical Rough-In is complete.

Next Week:
Frame Suspended GYP Board Ceilings.
Ceiling Rough-In.

Wrestling Room
Roofing work is currently suspended and will resume the week of June 22nd.
Interior Wall Framing is complete.
Boiler Room Equipment Installation and Buildout is ongoing.
HVAC Rough-In is ongoing.

Next Week:
GWB Hang, Tape & Finish.

Phase 1C:
Exterior Painting has begun and continues as areas become available.

Phase 1/New Construction:
Area 2
Expansion/Seismic Joint Cover Installation is complete.
Guardrail installation is complete; Handrail installation is ongoing.
WhiteBoards, TackBoards, CGs installation is ongoing.
Doors and Hardware Installation and Levels 2 & 1 is ongoing.

Next Week:
Completion of GWB at Guardrails.
Pour/Finish Concrete at Steel Stair.
Treads/Landing will occur on May 29th.

Area 3
Expansion/Seismic Joint Cover Installation is complete.
Doors & Hardware at Levels 1 and 2 is ongoing.
Acoustical Ceiling Tile/Linear Wood installation at Levels 1 and 2 is ongoing.
Installation of WhiteBoards, TackBoards, CGs, and etc. and is ongoing.
Painting of South Wall & Soffit in Existing Commons is ongoing.
Finish Carpentry/MDF and Wood Trim is complete.
Floor Coverings - RFT and Carpet at Level 2 is complete.

Next Week:
Floor Coverings - Library.
Acoustical Ceiling Tile/Linear Wood - Level 1.
TEMPORARY WALL WILL BE REMOVED AFTER SCHOOL IS OUT 6-22-2018
PER CCD, NEW ADA APPROVED RAMP & STAGE CONSTRUCTION TO BEGIN WEEK OF MAY 28TH.

Areas 4-A and 4-B
Light Fixture Installation at Level 1 and Level 2 Grid Classrooms and commons is ongoing.
Electrical Trim Installation at Level 1 is ongoing.
Electrical Trim Installation at Level 2 is ongoing.
Ceramic tiling at Level 1 and Level 2 restrooms is complete.
Casework/Cabinets & Countertop installation at Level 2 is ongoing.
Elevator Installation is ongoing.
Finish Carpentry/MDF & Wood Trim is ongoing.
Installation of Doors & Hardware is ongoing.
Installation of Steel Guardrails and Handrails at Steel Stair (4A) is complete.
Installation of Whiteboards/Tackboards/CGs/Etc. is ongoing.
GWB Hang/Tape/Finish of Elevator Fronts is ongoing.

Next Week:
CFB Siding at Penthouse
Pour/Finish Concrete at Steel Stair Treads/Landing will occur on May 29th.
Acoustical Ceiling Tile Classrooms at Level 2.

Building Perimeter and Commons Plaza
Grading for Hardscape at Courtyard is ongoing.
Irrigation Sleeving is ongoing.
F/P/S Concrete Hardscape at Courtyard is ongoing.

May 14 - May 18

  • May 14 - May 18, 2018 EHS construction photos
  • May 14 - May 18, 2018 EHS construction photos
  • May 14 - May 18, 2018 EHS construction photos
  • May 14 - May 18, 2018 EHS construction photos
  • May 14 - May 18, 2018 EHS construction photos
  • May 14 - May 18, 2018 EHS construction photos
  • May 14 - May 18, 2018 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1B: Auxiliary Gymnasium Remodel

Phase 1C: Existing School Exterior Finishes

Phase 1: New Construction Classroom Wings

Deliveries:
Area 4A & 4B Metal Ventilation Bases
Phase 1B MDF Wainscot

Phase 1 MDF/IDF:
Owners have begun their work.

Phase 1B:
Auxiliary Gym/Hallway, 920A & B
Roofing work continues (weather permitting).
Existing Siding Demolition continues (weather permitting).
Exterior CFB Siding continues.
Electrical Trim in Auxiliary Gym is complete.
Finish Carpentry/MDF & Wood Trim is scheduled to be completed by May 22nd.

Next Week:
Paint MDF & Wood Trim.
Install Scoreboard/Shot Clocks/Etc. in Auxiliary Gym.

Women’s Locker Room
CFB Siding Installation is ongoing.
Plumbing/Piping Rough-In is complete.
Interior Wall Framing/Pick-Up and Pre-Rock is complete.
HVAC Rough-In is complete.
Electrical Rough-In is complete.

Next Week:
Frame Suspended GYP Board Ceilings.
Ceiling Rough-In.

Wrestling Room
Roofing work is currently suspended and will resume the week of June 22nd.
Interior Wall Framing is ongoing.
Boiler Room Equipment Installation and Buildout is ongoing.
HVAC Rough-In is ongoing.
Fire Sprinkler Rough-In is complete.

Next Week:
GWB Hang, Tape & Finish.

Phase 1C:
Exterior Painting has begun and continues as areas become available.

Phase 1/New Construction:
Area 2
Expansion/Seismic Joint Cover Installation is now scheduled to be completed by May 25th, weather permitting.
Painting of Exterior Penthouse Siding is complete.
Acoustical Ceiling Tile/Linear Wood Installation at Levels 1 and 2 is complete.
Guardrail and Handrail installation is ongoing.
Floor Coverings - RFT & Carpet at Level 1 classrooms is complete.
Floor Coverings - RFT & Carpet at Level 2 classrooms is complete.
WhiteBoards, TackBoards, CGs installation is ongoing.
Doors and Hardware Installation and Levels 2 & 1 is ongoing.
HVAC Mechanical Start-Up has begun; Balancing to begin week of June 4th.

Next Week:
Completion of Expansion/Seismic Joint Cover Installation is scheduled to occur on May 25th.
Pour/Finish Concrete at Steel Stair Treads/Landing will occur on May 24th.

Area 3
Expansion/Seismic Joint Cover Installation has begun and is ongoing.
Painting of Exterior Penthouse Siding is complete.
Doors & Hardware at Levels 1 and 2 is ongoing.
Acoustical Ceiling Tile/Linear Wood - Level 2 is ongoing.
Installation of WhiteBoards, TackBoards, CGs, and etc. and is ongoing.
Fire Doors installation is complete.
Painting of South Wall & Soffit in Existing Commons is ongoing.

Next Week:
Floor Coverings - RFT & Carpet at Level 2.
Acoustical Ceiling Tile/Linear Wood - Level 1.
GWB Hang/Tape Level South Wall & Stage Soffit
TEMPORARY WALL WILL BE REMOVED AFTER SCHOOL IS OUT 6-22-2018
PER CCD, NEW ADA APPROVED RAMP & STAGE CONSTRUCTION TO BEGIN WEEK OF MAY 28TH.

Areas 4-A and 4-B
Light Fixture Installation at Level 1 and Level 2 Grid Classrooms and commons is ongoing.
Electrical Trim Installation at Level 1 is ongoing.
Electrical Trim Installation at Level 2 is ongoing.
Plumbing fixtures at Level 2 is complete.
Ceramic tiling at Level 1 and Level 2 restrooms has begun and is ongoing.
Casework/Cabinets & Countertop installation at Level 2 is ongoing.
Elevator Installation is ongoing.
Relite Glazing is complete.
Finish Carpentry/MDF & Wood Trim has begun and is ongoing.
Installation of Doors & Hardware has begun and is ongoing.
Installation of Steel Guardrails and Handrails at Steel Stair (4A) has begun and is ongoing.
Installation of Whiteboards/Tackboards/CGs/Etc. has begun and is ongoing.
Elevator Front Framing is complete.
GWB Hang/Tape/Finish of Elevator Fronts has begun and is scheduled to be completed by May 22nd.

Next Week:
Pour/Finish Concrete at Steel Stair Treads/Landing will occur on May 24th.
Plumbing fixtures at Level 1.

Building Perimeter and Commons Plaza
Grading for Hardscape at Courtyard is ongoing.
Irrigation Sleeving is ongoing.
F/P/S Concrete Hardscape at Courtyard has begun and is ongoing.
Acid Neutralization Tank Installation is complete.

May 7 - May 11

  • May 7 - May 11, 2018 EHS construction photos
  • May 7 - May 11, 2018 EHS construction photos
  • May 7 - May 11, 2018 EHS construction photos
  • May 7 - May 11, 2018 EHS construction photos
  • May 7 - May 11, 2018 EHS construction photos
  • May 7 - May 11, 2018 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1B: Auxiliary Gymnasium Remodel

Phase 1: New Construction Classroom Wings

Deliveries:
Light Fixtures - Classrooms Areas 3, 4, and 9 (Phase 1B)
Casework, Area 4 - Level 2
MDF Wall Panels for Area 4
Area 4A & 4B Metal Ventilation Bases
Doors w/Hardware for Area 4

Phase 1B:
Auxiliary Gym/Hallway, 920A & B
Roofing work has resumed (weather permitting).
Existing Siding Demolition has resumed (weather permitting).
Exterior CFB Siding continues.
Early Wall/Ceiling Rough-In in Hallway 920A & B as available.
HVAC Rough-In in Hallway 920A and 920B is complete.
Electrical Rough-In in Hallway 920A and 920B is complete.
Electrical Trim in Auxiliary Gym is ongoing.
Finish Carpentry/MDF & Wood Trim is ongoing.
Light Fixture installation in Auxiliary Gym is complete.
LV/Systems Cabling & Terminations in Auxiliary Gym is ongoing.

Women’s Locker Room
CFB Siding Installation has begun and is ongoing.
Plumbing/Piping Rough-In is ongoing.
Interior Wall Framing/Pick-Up and Pre-Rock is ongoing.
HVAC Rough-In is ongoing.
Electrical Rough-In is ongoing.

Wrestling Room
Roofing work is currently suspended and will resume the week of June 22nd.
Interior Wall Framing is ongoing.
Boiler Room Equipment Installation and Buildout is ongoing.
HVAC Rough-In has begun and is ongoing.
HVAC Rough-In has begun and is ongoing.

Phase 1/New Construction:        
Area 2
Expansion/Seismic Joint Cover Installation is scheduled to be completed by May 11th.
Guardrail and Handrail installation has begun and is ongoing.
Floor Coverings - RFT & Carpet at Level 1 classrooms is complete.
Floor Coverings - RFT & Carpet at Level 2 classrooms is complete.
WhiteBoards, TackBoards , CGs installation is ongoing.
Doors and Hardware Installation and Levels 2 & 1 is ongoing.

Next Week:
Completion of Expansion/Seismic Joint Cover Installation.
Pour/Finish Concrete at Steel Stair Treads/Landing.

Area 3
Storefront Glazing/Door Installation at Level 1 is complete.
Doors & Hardware at Levels 1 and 2 is ongoing.
Acoustical Ceiling Tile/Linear Wood - Level 2 has begun and is ongoing.
Installation of WhiteBoards, TackBoards, CGs, and etc. has begun and is ongoing.
Fire Doors installation has begun and is ongoing.
Stage/Ramp Demo, Form, Pour at Existing Commons/Area 3 is ongoing.
Painting of South Wall & Soffit in Existing Commons is ongoing.

Next Week:
Metal Siding System at North Elevation is postponed until week of May 29th.
Acoustical Ceiling Tile/Linear Wood - Level 1.
Expansion/Seismic Joint Cover Installation.
Patch Back Existing Acoustical Grid and Reinstall Lights, Devices and Acoustical Tiles.

TEMPORARY WALL WILL BE REMOVED AFTER SCHOOL IS OUT 6-22-2018

Areas 4-A and 4-B
Roofing/Low Roof detail work is ongoing as weather permits.
Metal Siding System at South and West Elevations is complete.
Light Fixture Installation at Level 1 and Level 2 Grid Classrooms and commons is ongoing.
Electrical Trim Installation at Level 1 is ongoing.
Electrical Trim Installation at Level 2 is ongoing.
Plumbing fixtures at Level 2 has begun and is ongoing.
Casework/Cabinets & Countertop installation at Level 2 is ongoing.
Elevator Installation is ongoing.

Next Week:
Doors and Hardware at Levels 2 and 1.
Whiteboards/Tackboards/CGs/Etc.

Building Perimeter and Commons Plaza
Grading for Hardscape at Courtyard is ongoing.
Irrigation Sleeving is ongoing.
Courtyard Light Pole Standards/Electrical Installation is complete.

Next Week:
F/P/S Concrete Hardscape at Courtyard.

April 30 - May 4

  • April 30 - May 4, 2018 EHS construction photos
  • April 30 - May 4, 2018 EHS construction photos
  • April 30 - May 4, 2018 EHS construction photos
  • April 30 - May 4, 2018 EHS construction photos
  • April 30 - May 4, 2018 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1B: Auxiliary Gymnasium Remodel

Phase 1: New Construction Classroom Wings

Deliveries:
Handrails and Guardrails for Area 2, 3, and 4
Casework, Area 4 - Level 1
MDF Wall Panels for Area 4
MDF Wainscot for Phase 1B areas

Phase 1 MDF/IDF:
**All IDF/MDF Panels, Racks, Terminations, Testing, Power-Up in new construction is complete.**

Phase 1B:
Auxiliary Gym/Hallway, 920A & B
Roofing work is currently suspended and will resume the week of June 22nd.
Existing Siding Demolition and Building Wrap Behind is complete.
Fire Sprinkler Rough-In at Hallway is complete.
Early Wall/Ceiling Rough-In in Hallway 920A & B as available.
HVAC Rough-In in Hallway 920A and 920B is ongoing.
Electrical Rough-In in Hallway 920A and 920B is ongoing.
FSORB Panel Installation in Auxiliary Gym is complete.
Electrical Trim in Auxiliary Gym is ongoing.
Finish Carpentry/MDF & Wood Trim has begun and is ongoing.
Light Fixture installation in Auxiliary Gym has begun and is ongoing.
LV/Systems Cabling & Terminations in Auxiliary Gym has begun and is ongoing.

Next Week:
GWB Repair/Finishes

Women’s Locker Room
Existing Siding Demolition and Building Wrap Behind is complete.
Plumbing/Piping Rough-In is ongoing.
Interior Wall Framing/Pick-Up and Pre-Rock is ongoing.
Fire Sprinkler Rough-In is complete.
HVAC Rough-In is ongoing.
Electrical Rough-In is ongoing.

Next Week:
CFB Siding (exterior)Installation begins.

Wrestling Room
Roofing work is currently suspended and will resume the week of June 22nd.
Interior Wall Framing is ongoing.
Boiler Room Equipment Installation and Buildout is ongoing.

Next Week:
Fire Sprinkler Rough-In.
HVAC Rough-In

Phase 1/New Construction:
Area 2
Expansion/Seismic Joint Cover Installation is scheduled to be completed by May 11th.
CFB Siding Installation is complete.
Floor Coverings - RFT & Carpet at Level 1 has begun and is ongoing.
WhiteBoards, TackBoards, CGs installation has begun and is ongoing.
Doors and Hardware Installation and Levels 2 & 1 is ongoing.
Acoustical Ceiling Tile/Linear Wood at Levels 1 and 2 is complete.

Next Week:
Guardrail and Handrail installation.
Installation of WhiteBoards, TackBoards, CGs, and etc.
Floor Coverings - RFT a & Carpet Level 2.

Area 3
CFB Siding - South Elevation is complete.
Finish Carpentry/MDF and Wood Trim installation is complete.
Doors & Hardware at Levels 1 and 2 has begun and is ongoing.
Installation of Light Fixtures at Levels 1 and 2 Grid is completed and was Inspected on May 3rd.
Energization of Lights/Plugs/Etc. is complete.
Plumbing, Toilet Fixtures at Level 2 is complete.
GWB Hang/Firetape at Existing Commons/Area 3 is complete.
Stage/Ramp Demo, Form, Pour at Existing Commons/Area 3 is ongoing.
Painting of South Wall & Soffit in Existing Commons has begun and is ongoing.

Next Week:
Metal Siding System at North Elevation.
Acoustical Ceiling Tile/Linear Wood - Level 2.
E xpansion/Seismic Joint Cover Installation.
Installation of WhiteBoards, TackBoards, CGs, and etc.
Fire Doors.
Patch Back Existing Acoustical Grid and Reinstall Lights, Devices and Acoustical Tiles.
TEMPORARY WALL WILL BE REMOVED AFTER SCHOOL IS OUT 6-22-2018

Areas 4-A and 4-B
Roofing/Low Roof detail work is ongoing as weather permits.
Metal Siding System at South and West Elevations is ongoing.
Light Fixture Installation at Level 1 and Level 2 Grid Classrooms is ongoing.
Electrical Trim Installation at Level 1 is ongoing.
Ceramic Tiling installation at Level 1 is complete.
Relite glazing is complete.
Casework/Cabinets & Countertop installation at Level 2 has begun and is ongoing.
Elevator Installation has begun and is ongoing!

Next Week:
Plumbing fixtures at Level 2.

Building Perimeter and Commons Plaza
Grading for Hardscape at Courtyard is ongoing.
FRPS Seat/Planter Footings and Walls is complete.
Irrigation Sleeving is ongoing.
Courtyard Light Pole Standards/Electrical Installation is complete.

Next Week:
F/P/S Concrete Hardscape at Courtyard.

April 19 - April 27

  • April 19 - April 27, 2018 EHS construction photos
  • April 19 - April 27, 2018 EHS construction photos
  • April 19 - April 27, 2018 EHS construction photos
  • April 19 - April 27, 2018 EHS construction photos
  • April 19 - April 27, 2018 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1B: Auxiliary Gymnasium Remodel

Phase 1: New Construction Classroom Wings

Deliveries:
Light Pole Standards

Phase 1B:
Auxiliary Gym/Hallway, 920A & B

Selective Roof Demolition, Framing and Infill is ongoing, weather permitting.
Roofing work is ongoing.
Existing Siding Demolition and Building Wrap Behind is ongoing.
Fire Sprinkler Rough-In at Hallway is ongoing.
Early Wall/Ceiling Rough-In in Hallway 920A & B as available.
HVAC Rough-In in Hallway 920A and 920B is ongoing.
Electrical Rough-In in Hallway 920A and 920B has begun and is ongoing.
FSORB Panel Installation in Auxiliary Gym is scheduled to be completed by Wednesday, May 2nd.
New CMU Walls and Infill is complete.
Electrical Wire/Term & Panelwork has begun and is ongoing.
Electrical Trim in Auxiliary Gym has begun and is ongoing.

Next Week:
Light Fixtures in Auxiliary Gym
LV/Systems Cabling & Terminations in Auxiliary Gym

Women’s Locker Room
Existing Siding Demolition is ongoing, weather permitting.
Roofing work is complete.
Existing Siding Demolition and Building Wrap Behind is ongoing.
Plumbing/Piping Rough-In is ongoing.
Interior Wall Framing/Pick-Up and Pre-Rock is ongoing.
HVAC Rough-In is ongoing.
Electrical Rough-In is ongoing.

Wrestling Room
Roof Selective Demolition is ongoing, weather permitting.
Roof Framing/Infill is ongoing, weather permitting.
Steel Erection is complete; Wall Framing is ongoing.
Boiler Room Equipment Installation and Buildout has begun and is ongoing.

Next Week:

Wall Framing.

Phase 1/New Construction:
Area 2
Expansion/Seismic Joint Cover Installation is ongoing and is now scheduled to be completed by May 11th.
CFB Siding Installation resumed and is now scheduled to be completed by May 4th.
Additional Overhead Coiling Grille installation is complete.
Casework/Cabinets/Countertops in additional rooms at Level 2 is complete.
Plumbing/Toilet Fixtures installation at Level 2 Casework is complete.
Plumbing/Toilet Fixtures installation at Levels 1 and 2 is complete.
Steel Stair installation is complete. Guardrail and Handrail installation is scheduled for the week of May 7th.
Doors and Hardware installation at Levels 1 and 2 continues.
Storefront & Exterior Entrance installation is complete.
Doors and Hardware Installation and Levels 2 & 1 is now ongoing; delivery delayed by American Direct.
Acoustical Ceiling Tile/Linear Wood at Levels 1 and 2 is ongoing.

Next Week:

Installation of WhiteBoards, TackBoards, CGs, and etc.
Floor Coverings - RFT a & Carpet Level 1.

Area 3
Metal Soffit System Installation is complete.
Finish Carpentry/MDF and Wood Trim installation is ongoing.
Relite Glazing is complete.
Installation of Light Fixtures at Levels 1 and 2 Grid is near completion and scheduled for Inspection on May 3rd.
Energization of Lights/Plugs/Etc. is nearly complete and scheduled for completion on May 3rd.
Interior Storefront Installation at Level 2 is complete.
Acoustical Ceiling Grid at Level 1 is complete.
GWB Hang/Firetape at Existing Commons/Area 3 is ongoing.
Stage/Ramp Demo, Form, Pour at Existing Commons/Area 3 is ongoing.
Electrical Trim Installation at Levels 1 and 2 is complete.

Next Week:
Plumbing/Toilet Fixtures at Level 2.
Expansion/Seismic Joint Cover Installation.
Installation of WhiteBoards, TackBoards, CGs, and etc.
Doors & Hardware at Levels 1 and 2.
Paint South Wall & Soffit in Existing Commons.

Areas 4-A and 4-B
Roofing/Low Roof detail work is ongoing as weather permits.
Metal Siding System at South and West Elevations is ongoing.
CFB Siding at Penthouse is complete.
Light Fixture Installation at Level 1 and Level 2 Grid Classrooms has begun and is ongoing.
HVAC Diffuser Installation at Level 2 is complete.
Acoustical Ceiling Grid at Level 1 and 2 Common Areas is complete.
Electrical Trim Installation at Level 1 has begun and is ongoing.
Overhead Coiling Grille installation is complete.
Ceramic Tiling installation at Level 1 has begun and is scheduled to be completed by May 4th.
Installation of steel staircase in Area 4B is complete.

Next Week:
Relite Glazing.
ELEVATOR INSTALLATION BEGINS APRIL 30TH!
Casework/Cabinets & Countertops at Level 2 then Level 1.

Building Perimeter and Commons Plaza
Grading for Hardscape at Courtyard is ongoing.
FRPS Seat/Planter Footings and Walls is ongoing.
Irrigation Sleeving is ongoing.
Courtyard Light Pole Standards/Electrical Installation has begun and is ongoing.

Next Week:

F/P/S Concrete Hardscape at Courtyard has been rescheduled to the week of May 7th.

April 9 - April 13

  • April 9 - April 13, 2018 EHS construction photos
  • April 9 - April 13, 2018 EHS construction photos
  • April 9 - April 13, 2018 EHS construction photos
  • April 9 - April 13, 2018 EHS construction photos
  • April 9 - April 13, 2018 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1B: Auxiliary Gymnasium Remodel

Phase 1: New Construction Classroom Wings

Deliveries:
Light Fixtures - Classroom Fixtures for Area 2+
Area 3 Casework
Area 3 MDF Wall Panels
Area 2 Level 2 Doors w/Hardware
Area 3 Levels 1 & 2 Doors w/Hardware
Phase 1B Duct Work
Phase 1B Boiler Structural Steel Rack

Phase 1B:
Auxiliary Gym/Hallway, 920A & B
Selective Roof Demolition, Framing and Infill is ongoing.
Roofing work is ongoing.
Existing Siding Demolition and Building Wrap Behind is ongoing.
Fire Sprinkler Rough-In at Auxiliary Gym is ongoing.
GWB Repair/Finishes are complete.
Early Wall/Ceiling Rough-In in Hallway 920A & B as available.
Painting of Exposed Structure and Walls (Interior) is ongoing.
Painting of Interior Exposed Structure and Walls was completed.
HVAC Rough-In in Hallway 920A and 920B has begun and is ongoing.
FSORB Panel Installation has begun and is ongoing.
New CMU Walls and Infill has begun and is ongoing.
HM Frames @ CMU was completed.
F/R/P/S Equipment & Housekeeping Pads at Boiler were poured on April 12th.

Next Week:
HVAC Rough-In in Hallway 920A and 920B.
Fire Sprinkler Rough-In in Hallway, 920A & B.

Women’s Locker Room
Existing Siding Demolition is ongoing.
Selective Roof Demolition, Framing and Infill is ongoing.
Roofing work is ongoing.
Existing Siding Demolition and Building Wrap Behind is ongoing.
Chase Wall Plumbing Rough-In is ongoing.
Early Wall/Ceiling Rough-In is ongoing as available.
Plumbing/Piping Rough-In has begun and is ongoing.
Interior Wall Framing/Pick-Up and Pre-Rock has begun and is ongoing.
HM Frames were installed at CMU
CMU - New Walls and Infill has begun and is ongoing.
Fire Sprinkler Rough-In was completed.
HVAC Rough-In has begun and is ongoing.

Wrestling Room
Roof Selective Demolition has begun and is ongoing, weather permitting.
Roof Framing/Infill has begun and is ongoing, weather permitting.
Early Wall/Ceiling Rough-In as available.

Next Week:
Steel Erection; Wall Framing.

Phase 1/New Construction:
Area 2
Overhead Coiling Grille installation is complete.
CFB Siding Installation will continue beginning the week of April 23rd.
Expansion/Seismic Joint Cover Installation is ongoing and is now scheduled to be completed by April 20th.
Finish Carpentry/MDF and Wood Trim installation is ongoing.
Casework/Cabinets/Countertops in additional rooms at Level 2 is ongoing.
Plumbing/Toilet Fixtures installation at Level 1 casework is complete.
Plumbing/Toilet Fixtures installation at Level 2 Casework has begun and is ongoing.
Fume Hood Installation in Science Lab has begun and is ongoing.
Installation of Steel Stairs and Guardrails is ongoing.
IDF 213A Racks, Terminations and Testing is ongoing.
IDF 262 Racks, Terminations and Testing is ongoing.
Doors and Hardware installation at Levels 1 and 2 continues.
Metal Soffit System installation is complete.
Energization of Area 3 Lights/Plugs/Etc. is ongoing.
Storefront Window/Opening Sill Pans/Flashings is complete.
Storefront & Exterior Doors/Entrance has begun and is ongoing.
Doors and Hardware Installation and Levels 2 & 1 has begun and is ongoing.

Next Week:
Plumbing/Toilet Fixtures at Level 2 Casework.
Acoustical Ceiling Tile/Linear Wood at Levels 2 has been rescheduled to the week of April 16th.
Interior Storefront Installation at Level 2.

Area 3
LV/Systems Cabling & Termination at Levels 1 and 2 is ongoing.
Installation of Light Fixtures at Levels 1 and 2 Grid is ongoing as lights are delivered.
Electrical Trim at Level 2 is complete.
Mechanical Mezzanine Buildout-Duct/Piping/Electrical is ongoing.
Painting at Level 1 is ongoing.
Casework/Cabinets & Countertop installation - Level 2, then Level 1.
Metal Siding System installation at South & West Elevations is ongoing.
CFB Siding installation at Penthouse is complete.
Acoustical Ceiling Grid at Level 1 is ongoing.
GWB Hang/Firetape at Existing Commons/Area 3 has begun and is ongoing.
Installation of Storefront & Exterior Doors Entrances at Level 1 is ongoing.
Stage/Ramp Demo, Form, Pour at Existing Commons/Area 3 is ongoing.
Ceramic Tiling at Level 1 is ongoing.
Electrical Trim at Level 1 is complete.
Library Casework/Shelving installation has begun and is ongoing.
Ceramic Tiling of Level 2 Restroom 356 is complete.

Next Week:
Expansion/Seismic Joint Cover Installation.
Interior Storefront Installation at Level 2.
Interior Storefront Installation at Level 1.
Finish Carpentry/MDF and Wood Trim.

Areas 4-A and 4-B
Roofing/Low Roof detail work is ongoing as weather permits.
Metal Siding System Installation in Courtyard Area is complete.
Metal Siding System at South and West Elevations has begun and is ongoing.
CFB Siding installation at Penthouse is complete.
Mechanical Mezzanine Buildout-Duct/Piping/Electrical is ongoing.
Ceramic Tiling of all restrooms is ongoing.
Painting at Levels 1 and 2 Commons Area is complete.
Painting at Levels 1 and 2 is ongoing.
Electrical Rooms 417 Panels & Terminations are ongoing.
Electrical Wire/Term and Panelwork is ongoing.
Acoustical Ceiling Grid at Level 1 Classrooms is complete.

Next Week:
Overhead Coiling Grilles.
ELEVATOR INSTALLATION BEGINS APRIL 30TH!

Building Perimeter and Commons Plaza
Phase 1A Site Boundary Survey occurred on April 13th.
Grading for Hardscape at Courtyard has begun and is ongoing.
FRPS Seat/Planter Footings and Walls is ongoing.

Next Week:
F/P/S Concrete Hardscape at Courtyard has been rescheduled to the week of April 23rd.
Irrigation Sleeving as Needed.

April 2 - April 6, 2018

  • April 2 - April 6, 2018 EHS construction photos
  • April 2 - April 6, 2018 EHS construction photos
  • April 2 - April 6, 2018 EHS construction photos
  • April 2 - April 6, 2018 EHS construction photos
  • April 2 - April 6, 2018EHS construction photos
  • April 2 - April 6, 2018 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1B: Auxiliary Gymnasium Remodel

Phase 1: New Construction Classroom Wings

Deliveries:
Toe Kick Plenum Frames for Area 3
Area 3 Casework - Level 2
Area 3 MDF Wall Panels for Level 2
Area 2 and Area 4 Stairs/Guardrails
Phase 1B Boiler

Phase 1B:
Auxiliary Gym/Hallway, 920A & B
Selective Roof Demolition, Framing and Infill is ongoing.
Roofing work is ongoing.
Existing Siding Demolition and Building Wrap Behind is ongoing.
Fire Sprinkler Rough-In at Auxiliary Gym is ongoing.
GWB Repair/Finishes are ongoing.
Early Wall/Ceiling Rough-In in Hallway 920A & B as available.
Painting of Exposed Structure and Walls (Interior) has begun and is ongoing.

Next Week:
HVAC Rough-In in Hallway 920A and 920B.
Painting of Exposed Structure and Walls (Interior).
Fire Sprinkler Rough-In in Hallway, 920A & B.

Women’s Locker Room
Existing Siding Demolition is ongoing.
Selective Roof Demolition, Framing and Infill is ongoing.
Roofing work is ongoing.
Existing Siding Demolition and Building Wrap Behind is ongoing.
Chase Wall Plumbing Rough-In is ongoing.
Early Wall/Ceiling Rough-In is ongoing as available.
Plumbing/Piping Rough-In has begun and is ongoing.

Next Week:
Fire Sprinkler Rough-In.
CMU - New Walls and Infill.
HVAC Rough-In.
HM Frames at CMU.
Interior Wall Framing/Pick-Up and Pre-Rock.

Wrestling Room
Roof Selective Demolition has begun and is ongoing, weather permitting.
Roof Framing/Infill has begun and is ongoing, weather permitting.
Early Wall/Ceiling Rough-In as available.
Slab-On-Grade prep and placement at Boiler Room was completed.
F/R/P/S Concrete Topping Slab at Athletic Storage Area was completed.

Next Week:
Steel Erection; Wall Framing.

Phase 1/New Construction:
Area 2
Metal Siding System installation is complete.
CFB Siding Installation is ongoing.
Expansion/Seismic Joint Cover Installation is ongoing and scheduled to be completed by April 13th.
Finish Carpentry/MDF and Wood Trim installation is ongoing.
Casework/Cabinets/Countertops in additional rooms at Level 2 is ongoing.
Plumbing/Toilet Fixtures installation at Level 1 casework is now scheduled to be completed by April 13th.
Installation of Steel Stairs and Guardrails has begun and is ongoing.
IDF 213A Racks, Terminations and Testing is ongoing.
IDF 262 Racks, Terminations and Testing is ongoing.
Doors and Hardware installation at Levels 1 and 2 continues.

Next Week:
Plumbing/Toilet Fixtures at Level 2 Casework.
Acoustical Ceiling Tile/Linear Wood at Levels 1 and 2 has been rescheduled to the week of April 9th
Installation of Steel Stairs and Guardrails.
Plumbing/Toilet Fixture installation at Level 2.
Storefront Window/Opening Sill Pans/Flashings.
Storefront & Exterior Doors/Entrances.

Area 3
Electrical Rough-In/Fire Sprinkler Cover Inspections at Metal Soffit System occurred on April 4th.
Metal Soffit System installation has begun and is scheduled to be completed on April 9th.
Storefront Window/Opening Sill Pans/Flashing installation at Level 1 was completed.
Energization of Lights/Plugs/Etc. was completed.
Installation of Light Fixtures at Levels 1 and 2 Grid is ongoing as lights are delivered.
Electrical Trim at Level 2 is complete.
Mechanical Mezzanine Buildout-Duct/Piping/Electrical is ongoing.
Painting at Level 1 is ongoing.
Casework/Cabinets & Countertop installation - Level 2, then Level 1.
Metal Siding System installation is complete.
CFB Siding installation is complete.
Acoustical Ceiling Grid at Level 1 is ongoing.
GWB Hang/Firetape at Level 2 South Wall is complete.
Relite Glazing is complete.
Installation of Storefront & Exterior Doors Entrances at Level 1 is ongoing.
Stage/Ramp Demo, Form, Pour at Existing Commons/Area 3 is ongoing.

Next Week:
Expansion/Seismic Joint Cover Installation.
Interior Storefront Installation at Level 2.
Interior Storefront Installation at Level 1.
Electrical Trim at Level 1.
Library Casework/Shelving.
Ceramic Tiling of Level 2 Restroom 356.

Areas 4-A and 4-B
Roofing/Low Roof detail work is ongoing as weather permits.
Metal Siding System Installation is ongoing.
CFB Siding installation at East Wall is complete.
Mezzanine Deck Wall Framing and Sheathing is ongoing.
Mechanical Mezzanine Buildout-Duct/Piping/Electrical is ongoing.
Wall/Header Framing NLB/Pick-up is complete.
Glass Skylight Glazing Installation is complete.
Ceramic Tiling of all restrooms is ongoing.
Painting at Levels 1 and 2 is ongoing.
Electrical Rooms 417 Panels & Terminations are ongoing.
Electrical Wire/Term and Panelwork is ongoing.
Acoustical Ceiling Grid at Level 1 is ongoing.
Elevator Equipment Room Buildout is complete.

Next Week:
CFB Siding installation at Penthouse.
Metal Siding System at South & West Elevations.
ELEVATOR INSTALLATION BEGINS APRIL 30TH!

Building Perimeter and Commons Plaza
Grading for Hardscape at Courtyard has begun and is ongoing.
FRPS Seat/Planter Footings and Walls is ongoing; pour occurred on April 3rd.

Next Week:
F/P/S Concrete Hardscape at Courtyard has been rescheduled to the week of April 9th.
Irrigation Sleeving as Needed.

March 26 - March 30

  • March 26 - March 30, 2018 EHS construction photos
  • March 26 - March 30, 2018 EHS construction photos
  • March 26 - March 30, 2018 EHS construction photos
  • March 26 - March 30, 2018 EHS construction photos
  • March 26 - March 30, 2018 EHS construction photos
  • March 26 - March 30, 2018 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1B: Auxiliary Gymnasium Remodel

Phase 1: New Construction Classroom Wings

Deliveries:
Area 4A Mezzanine
Area 2 and Area 4 Stairs/Guardrails
Integrated Doors & Door Frames for Areas 3 and 4
Doors with Hardware for Area 2, Levels 1 and 2

Phase 1B:
Auxiliary Gym/Hallway, 920A & B
Selective Roof Demolition, Framing and Infill has begun (weather permitting) and is ongoing.
Roofing work has begun (weather permitting) and is ongoing.
Existing Siding Demolition and Building Wrap Behind has begun (weather permitting) and is ongoing.
Fire Sprinkler Rough-In at Auxiliary Gym is ongoing.
GWB Repair/Finishes are ongoing.
Early Wall/Ceiling Rough-In in Hallway 920A & B as available.

Next Week:
HVAC Rough-In.
Painting of Exposed Structure and Walls (Interior).
Fire Sprinkler Rough-In in Hallway, 920A & B.

Women’s Locker Room
Existing Siding Demolition.
Selective Roof Demolition, Framing and Infill has begun (weather permitting) and is ongoing.
Roofing work has begun (weather permitting) and is ongoing.
Existing Siding Demolition and Building Wrap Behind has begun (weather permitting) and is ongoing.
Chase Wall Plumbing Rough-In has begun.
Early Wall/Ceiling Rough-In as available.

Next Week:
Fire Sprinkler Rough-In.
CMU - New Walls and Infill.

Wrestling Room
Underslab MEP was completed.
Early Wall/Ceiling Rough-In as available.

Next Week:

Steel Erection; Wall Framing; Slab-On-Grade prep and placement at Boiler Room has been rescheduled to week of April 9th.

Phase 1/New Construction:
Area 2
Metal Siding System installation is nearly complete. Ex. Filler Panels, Pcaps, etc. installation remaining.
CFB Siding Installation is ongoing.
Electrical Trim at Level 2 is complete
Finish Carpentry/MDF and Wood Trim installation is ongoing.
Casework/Cabinets/Countertops in additional rooms at Level 2 is ongoing.
Plumbing/Toilet Fixtures installation at Level 1 casework is complete.
IDF 213A Racks, Terminations and Testing is ongoing.
IDF 262 Racks, Terminations and Testing is ongoing.
Doors and Hardware installation at Levels 1 and 2 is ongoing, delayed due to light deliveries.

Next Week:
Plumbing/Toilet Fixtures at Level 2 Casework.
Acoustical Ceiling Tile/Linear Wood at Levels 1 and 2 has been rescheduled to the week of April 9th.
Installation of Steel Stairs and Guardrails.

Area 3
Mechanical Mezzanine Buildout-Duct/Piping/Electrical is ongoing.
Painting at Level 1 is ongoing.
Metal Siding System installation is nearly complete.
CFB Siding installation is ongoing.
Coiling Fire Shutter Installation is complete.
Acoustical Ceiling Grid at Level 1 is ongoing.
GWB Hang/Firetape at Level 2 South Wall is ongoing.
Installation of Light Fixtures at Level 1 Grid is ongoing.
Installation of Light Fixtures at Level 2 Grid is ongoing.
Relite Glazing has begun and is ongoing.
Ceramic Tiling of Level 2 Restroom 356 is complete.
Installation of Storefront & Exterior Doors Entrances at Level 1 is ongoing.
Stage/Ramp Demo, Form, Pour at Existing Commons/Area 3 is ongoing.
Installation of Light Fixtures at Level 1 Grid is ongoing as lights are delivered.
Electrical Trim at Level 1 is complete.

Next Week:
Storefront Window /Opening Sill Pans/Flashings at Level 1.
Storefront and Exterior Doors/Entrances at Level 1.
Expansion/Seismic Joint Cover Installation.
Interior Storefront Installation at Level 2.
Casework/Cabinets & Countertops – Level 2, then Level 1.
Interior Storefront Installation at Level 2.

Area 4-A
Roofing/Low Roof detail work is ongoing as weather permits.
Metal Siding System Installation is ongoing.
Mezzanine Deck Wall Framing and Sheathing is ongoing.
Mechanical Mezzanine Buildout-Duct/Piping/Electrical is ongoing.
Batt Insulation at Level 2 is complete.
Glass Skylight Glazing Installation began on March 26th.

Next Week:
CFB Siding Installation begins.

Area 4-B
Wall/Header Framing NLB/Pick-up is ongoing.
Roofing/Low Roof is ongoing.
Electrical Rough-In of Level 2 is ongoing.
HVAC Rough-In of Level 2 is complete.
GWB Hang/Tape at Level 2 is complete.
GWB Hang/Tape at Level 1 is ongoing.
Electrical Rooms 417 Panels & Terminations are ongoing.
Electrical Wire/Term and Panelwork is ongoing.
Acoustical Ceiling Grid at Level 1 has begun and is ongoing.
Painting at Level 1 is ongoing.
Painting at Level 2 has begun and is ongoing.
Ceramic Tiling of all restrooms has begun and is ongoing.
Installation of Light Fixtures at Level 1 Grid has begun and is ongoing.
Elevator Equipment Room Buildout has begun and is scheduled to be completed by April 6th.

Next Week:
Electrical Trim at Level 1.
ELEVATOR INSTALLATION BEGINS APRIL 30TH!

Building Perimeter and Commons Plaza
Excavation for Seat Walls/Planter Walls/Stair Walls - Footings is complete.
Grading for Hardscape at Courtyard has begun and is ongoing.
FRPS Seat/Planter Footings and Walls is ongoing; pour to occur on Tuesday, April 3rd.
Electrical Rough-In at Seat Walls is complete.

Next Week:
F/P/S Concrete Hardscape at Courtyard has been rescheduled to the week of April 9th.

March 12 - 16, 2018

  • March 12 - March 16, 2018 EHS construction photos
  • March 12 - March 16, 2018 EHS construction photos
  • March 12 - March 16, 2018 EHS construction photos
  • March 12 - March 16, 2018 EHS construction photos
  • March 12 - March 16, 2018 EHS construction photos
  • March 12 - March 16, 2018 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1B: Auxiliary Gymnasium Remodel

Phase 1: New Construction Classroom Wings

Deliveries:
MDF Wall Panels, Level 2
Light Fixtures
Overhead Coiling Doors for areas 2, 3 & 4

Phase 1B:
Auxiliary Gym/Hallway, 920A & B
Ceiling/Wall/GLB
Header/Framing/Furring, etc. is ongoing.
Electrical Rough-In is ongoing.
Early Wall/Ceiling Rough-In as available.

Next Week:
Fire Sprinkler Rough-In
GWB Repair/Finishes

Women’s Locker Room
Underslab MEP.
Early Wall/Ceiling Rough-In as available.
Slab Preparation, F/P/F Footings for Slab-On-Grade has begun.

Next Week:
FRPS Footings, Slab-On-Grade.

Wrestling Room
Interior Demo - Ceilings, Hardwood Floors, Slab-On-Grade is ongoing.
Digging of Auger Piles at Boiler Room was completed.
Early Wall/Ceiling Rough-In as available.

Next Week:
F/R/P/S of Auger Piles at Boiler Room.

Phase 1/New Construction:
Area 2
Metal Siding System installation is ongoing.
CFB Siding Installation is ongoing.
Electrical Trim at Level 1 is ongoing.
Casework/Cabinets/Countertops at Level 2 is ongoing.
Installation of Overhead Coiling Grilles has begun and is ongoing.
Plumbing/Toilet Fixtures installation at Level 1 has begun and is ongoing.
IDF 213A Racks, Terminations and Testing is ongoing.
IDF 262 Racks, Terminations and Testing is ongoing.
Ceramic Tiling of Level 1 is ongoing.
Casework/Cabinets/Countertops installation at Level 1 is ongoing.
Wood Stair Framing is complete.

Next Week:
Finish Carpentry/MDF and Wood Trim.
Acoustical Ceiling Tile/Linear Wood at Level 1.
Doors and Hardware at Levels 1 and 2.
Installation of Steel Stairs and Guardrails.

Area 3
Mechanical Mezzanine Buildout-Duct/Piping/Electrical is ongoing.
Painting at Level 1 is ongoing.
Metal Siding System and CFB Siding is ongoing.
Acoustical Ceiling Grid at Level 1 has begun and is ongoing.
Installation of Light Fixtures at Level 1 Grid has begun and is ongoing.
Installation of Light Fixtures at Level 2 Grid has begun and is ongoing.
Installation of HVAC Diffusers at Level 2 has begun and is scheduled to be completed by March 19th.
Installation of Storefront & Exterior Doors Entrances at Level 1 has begun and is ongoing.
Stage/Ramp Demo, Form, Pour at Existing Commons/Area 3 has begun and is ongoing.
Installation of Light Fixtures at Level 2 Grid has begun and is scheduled to be completed by March 15th.

Next Week:
Coiling Fire Shutters.
Electrical Trim at Level 2.
GWB Hang/Firetape at Level 2 South Wall completion.
Acoustical Ceiling Grid at Level 2.

Area 4-A
Roofing/Low Roof detail work is ongoing.
Metal Siding System Installation is ongoing.
HVAC Rough-In at Levels 1 and 2 is complete.
Mezzanine Deck Wall Framing and Sheathing is ongoing.
Mechanical Mezzanine Buildout-Duct/Piping/Electrical is ongoing.
Batt Insulation at Level 2 has begun and is ongoing.

Area 4-B
Wall/Header Framing NLB/Pick-up is ongoing.
Roofing/Low Roof is ongoing.
Electrical Rough-In of Level 2 is ongoing.
HVAC Rough-In of Level 2 is complete.
GWB Hang/Tape at Level 2 is ongoing.
GWB Hang/Tape at Level 1 is ongoing.
Electrical Rooms 417 Panels & Terminations are ongoing.
Electrical Wire/Term and Panelwork is ongoing.
Painting at Level 1 is ongoing.
Framing/Backing of Elevator Shaft has begun and is scheduled to be completed by March 21st.

Building Perimeter and Commons Plaza
Excavation for Seat Walls/Planter Walls/Stair Walls - Footings is ongoing.
FRPS Seat/Planter Footings and Walls is ongoing.
Electrical Rough-In at Seat Walls is ongoing.

February 19 - February 23

  • February 19 - February 23, 2018 EHS construction photos
  • February 19 - February 23, 2018 EHS construction photos
  • February 19 - February 23, 2018 EHS construction photos
  • February 19 - February 23, 2018 EHS construction photos
  • February 19 - February 23, 2018 EHS construction photos
  • February 19 - February 23, 2018 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1B: Auxiliary Gymnasium Remodel

Phase 1: New Construction Classroom Wings

Deliveries:
Metal Siding for Areas 3 and 4
Shipladders, Stairs, etc. for Area 2
Casework for Area 2, Level 1
Integrated Door Frames for Areas 3 and 4
Glass for Storefronts and Exterior Windows for Area 3, Level 2

Phase 1B:
Setup/Demo
Auxiliary Gym Interior Selective Demolition is ongoing.
Auxiliary Gym Interior Mold Remediation/Removal is complete, Air Testing has occurred.
Electrical Rough-In is ongoing.
Salvage of Lockers and etc. has begun.

Phase 1/New Construction:
Area 2
Metal Siding System installation is ongoing.
Expansion/Seismic Joint Cover Installation is ongoing, weather permitting.
IDF 213A Racks, Terminations and Testing is ongoing.
IDF 262 Racks, Terminations and Testing has begun and is ongoing.
Painting of Toe Kick Plenums at Level 1 is complete.
Installation of Acoustical Ceiling Grid at Level 2, common and adjacent rooms is complete.
Ceramic Tiling of Level 1 has begun and is ongoing.
Casework Ventilation Base - Classrooms, Level 1 is complete.
Gypcrete floor pouring of Level 2 is complete.
Concrete Floor Polishing Level 1 rooms 207 and 209 has begun an is ongoing.
Casework/Cabinets/Countertops installation at Level 1 has begun and is ongoing.

Next Week:
Casework Ventilation Base - Classrooms, Level 2.

Area 3
Storefront and Exterior Doors/Entrances is complete.
Storefront Window/Opening Sill Pans and Flashings at Level 1 is complete.
Stage/Ramp Demolition, Form and Pour is ongoing.
LV Systems Cabling and Terminations is complete.
GWB Hang/Tape of Level 1 is complete.
Metal Siding System and CFB Siding is ongoing.
Acoustical Ceiling Grid at Level 2 has begun and is ongoing.
Gypcrete is complete.

Next Week:
IDF 355/305 B Racks/Terminations/Testing.
Storefront Window Glazing at Level 2.

Area 4-A
Roofing/High Mezz Roof is complete.
Roofing/Low Roof is ongoing.
Metal Siding System Installation is ongoing.
HVAC Rough-In at Level 2 is ongoing.
Mezzanine Deck Wall Framing and Sheathing is ongoing.
Mechanical Mezzanine Buildout-Duct/Piping/Electrical is ongoing.

Next Week:
Batt Insulation at Level 2.

Area 4-B
Wall/Header Framing NLB/Pick-up is ongoing.
Roofing/Low Roof is ongoing.
Electrical Rough-In of Level 2 is ongoing.
HVAC Rough-In of Level 2 is ongoing.
GWB Hang/Tape at Level 1 is ongoing.
Batt Insulation at Level 2 has begun and is ongoing.
Electrical Rooms 417 Panels & Terminations are ongoing.
Electrical Wire/Term and Panelwork has begun and is ongoing.
Storefront Window/Opening Sill Pans/Flashings installation is complete.
Storefront & Exterior Doors/Entrances is complete.
Area Drains/Rain Leaders-Storm Lines/CBs and Tie-Ins was completed.
Fire Hydrant installed on Semanski.

Next Week:
Painting at Level 1.
GWB Hang/Tape at Level 2.
Spray Insulation at Common Wall Grid W1.
Excavation for Seat Walls/Planter Walls/Stair Walls - Footings.
FRPS Seat/Planter Footings and Walls
Electrical Rough-In at Seat Walls

February 12 - February 16

  • February 12 - February 16, 2018 EHS construction photos
  • February 12 - February 16, 2018 EHS construction photos
  • February 12 - February 16, 2018 EHS construction photos
  • February 12 - February 16, 2018 EHS construction photos
  • February 12 - February 16, 2018 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1B: Auxiliary Gymnasium Remodel

Phase 1: New Construction Classroom Wings

Phase 1B:
Setup/Demo
Auxiliary Gym Interior Selective Demolition is ongoing.
Auxiliary Gym Interior Mold Remediation/Removal.
Electrical Rough-In has begun and is ongoing.

Next Week:
GLB Framing/Header.
Wall and Ceiling Framing/Furring.
Cut/Shore Opening at New Alcove.
Demolition/Cut Roof Openings.
Temporary Shoring for New Alcove Framing.

Phase 1/New Construction:
Area 2
Metal Siding System installation is ongoing.
Expansion/Seismic Joint Cover Installation is ongoing, weather permitting.
IDF 213A Racks, Terminations and Testing is ongoing.
Painting of Level 2 Classrooms is complete.
Installation of Acoustical Ceiling Grid at Level 2, common and adjacent rooms is complete.
Casework Ventilation Base - Classrooms, Level 1 has begun.
Clearing and prepping for Gypcrete at Level 2 is complete.
Vinyl Wall Coverings at Level 2 is complete.

Next Week:
Ceramic Tiling of Level 1.
Casework/Cabinets/Countertops - Level 1
Casework Ventilation Base - Classrooms, Level 2.
IDF 262 Racks, Terminations and Testing

Area 3
Storefront and Exterior Doors/Entrances is ongoing.
Electrical Room 305 Wire/Term & Panel Work is complete
Stage/Ramp Demolition, Form and Pour is ongoing.
GWB Hang/Tape of Level 1 is complete.
Metal Siding System and CFB Siding is ongoing.
Acoustical Ceiling Grid at Level 2 has begun and is scheduled to be completed by February 23rd.

Next Week:
Storefront Window/Opening Sill Pans and Flashings at Level 1.
Storefront Window Glazing at Level 2.
Painting at Level 1.
Gypcrete.

Area 4-A
Roofing/High Mezz Roof is complete.
Roofing/Low Roof is ongoing.
Metal Siding System Installation is ongoing.
HVAC Rough-In at Level 2 is ongoing.
Mezzanine Deck Wall Framing and Sheathing is ongoing.
Mechanical Mezzanine Buildout-Duct/Piping/Electrical is ongoing.

Next Week:
Batt Insulation at Level 2.

Area 4-B
Wall/Header Framing NLB/Pick-up is scheduled to be completed by Friday, February 23rd.
Roofing - High Mezz Roof is complete.
Roofing/Low Roof is ongoing.
Electrical Rough-In of Level 2 is ongoing.
HVAC Rough-In of Level 2 is ongoing.
GWB Hang/Tape at Level 1 is ongoing.
Batt Insulation at Level 1 is complete.
Electrical Rooms 417 Panels & Terminations are ongoing.

Next Week:
Skylight Flashing and Skylight Installation will occur the week of February 19th.
Storefront Window/Opening Sill Pans/Flashings.
Storefront & Exterior Doors/Entrances.

February 5 - February 9

  • February 2 - February 9, 2018 EHS construction photos
  • February 2 - February 9, 2018 EHS construction photos
  • February 2 - February 9, 2018 EHS construction photos
  • February 2 - February 9, 2018 EHS construction photos
  • February 2 - February 9, 2018 EHS construction photos
  • February 2 - February 9, 2018 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1B: Auxiliary Gymnasium Remodel

Phase 1: New Construction Classroom Wings

Phase 1B:
Setup/Demo
Auxiliary Gym Interior Selective Demolition is ongoing.

Next Week:
Cut/Shore Opening at New Alcove.
Demolition/Cut Roof Openings.
Temporary Shoring for New Alcove Framing.
Electrical Rough-In will begin.

Phase 1/New Construction:
Area 2
Metal Siding System installation is ongoing.
Expansion/Seismic Joint Cover Installation is ongoing.
HVAC Diffuser installation at Level 1 Grid is complete.
IDF 213A Racks, Terminations and Testing is ongoing.
LV/Systems Cabling and Terminations at Level 2 is complete.
Painting of Level 2 Classrooms is ongoing.
Installation of Acoustical Ceiling Grid at Level 1 is complete.
Installation of Vinyl Wall Coverings at Level 2 is complete.
Installation of Acoustical Ceiling Grid at Level 2 has begun and is scheduled to be completed on Monday, February 12th.
Clearing and prepping for Gypcrete at Level 2 has begun and is scheduled to be completed by Wednesday, February 14th.

Next Week:
Ceramic Tiling of Level 1.

Area 3
Storefront and Exterior Doors/Entrances is ongoing.
Electrical Room 305 Wire/Term & Panel Work is complete
Stage/Ramp Demolition, Form and Pour is ongoing.
GWB Hang/Tape of Level 2 is ongoing.
GWB Hang/Tape of Skylight Wells is complete.
Metal Siding System and CFB Siding is ongoing.

Area 4-A
Roofing is ongoing.
Metal Siding System Installation has begun and is ongoing.
HVAC Rough-In at Level 2 is ongoing.
Mezzanine Deck Wall Framing and Sheathing is ongoing.
GWB Hang/Tape of Level 1 is ongoing.
Electrical Rough-In of Level 1 is ongoing.
Electrical Rough-In of Level 2 is complete.
Mechanical Mezzanine Buildout-Duct/Piping/Electrical is ongoing.

Next Week:
Painting of Level 2

Area 4-B
Wall/Header Framing NLB/Pick-up is ongoing.
Roofing is ongoing, and is scheduled to be completed by Friday, February 16th.
Electrical Rough-In of Level 2 is ongoing.
HVAC Rough-In of Level 2 is ongoing.
HM Frames - Level 1 and 2 is complete.
GWB Hang/Tape at Level 1 is ongoing.
Batt Insulation at Level 1 is ongoing.
Electrical Rooms 417 Panels & Terminations have begun and are ongoing.

Next Week:
Skylight Flashing and Skylight Installation will occur the week of February 19th.

January 29 - February 2

  • January 29 - February 2, 2018 EHS construction photos
  • January 29 - February 2, 2018 EHS construction photos
  • January 29 - February 2, 2018 EHS construction photos
  • January 29 - February 2, 2018 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1B: Auxiliary Gymnasium Remodel

Phase 1: New Construction Classroom Wings

Phase 1B:
Setup/Demo
Pre-Abatement Air Testing was done.
Temporary Fence was placed.
Systems Isolation/Shutdown as Needed for Demolition.
Temporary Lighting/Temporary Power established.
Auxiliary Gym Interior Selective Demolition has begun and is ongoing.

Phase 1/New Construction:
Deliveries:Integrated Door Frames for Area 2.

Area 2
Metal Siding System installation is ongoing.
Expansion/Seismic Joint Cover Installation has begun and is ongoing
Fire Treated Wall Sheathing - Level 1 IDF at #213A was completed.
HVAC Diffusers - Level 1 Grid has begun and is scheduled to be completed by February 7th.
IDF 213A Racks, Terminations and Testing has begun and is ongoing.
LV/Systems Cabling and Terminations at Level 1 is complete.
LV/Systems Cabling and Terminations at Level 2 is ongoing.
Electrical Room 210 Wire/Term and Panel Work is complete.
Painting of Level 1 & 2 Commons and adjacent rooms is complete.
Painting of Level 2 Classrooms is ongoing.
Installation of Acoustical Ceiling Grid at Level 1 is ongoing.
Installation of Vinyl Wall Coverings at Level 1 is complete.

Next Week:
Level 2 clear and prep for Gypcrete.
Installation of Acoustical Ceiling Grid at Level 2.

Area 3
Storefront and Exterior Doors/Entrances is ongoing.
Electrical Room 305 Wire/Term & Panel Work is ongoing.
Stage/Ramp Demolition, Form and Pour is ongoing.
GWB Hang/Tape of Level 2 is ongoing.
Metal Siding System and CFB Siding is ongoing.
Electrical Rough-In of Level 1 Existing Commons/Area 3 was completed and inspected.

Area 4-A
Roofing is ongoing.
West Clearstory Wall Strongback is complete.
Spray Insulation at Common Wall Grid W1 is complete.
HVAC Rough-In at Level 2 is ongoing.
Mezzanine Deck Wall Framing and Sheathing is ongoing.
GWB Hang/Tape of Level 1 has begun and is ongoing.
Electrical Rough-In of Level 1 is ongoing.
Electrical Rough-In of Level 2 has begun and is ongoing.
Mechanical Mezzanine Buildout-Duct/Piping/Electrical is ongoing.

Next Week:
Painting of Level 2
Metal Siding System installation.

Area 4-B
Wall/Header Framing NLB/Pick-up is ongoing.
Plumbing Rough-In at Level 2 is complete.
Roofing is ongoing.
Electrical Rough-In of Level 2 is ongoing.
HVAC Rough-In of Level 2 is ongoing.
HM Frames - Level 1 and 2 is ongoing.
GWB Hang/Tape at Level 1 has begun and is ongoing.
Batt Insulation at Level 1 has begun and is ongoing.

Next Week:
Skylight Flashing and Skylight Installation.
Electrical Rooms 417 Panels & Terminations.

January 22 - January 26

  • January 22 - 26, 2018 EHS construction photos
  • January 22 - 26, 2018 EHS construction photos
  • January 22 - 26, 2018 EHS construction photos
  • January 22 - 26, 2018 EHS construction photos
  • January 22 - 26, 2018 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1B: Auxiliary Gymnasium Remodel

Phase 1: New Construction Classroom Wings

Phase 1B:
Demolition is scheduled to begin on February 1st.
Phase 1B work is scheduled to begin on February 15th.

Phase 1/New Construction:
Area 2
Deliveries:
Metal Siding for Area 2
Windows for Areas 4A/4B Level 2

Metal Siding System installation is ongoing.
LV/Systems Cabling and Terminations at Level 1 is ongoing.
LV/Systems Cabling and Terminations at Level 2 is ongoing.
Electrical Room 210 Wire/Term and Panel Work is ongoing.
GWB Hang/Tape of Level 2 classrooms is complete.
Painting of Level 1 & 2 Commons and adjacent rooms is ongoing.
Painting of Level 2 Classrooms is ongoing.
Installation of Acoustical Ceiling Grid at Level 1 has begun and is ongoing.
Installation of Vinyl Wall Coverings at Level 1 has begun and is ongoing.

Next Week:
Expansion/Seismic Joint Cover Installation.
HVAC Diffusers - Level 1 Grid.
Fire Treated Wall Sheathing - Level 1 IDF at #213A.

Area 3
Exterior GWB Installation and PT Wall Plating prior to Expansion Joint Installation was completed.
Storefront and Exterior Doors/Entrances is ongoing.
Electrical Room 305 Wire/Term & Panel Work is ongoing.
Stage/Ramp Demolition, Form and Pour is ongoing.
GWB Hang/Tape of Level 2 is ongoing.
Metal Siding System and CFB Siding is ongoing.
Electrical Rough-In of Level 1 Existing Commons/Area 3 was completed and inspected.

Area 4-A
Roofing is ongoing.
Exterior Fall Protection Anchors Installation is complete.
Mezzanine Deck Wall Framing and Sheathing is ongoing.
Pre-Rock/Insulation is ongoing.
HVAC Rough-In of Level 1 is complete.
HVAC Rough-In of Level 2 is ongoing.
HM Frames at Level 1 and 2 is ongoing.
Electrical Rough-In of Level 1 is ongoing.
Electrical Rough-In of Level 2 has begun and is ongoing.
Mechanical Mezzanine Buildout-Duct/Piping/Electrical has begun and is ongoing.

Next Week:
Electrical Room 417 and 464 Panels & Terminations.
Batt Insulation of Level 1.

Area 4-B
Wall/Header Framing NLB/Pick-up is ongoing.
Roofing is ongoing.
Electrical Rough-In of Level 2 is ongoing.
HVAC Rough-In of Level 2 is ongoing.
HM Frames - Level 1 and 2 is ongoing.

Next Week:
Electrical Rooms 417 and 464 Panels & Terminations.
Batt Insulation of Level 1.
GWB Hang/Tape Level 1.

January 15 - January 19

  • January 15 - 19, 2018 EHS construction photos
  • January 15 - 19, 2018 EHS construction photos
  • January 15 - 19, 2018 EHS construction photos
  • January 15 - 19, 2018 EHS construction photos
  • January 15 - 19, 2018 EHS construction photos
  • January 15 - 19, 2018 EHS construction photos
  • January 15 - 19, 2018 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1B: Auxiliary Gymnasium Remodel

Phase 1: New Construction Classroom Wings

Phase 1B:
Demolition is scheduled to begin on February 1st.
Phase 1B work is scheduled to begin on February 15th.
The Conex was relocated this week.

Phase 1/New Construction:

Area 2
Metal Siding System installation is ongoing.
Storefront Window/Opening Sill Pans/Flashings were installed.
Storefront & Exterior Doors/Entrances installation has begun and is ongoing.
Exterior GWB and PT Wall Plate Installation prior to Expansion Joint Installation was completed.
LV/Systems Cabling and Terminations at Level 1 has begun and is ongoing.
Electrical Room 210 Wire/Term and Panel Work is ongoing.
GWB Hang/Tape of Level 2 classrooms is ongoing.
GWB Hang/Tape of Level 1 & 2 Commons and adjacent rooms is ongoing.
Painting of Level 1 Classrooms was completed.
Painting of Level 2 Classrooms has begun and is ongoing.

Next Week:
Expansion/Seismic Joint Cover Installation.
LV/Systems Cabling and Terminations - Level 2.
Acoustical Ceiling Grid at Level 1.
Paint of Level 1 & 2 Commons and Adjoining Rooms.

Area 3
Skylight Installation is complete.
Storefront Window/Opening Sill Pans/Flashing installation is complete.
Storefront and Exterior Doors/Entrances has begun and is ongoing.
Electrical Room 305 Wire/Term & Panel Work is ongoing.
Stage/Ramp Demolition, Form and Pour is ongoing.
GWB Hang/Tape of Level 2 is ongoing.
Metal Siding System and CFB Siding is ongoing.

Next Week:
Exterior GWB Installation and PT Wall Plating prior to Expansion Joint Installation

Area 4-A
Roofing is ongoing.
Fall Protection Anchors at Low Roof is complete.
Mezzanine Deck Wall Framing and Sheathing is ongoing.
Pre-Rock/Insulation is ongoing.
HVAC Rough-In of Level 1 is complete.
HVAC Rough-In of Level 2 is ongoing.
HM Frames at Level 1 and 2 is ongoing.
Electrical Rough-In of Level 1 is ongoing.
Electrical Rough-In of Level 2 has begun and is ongoing.
Spray Insulation of Levels 1 and 2 is complete.

Next Week:
Electrical Room 417 and 464 Panels & Terminations.
Mechanical Mezzanine Buildout-Duct/Piping/Electrical.
HM Frames - Levels 1 and 2.
Batt Insulation of Level 1.

Area 4-B
Wall/Header Framing NLB/Pick-up is ongoing.
Roofing is ongoing.
Pre-Rock/Insulation is complete.
HVAC Rough-In of Level 1 is complete.
Electrical Rough-In of Level 1 is complete.
Plumbing Rough-In at Level 2 is complete.
Electrical Rough-In of Level 2 is ongoing.
HVAC Rough-In of Level 2 is ongoing.
HM Frames - Level 1 and 2 is ongoing.
Installation of Skylights and Flashings is complete.

Next Week:
Electrical Rooms 417 and 464 Panels & Terminations.
Batt Insulation of Level 1.

January 8 - January 12

  • January 8 - 12, 2018 EHS construction photos
  • January 8 - 12, 2018 EHS construction photos
  • January 8 - 12, 2018 EHS construction photos
  • January 8 - 12, 2018 EHS construction photos
  • January 8 - 12, 2018 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1B: Auxiliary Gymnasium Remodel

Phase 1: New Construction Classroom Wings

Phase 1B:
Demolition is scheduled to begin on February 1st.
Phase 1B work is scheduled to begin on February 15th.

Phase 1/New Construction:
Deliveries:
Area 4A/4B Level 1 West Side Duct
Vinyl Windows - Area 4 Type W15s

Area 2
Metal Siding System installation has begun and is ongoing.
Electrical Wire/Term & Panel Work is complete.
Electrical Room 210 Wire/Term and Panel Work has begun and is ongoing.
GWB Hang/Tape of Level 2 classrooms is ongoing.
GWB Hang/Tape of Level 1 & 2 Commons and adjacent rooms is ongoing.
Painting of Level 1 Classrooms has begun and is scheduled to be completed by January 19th.

Next Week:
Painting of Level 2 Classrooms.
LV/Systems Cabling and Terminations - Level 1

Area 3
Roofing - Low is complete.
Skylight Flashing installation is complete.
Electrical Wire/Term and Panel work is complete.
Batt Insulation of Level 2 is complete.
Stage/Ramp Demolition, Form and Pour is ongoing.
GWB Hang/Tape of Level 2 is ongoing.
Metal Siding System and CFB Siding is ongoing.

Next Week:
Skylight Installation
Storefront Window/Opening Sill Pans/Flashings
Storefront and Exterior Doors/Entrances
Exterior GWB Installation and PT Wall Plating prior to Expansion Joint Installation

Area 4-A
Roofing is ongoing.
Mezzanine Deck Wall Framing and Sheathing is ongoing.
Spray Insulation of Level 2 is complete.
Pre-Rock/Insulation is ongoing.
HVAC Rough-In of Level 1 is ongoing.
HVAC Rough-In of Level 2 is ongoing.
HM Frames at Level 1 and 2 have has begun and is scheduled to be completed by January 12th.

Next Week:
Electrical Rough-In of Level 2

Area 4-B
Temporary Heat is Operational!
Wall/Header Framing NLB/Pick-up is ongoing.
Roofing is ongoing.
Pre-Rock/Insulation is ongoing.
HVAC Rough-In of Level 1 is ongoing.
Electrical Rough-In of Level 1 is ongoing.
Electrical Rough-In of Level 2 is ongoing.
HVAC Rough-In of Level 2 is ongoing.
HM Frames - Level 1 and 2 is ongoing.

Next Week:
Installation of Skylights and Flashings

January 2 - January 5, 2018

  • January 2 - 5, 2018 EHS construction photos
  • January 2 - 5, 2018 EHS construction photos
  • January 2 - 5, 2018 EHS construction photos
  • January 2 - 5, 2018 EHS construction photos
  • January 2 - 5, 2018 EHS construction photos
  • January 2 - 5, 2018 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1B: Auxiliary Gymnasium Remodel

Phase 1: New Construction Classroom Wings

Phase 1B:
Demolition is scheduled to begin on February 1st.
Phase 1B work is scheduled to begin on February 15th.

Phase 1/New Construction:
Area 2
Mechanical Mezzanine Buildout-Duct/Piping/Electrical is complete.
Electrical Wire/Term & Panel Work is ongoing and scheduled to be completed by January 12th.
Sound Insulation/Pre-Rock is ongoing.
GWB Hang/Tape of Level 2 classrooms is ongoing.
GWB Hang/Tape of Level 1 & 2 Commons and adjacent rooms has begun and is ongoing.

Next Week:
Painting of Level 1 Classrooms

Area 3
Roofing - High Mezzanine Roof is complete.
Electrical Wire/Term and Panel work is ongoing.
Batt Insulation of Level 2 is ongoing.
Stage/Ramp Demolition, Form and Pour is ongoing.
GWB Hang/Tape of Level 2 is ongoing.
Metal Siding System and CFB Siding has begun and is ongoing.

Next Week:
Skylight Installation
Storefront Window/Opening Sill Pans/Flashings
Storefront and Exterior Doors/Entrances
State/Ramp Demo, Form, Pour
Electrical Rough-In in Existing Commons Area

Area 4-A
Roofing is ongoing.
Mezzanine Deck Wall Framing and Sheathing is ongoing.
Spray Insulation of Level 2 is ongoing.
Pre-Rock is ongoing.
HVAC Rough-In of Level 1 is ongoing.
HVAC Rough-In of Level 2 has begun and is ongoing.
HM Frames at Level 1 and 2 have has begun and is scheduled to be completed by January 12th.

Next Week:
Temporary Heat will be operational!

Area 4-B
Wall/Header Framing NLB/Pick-up is ongoing.
Building and Window Opening Wrap is complete.
Spray Insulation of Level 2 is complete.
Roofing is ongoing.
Pre-Rock/Insulation is ongoing.
HVAC Rough-In of Level 1 is ongoing.
Electrical Rough-In of Level 1 is ongoing.
Electrical Rough-In of Level 2 is ongoing.
HVAC Rough-In of Level 2 is ongoing.
HM Frames - Level 1 and 2 is ongoing.

December 18 - December 29, 2017

  • December 18 - December 29 EHS construction photos
  • December 18 - December 29 EHS construction photos
  • December 18 - December 29 EHS construction photos
  • December 18 - December 29 EHS construction photos
  • December 18 - December 29 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1: New Construction Classroom Wings

Phase 1A/Gymnasium (Area 9):
Main Gym - Interior
Gym Flooring Specialist Inspection occurred on December 20th.
Architectural Punch/Back Punch completed week ending December 22nd.

Main Gym - Exterior E/W & N Walls
Metal Panel Siding installation is ongoing.
Rough-In of Added Exterior Lights completed week ending December 22nd.

Phase 1/New Construction:
Deliveries:
Duct for Area 4A/4B Level 1 West Side

Area 2
Fire Sprinkler Riser Room Buildout is complete.
Fire Marshal Inspection occurred on December 19th.
Mechanical Mezzanine Buildout-Duct/Piping/Electrical is ongoing.
Electrical Wire/Term & Panel Work is ongoing.
Sound Insulation/Pre-Rock is ongoing.
GWB Hang/Tape of Level 2 is ongoing.
Storefront Window/Opening Flashing installation is complete.

Area 3
Roofing - Low Roof is complete.
Storefront Window/Opening Sill Pans/Flashings is complete.
Electrical Wire/Term and Panel work is ongoing.
Batt Insulation of Level 2 is ongoing.
Stage/Ramp Demolition, Form and Pour is ongoing.
GWB Hang/Tape of Level 2 is ongoing.
Metal Siding System and CFB Siding has begun and is ongoing.

Area 4-A
Roof Framing/Sheathing of Low Roof is complete.
Roofing is ongoing.
Mezzanine Deck Wall Framing and Sheathing is ongoing.
Early Wall Rough-In is Ongoing.
Spray Insulation of Level 2 is ongoing.
Pre-Rock is ongoing.
HVAC Rough-In of Level 1 is ongoing.
HVAC Rough-In of Level 2 has begun and is ongoing.

Next Week:
Electrical Room 417 and 464 Panels & Terminations.
Mechanical Mezzanine Buildout - Duct/Piping/Electrical.

Area 4-B
2nd Floor Framing/Sheathing and Wall Plating is complete.
Early Wall Rough-In is ongoing.
Wall/Header Framing NLB/Pick-up is ongoing.
Building and Window Opening Wrap is ongoing.
Spray Insulation of Level 2 has begun and is ongoing.
Roofing is ongoing.
Pre-Rock has begun and is ongoing.
HVAC Rough-In of Level 1 is ongoing.
Electrical Rough-In of Level 1 is ongoing.
Electrical Rough-In of Level 2 has begun and is ongoing.
HVAC Rough-In of Level 2 has begun and is ongoing.
HM Frames - Level 1 and 2 has begun and is ongoing.

December 11 - December 15

  • December 11 - December 15 EHS construction photos
  • December 11 - December 15 EHS construction photos
  • December 11 - December 15 EHS construction photos
  • December 11 - December 15 EHS construction photos
  • December 11 - December 15 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1: New Construction Classroom Wings

Phase 1A/Gymnasium (Area 9):
Main Gym - Interior
Architectural Punch/Back Punch completed for Main Gym Interior, Men’s Locker Room, Staff Restroom 903J & North Locker Room, Gym Lobby Addition, and Athletic Offices.

Main Gym - Exterior E/W & N Walls
Horizontal Furring and Rigid insulation installation is ongoing.
Metal Panel Siding installation is ongoing.

Next Week:

Rough-In of Added Exterior Lights
Complete Building Wrap

Phase 1/New Construction:
Deliveries:
Duct for Area 4A/4B East Side
Remainder of HM Door/Relite Frames for Areas 2 and 3
Type W15 Windows for Areas 2, 3 and 4
Interstate Sheet Metal Job Trailer

Area 2
Fire Sprinkler Riser Room Buildout is ongoing.
Batt Insulation of Level 2 is complete.

December 4 - December 8

  • December 4 - December 8 EHS construction photos
  • December 4 - December 8 EHS construction photos
  • December 4 - December 8 EHS construction photos
  • December 4 - December 8 EHS construction photos
  • December 4 - December 8 EHS construction photos
  • December 4 - December 8 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1: New Construction Classroom Wings

Phase 1A/Gymnasium (Area 9)
Main Gym - Exterior E/W & N Walls
Horizontal Furring and Rigid insulation installation is ongoing.
Metal Panel Siding installation is ongoing.

Phase 1/New Construction:
Deliveries:
GWB for Area 2 Level 2
Remainder of HM Door/Relite Frames for Areas 2 and 3
Type W15 Windows for Area 2

Area 2
Window installation is complete.
Vinyl Window Sill Flashing installation is complete.
Fire Sprinkler Riser Room Buildout has begun and is ongoing.
Batt Insulation of Level 2 is ongoing.
Roofing - Low roof - West, East then North - completed.
Skylight Flashings installed.
HVAC Rough-In Level 2 is complete.
Mechanical Mezzanine Buildout-Duct/Piping/Electrical is ongoing.
Electrical Wire/Term & Panel Work is ongoing.
Sound Insulation/Pre-Rock is ongoing.
GWB Hang/Tape of Level 2 has is ongoing.
Metal Siding System and CFB Siding has begun and is ongoing.
Storefront Window/Opening Flashing installation has begun and is ongoing.

Area 3
Fall Protection Anchor installation is complete.
High Mezz Roofing Dry-In is complete.
Roofing is ongoing.
HVAC Rough-In at Level 2 is ongoing.
Electrical Rough-In at Level 1 is ongoing.
Electrical Wire/Term and Panelwork has begun and is ongoing.
Electrical Rough-In of Existing Commons/Area 3 has begun and is ongoing.

Next Week:
Batt Insulation of Level 2 will begin.

Area 4-A
Roof Framing/Sheathing of Low Roof is complete.
Mezzanine Deck Framing and Sheathing is complete.
Mezzanine Deck Wall Framing and Sheathing has begun and is ongoing.
Early Wall Rough-In is Ongoing.
Wall/Header Framing NLB/Pick-up is ongoing.
Spray Insulation of Level 1 is complete
Spray Insulation of Level 2 has begun and is ongoing.

Next Week:
Pre-Rock
HVAC Rough-In of Level 1.

Area 4-B
2nd Floor Framing/Sheathing and Wall Plating is ongoing.
Early Wall Rough-In is ongoing.
Wall/Header Framing NLB/Pick-up is ongoing.
Building and Window Opening Wrap is ongoing.
Spray Insulation of Level 1 has begun and is ongoing.

Next Week:
Roofing/Dry-In (weather depending).
Electrical Rough-In of Level 1.
HVAC Rough-In of Level 1.

November 27 - December 1

  • November 27 - December 1 EHS construction photos
  • November 27 - December 1 EHS construction photos
  • November 27 - December 1 EHS construction photos
  • November 27 - December 1 EHS construction photos
  • November 27 - December 1 EHS construction photos
  • November 27 - December 1 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1: New Construction Classroom Wings

Phase 1A/Gymnasium (Area 9):

Main Gym - Interior
Power switchover DID NOT occur as scheduled on November 18th. Due to an unforeseen emergency for the person handling the safety and grounding equipment, that person was not available to orchestrate that aspect of the switchover. Power switchover scheduling to be coordinated with School.

Main Gym - Exterior E/W & N Walls
Horizontal Furring and Rigid insulation installation is ongoing.
Metal Panel Siding installation is ongoing.

Phase 1/New Construction:
Deliveries:
Vinyl Windows for Areas 3 and 4.

Area 2
Window installation is ongoing.Vinyl Window Sill Flashing installation is ongoing.
Fire Sprinkler Riser Room Buildout has begun and is ongoing.
Batt Insulation of Level 1 is complete.
Batt Insulation of Level 2 is ongoing.
Roofing - Low roof/High roof is ongoing.
Electrical Rough-In Level 2 is complete
HVAC Rough-In Level 2 is ongoing.
Mechanical Mezzanine Buildout-Duct/Piping/Electrical is ongoing.
Electrical Wire/Term & Panel Work is ongoing.
HM Frames at Level 1 and 2 is complete.
Sound Insulation/Pre-Rock is ongoing.
GWB Hang/Tape of Level 2 has begun and is ongoing.

Next Week:
Metal Siding System and CFB Siding installation begins.
Storefront Window/Opening Flashing installation.

Area 3
Temporary Heat is operational!
High Mezz Roof Framing/Sheathing is complete.
Roofing is ongoing.
HVAC Rough-In at Level 2 is ongoing.
Electrical Rough-In at Level 1 is ongoing.

Next Week:
Electrical Wire/Term and Panelwork.
HM Frames - Levels 1 and 2.
Batt Insulation of Level 2 will begin.
Electrical Rough-In of Existing Commons/Area 3.

Area 4-A
Roof Framing/Sheathing of Low Roof is complete.
Mezzanine Deck Framing and Sheathing is ongoing.
Plumbing Rough-In at Level 1 is complete.
Early Wall Rough-In is Ongoing.
Building and Window Opening Wrap is complete.
Spray Insulation of Level 1 is ongoing.

Next Week:
Pre-Rock
HVAC Rough-In of Level 1.
Fire Sprinkler Rough-In at Level 2.
Spray Insulation at Level 2.

Area 4-B
2nd Floor Framing/Sheathing and Wall Plating is ongoing.
Early Wall Rough-In is ongoing.
Wall/Header Framing NLB/Pick-up is ongoing.
Building and Window Opening Wrap is ongoing.

Next Week:
Roofing will begin (weather depending).
Pre-Rock.
HVAC Rough-In of Level 1.

November 20 - November 22

  • November 20 - November 22 EHS construction photos
  • November 20 - November 22 EHS construction photos
  • November 20 - November 22 EHS construction photos
  • November 20 - November 22 EHS construction photos
  • November 20 - November 22 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1: New Construction Classroom Wings

Phase 1A/Gymnasium (Area 9):

Main Gym - Interior

Power switchover DID NOT occur as scheduled on November 18th. Due to an unforeseen emergency for the person handling the safety and grounding equipment, that person was not available to orchestrate that aspect of the switchover. Power switchover will be rescheduled and will occur as soon as possible during the month of December.

Main Gym - Exterior E/W & N Walls
Horizontal Furring and Rigid insulation installation is ongoing.
Metal Panel Siding installation is ongoing.

Phase 1/New Construction:
Deliveries:
Area 3 Level 2 HVAC Duct
Remaining HM Door James for Area 2 and 3.
Additional Vinyl Windows for Area 2.

Area 2
Window installation is ongoing.
Vinyl Window Sill Flashing installation is ongoing.
Batt Insulation of Level 1 is ongoing.
Batt Insulation of Level 2 is ongoing.
Roofing - Low roof/High roof is ongoing.
Electrical Rough-In Level 2 is ongoing.
HVAC Rough-In Level 2 is ongoing.
Mechanical Mezzanine Buildout-Duct/Piping/Electrical is ongoing.
Electrical Wire/Term & Panel Work is ongoing.
HM Frames at Level 1 and 2 is ongoing.
Sound Insulation/Pre-Rock is ongoing.
GWB Hang/Tape of Level 1 has is ongoing.

Next Week:
GWB Hang/Tape of Level 2.
Fire Sprinkler Riser Room Buildout will begin.

Area 3
Storefront Window/Opening Flashings were installed.
Roofing has is ongoing.
HVAC Rough-In at Level 2 is ongoing.
Electrical Rough-In at Level 1 is ongoing.
Spray Insulation of Level 2 is complete.

Area 4-A
2nd Floor Framing/Sheathing is complete.
Roof Framing/Sheathing of Low Roof is ongoing.
Mezzanine Deck Framing and Sheathing is ongoing.
Plumbing Rough-In at Level 1 is complete.
Early Wall Rough-In is Ongoing.
Wall/Header Framing NLB/Pick-up is complete.
Building and Window Opening Wrap is ongoing.
Spray Insulation of Level 1 has begun and is ongoing.

Area 4-B
2nd Floor Framing/Sheathing and Wall Plating is ongoing.
Early Wall Rough-In is ongoing.
Wall/Header Framing NLB/Pick-up is complete.

Fire Sprinkler and HVAC Rough-In will begin after the Thanksgiving Holiday.

November 13th - November 17

  • November 13 - November 17 EHS construction photos
  • November 13 - November 17 EHS construction photos
  • November 13 - November 17 EHS construction photos
  • November 13 - November 17 EHS construction photos
  • November 13 - November 17 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1: New Construction Classroom Wings

Phase 1A/Gymnasium (Area 9):

Main Gym - Interior
Power switchover will occur and be completed on Saturday, November 18th!

Main Gym - Exterior E/W & N Walls
Horizontal Furring and Rigid insulation installation is ongoing.
Metal Panel Siding installation has is ongoing.
Gutter and Downspout installation is complete.

Phase 1/New Construction:
Deliveries:
Area 2 and 3 HM Door Jambs.
Area 2 Vinyl Windows.

Area 2
Window installation has begun and is ongoing.
Vinyl Window Sill Flashing installation has begun and is ongoing.
Batt Insulation of Level 1 is ongoing.
Batt Insulation of Level 2 is ongoing.
Roofing - Low roof/High roof is ongoing.
Electrical Rough-In Level 2 is ongoing.
HVAC Rough-In Level 2 is ongoing.
Mechanical Mezzanine Buildout-Duct/Piping/Electrical is ongoing.
Electrical Wire/Term & Panel Work is ongoing.
HM Frames at Level 1 and 2 is ongoing.
Sound Insulation/Pre-Rock is ongoing.
GWB Hang/Tape of Level 1 has begun and is ongoing.

Area 3
F/P/S Housekeeping Pads were installed (x2).
Roofing has begun is ongoing.
HVAC Rough-In at Level 2 is ongoing.
Fire Sprinkler Rough-In at Level 2 is complete.
Plumbing Rough-In at Level 2 is complete.
Electrical Rough-In at Level 1 is ongoing.
Spray Insulation of Level 1 is complete.
Spray Insulation of Level 2 is ongoing.

Area 4-A
2nd Floor Framing/Sheathing is ongoing.
Mezzanine Deck Framing and Sheathing is ongoing.
Plumbing Rough-In at Level 1 is complete.
Early Wall Rough-In is Ongoing.
Wall/Header Framing NLB/Pick-up is ongoing.

Next Week:
Building and Window Opening Wrap!
Spray Insulation of Level 1.

Area 4-B
2nd Floor Framing/Sheathing and Wall Plating is ongoing.
Early Wall Rough-In is ongoing.
Wall/Header Framing NLB/Pick-up is ongoing.
Plumbing Rough-In at Level 1 is ongoing.
Fire Sprinkler and HVAC Rough-In will begin after the Thanksgiving Holiday.

November 6 - November 10

  • November 6 - November 10 EHS construction photos
  • November 6 - November 10 EHS construction photos
  • November 6 - November 10 EHS construction photos
  • November 6 - November 10 EHS construction photos
  • November 6 - November 10 EHS construction photos

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1: New Construction Classroom Wings

Phase 1A/Gymnasium (Area 9): Main Gym - Interior
Relay Box completion (power switchover) is ongoing.

Main Gym - Exterior E/W & N Walls
Horizontal Furring and Rigid insulation installation has begun and is ongoing.
Metal Panel Siding installation has begun and is ongoing.

Phase 1/New Construction:
Deliveries:
Area 4 Mezzanine/Roof Joists.
Area 2 Mezzanine Level HVAC Ducts.

Area 2
Louvers and Louver Flashing installation complete.
Temporary heat is operational.
Batt Insulation of Level 1 has begun and is ongoing.
Batt Insulation of Level 2 has begun and is ongoing.
Fire Sprinkler Riser Room Buildout is complete.
Roofing - Low roof/High roof is ongoing.
Electrical Rough-In Level 2 is ongoing.
HVAC Rough-In Level 2 is ongoing.
Painting of Fire Sprinkler Riser Room is complete.
Mechanical Mezzanine Buildout-Duct/Piping/Electrical is ongoing.
Electrical Wire/Term & Panel Work is ongoing.
HM Frames at Level 1 and 2 is ongoing.
Sound Insulation/Pre-Rock is ongoing.

Area 3
Temporary Duct removed.
Frame Floor/Place Walls/Frame Mezzanine Deck 2B complete.
Core Board Walls installed.
Fall Protection Anchors and Roof Penetrations completed.
Roofing Dry-In complete.
Roofing has begun and is ongoing.
HVAC Rough-In at Level 2 is ongoing.
Fire Sprinkler Rough-In at Level 2 is ongoing.
Plumbing Rough-In at Level 2 is ongoing.
Electrical Rough-In at Level 1 is ongoing.
Spray Insulation of Levels 1 and 2 is ongoing.

Area 4-A
2nd Floor Framing/Sheathing is ongoing.
Fire Sprinkler Rough-In at Level 1 is complete.
Plumbing Rough-In at Level 1 is ongoing.
Early Wall Rough-In is ongoing.

Area 4-B
2nd Floor Framing/Sheathing and Wall Plating is ongoing.
Early Wall Rough-In has begun and is ongoing.
Wall/Header Framing NLB/Pick-up is ongoing.

October 30 - November 3

  • October 30 - November 3 EHS construction
  • October 30 - November 3 EHS construction
  • October 30 - November 3 EHS construction
  • October 30 - November 3 EHS construction
  • October 30 - November 3 EHS construction

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1: New Construction Classroom Wings

Phase 1A/Gymnasium (Area 9):
Main Gym - Interior
Relay Box completion (power switchover) is ongoing.
Lighting Controls are functional.
Fence around Generator installed.

Lobby Exterior Wall
Installation of Gutters and Downspouts is complete.

Next Week:
Horizontal Furring and Rigid insulation installation begins.
Metal Panel Siding installation begins.

 

Phase 1/New Construction
Deliveries:
Area 4 Mezzanine/Roof Joists.
Area 2 Mezzanine Level HVAC Ducts.
Area 3 HVAC Duct to Replace Temporary Duct.

Area 2
Window Opening Wrap completed.
Roofing - Low roof/High roof is ongoing.
Electrical Rough-In Level 2 is ongoing.
HVAC Rough-In Level 2 is ongoing.
Painting of Fire Sprinkler Riser Room is complete.
Mechanical Mezzanine Buildout-Duct/Piping/Electrical is ongoing.
Electrical Wire/Term & Panel Work is ongoing.
HM Frames at Level 1 and 2 is ongoing.
Sound Insulation/Pre-Rock is ongoing.

Next Week:
Fire Sprinkler Riser Room Buildout.
Batt Insulation of Level 1 will begin.

Area 3
2nd Floor Framing/Sheathing/Erecting is ongoing.
Early Wall Rough-In as available.
Wall/Header Framing and NLB Pick-up is ongoing.
Roof Framing/Sheathing is ongoing.
HVAC Rough-In at Level 1 is complete
HVAC Rough-In at Level 2 is ongoing.
Fire Sprinkler Rough-In at Level 2 is ongoing.
Plumbing Rough-In at Level 2 is ongoing.
Electrical Rough-In at Level 1 is ongoing.
Spray Insulation of Levels 1 and 2 is ongoing.

Area 4-A
2nd Floor Framing/Sheathing is ongoing.
Fire Sprinkler Rough-In at Level 1 is ongoing.
Plumbing Rough-In at Level 1 is ongoing.
Early Wall Rough-In is ongoing.

Area 4-B
2nd Floor Framing/Sheathing and Wall Plating is ongoing.
Early Wall Rough-In has begun and is ongoing.
Next Week:
Wall/Header Framing NLB/Pick-up

October 23 - October 27

  • October 23 - 27 EHS construction
  • October 23 - 27 EHS construction
  • October 23 - 27 EHS construction
  • October 23 - 27 EHS construction
  • October 23 - 27 EHS construction

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1: New Construction Classroom Wings

Phase 1A/Gymnasium (Area 9):

Main Gym - Interior
Relay Box completion (power switchover) is ongoing and is now scheduled to be completed by end of day, today.

Next Week:
Lighting Controls should be functional by November 1st.
Fence around Generator should be installed on October 31st.

Lobby Exterior Wall
Flashing installation is complete.
Complete Building Wrap over CMU is complete.
Siding Installation is ongoing.
Installation of Gutters and Downspouts is complete.

Phase 1/New Construction:
Deliveries:
Area 4 Mezzanine/Roof Joists.
Area 2 Mezzanine Level HVAC Duct.
Area 2 Roofing Materials - Boom Truck will be placing on roof on Monday, October 23rd.

Area 2
Louvers and louver flashing installed.
Roofing - Low roof/High roof is ongoing.
Mechanical Insulation is complete.
Electrical Rough-In Level 2 is ongoing.
HVAC Rough-In Level 2 is ongoing.
Painting of Mezzanine is complete.
Painting of Fire Sprinkler Riser Room is complete.
Mechanical Mezzanine Buildout-Duct/Piping/Electrical is ongoing.
Electrical Wire/Term & Panel Work is ongoing.
HM Frames at Level 1 and 2 has begun and is ongoing.
Sound Insulation/Pre-Rock has begun and is ongoing.

Next Week:
Skylight and Skylight Flashing installation.
Delivery and beginning of window installation.
Batt Insulation of Level 1.
Temporary heating will be operational.

Area 3
Roofing/Dry-In is complete
Spray Insulate of Level 1 is complete.
2nd Floor Framing/Sheathing/Erecting is ongoing.
Early Wall Rough-In as available.
Wall/Header Framing and NLB Pick-up is ongoing.
Roof Framing/Sheathing is ongoing.
HVAC Rough-In at Level 1 is ongoing.
Fire Sprinkler Rough-In at Level 1 is ongoing.
Plumbing Rough-In at Level 1 is ongoing.
Electrical Rough-In at Level 1 is ongoing.

Next Week:
Fire Sprinkler Rough-In at Level 2.
HVAC Rough-In at Level 2.
Spray Insulation of Level 2.

Area 4-A
Wall Framing/Sheathing of 1st Floor is ongoing.
Erection of Red-Iron and GLBs is complete.
2nd Floor Framing/Sheathing is ongoing.
Fire Sprinkler Rough-In at Level 1 is ongoing.

Area 4-B
2nd Floor Framing/Sheathing and Wall Plating is ongoing.
Early Wall Rough-In has begun and is ongoing.

October 16 - October 20

  • October 16 - 20 EHS construction
  • October 16 - 20 EHS construction
  • October 16 - 20 EHS construction
  • October 16 - 20 EHS construction
  • October 16 - 20 EHS construction

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1: New Construction Classroom Wings

Phase 1A/Gymnasium (Area 9):
Deliveries:
Basketball Backstops/Motors

Main Gym - Interior
Relay Box completion (power switchover) is ongoing and is now scheduled to be completed by October 27th.

Next Week:
Lighting Controls should be functional by 11/1/2017.

Lobby Exterior Wall
Flashing installation is ongoing.
Complete Building Wrap over CMU is ongoing.
Siding Installation is ongoing.
Installation of Gutters and Downspouts is ongoing.

Phase 1/New Construction:
Deliveries:
Fall Protection Anchors.
Air Handling Units 301, 302, 401, 402, 403 and 404.
Hardie Siding.
Area 2 Roofing Materials - Boom Truck will be placing on roof on Monday, October 23rd.

Area 2
Building Wrap was completed.
Fall Protection Anchor installation completed.
Roofing - Low roof/High roof is ongoing.
Mechanical Insulation is ongoing.
Electrical Rough-In Level 2 is ongoing.
HVAC Rough-In Level 2 is ongoing.
Painting of Mezzanine is complete.
Painting of Fire Sprinkler Riser Room is complete.
Mechanical Mezzanine Buildout-Duct/Piping/Electrical is ongoing.
Electrical Wire/Term & Panel Work has begun and is ongoing.
GWB - Hang/Tape/Finish Level 3 Mezzanine Walls and Fire Sprinkler Riser Room is complete.
Sound Insulation/Pre-Rock has begun and is ongoing.

Next Week:
HM Frames install Level 1 and 2.

Area 3
2nd Floor Framing/Sheathing/Erecting is ongoing.
Early Wall Rough-In as available.
Wall/Header Framing and NLB Pick-up has begun and is ongoing.
Roof Framing/Sheathing has begun is ongoing.
HVAC Rough-In at Level is ongoing.
Fire Sprinkler Rough-In at Level 1 is ongoing.
Plumbing Rough-In at Level 1 is ongoing.
Electrical Rough-In at Level 1 has begun and is ongoing.

Next Week:
Building wrap!
Fall Protection Anchors to be complete.
Roofing/Dry-In.
Spray Insulate of Level 1.

Area 4-A
Wall Framing/Sheathing of 1st Floor is ongoing.
Erection of Red-Iron and GLBs is ongoing.
2nd Floor Framing/Sheathing is ongoing.
Fire Sprinkler Rough-In at Level 1 is ongoing.

Area 4-B
Wall Framing and Sheathing of 1st floor is ongoing.
Erection of Red-Iron and GluLam Beams is complete.
2nd Floor Framing/Sheathing and Wall Plating is ongoing

October 9 - October 13

  • October 9 - 13 EHS construction
  • October 9 - 13 EHS construction
  • October 9 - 13 EHS construction
  • October 9 - 13 EHS construction
  • October 9 - 13 EHS construction

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition

Phase 1: New Construction Classroom Wings Phase 1A/Gymnasium (Area 9):

Main Gym - Interior
Relay Box completion (power switchover) has begun and is ongoing. Work is scheduled to be completed by Friday, October 20th.

Next Week:
Lighting Controls Rough-In is scheduled for October 17th; should be functional by 11/1/2017.

Athletic Offices
Casework is complete.

Lobby Exterior Wall
Flashing installation is ongoing.
Complete Building Wrap over CMU has begun and is scheduled to be completed by October 18th.
Siding Installation is ongoing.
Installation of Gutters and Downspouts is ongoing.

Phase 1/New Construction:

Area 2
Electrical Rough-In Level 2 is ongoing.
HVAC Rough-In Level 2 has begun and is ongoing.
Spray Insulation and Batting Insulation - Level 3 Mezzanine is complete.
Roofing - Low roof/High roof is ongoing.
Spray Insulation and Batting Insulation - Fire Sprinkler Riser is complete.
Complete Spray Insulation at Level 2 is complete.
GWB - Hang/Tape/Finish Level 3 Mezzanine Walls and Fire Sprinkler Riser Room is ongoing and scheduled to be completed by October 18th.
Sound Insulation/Pre-Rock has begun and is ongoing.

Next Week:
Painting of Mezzanine.
Painting of Fire Sprinkler Riser Room.
Mechanical Mezzanine Buildout - Duct/Piping/Electrical.
Electrical Wire/Term & Panel Work.
Louver and Louver Flashing installation.

Area 3
2nd Floor Framing/Sheathing/Erecting is ongoing.
Early Wall Rough-In as available.
Wall/Header Framing and NLB Pick-up has begun and is ongoing.
Roof Framing/Sheathing has begun and is ongoing.
HVAC Rough-In at Level 1 has begun and is ongoing.
Fire Sprinkler Rough-In at Level 1 has begun and is ongoing.
Plumbing Rough-In at Level 1 has begun and is ongoing.

Next Week:
Building wrap!
Electrical Rough-In at Level 1.

Area 4-A
Wall Framing/Sheathing of 1st Floor is ongoing.
Erection of Red-Iron and GLBs is ongoing.
2nd Floor Framing/Sheathing is ongoing.
Fire Sprinkler Rough-In at Level 1 is ongoing.

Area 4-B
Wall Framing and Sheathing of 1st floor is ongoing.
Erection of Red-Iron and GluLam Beams is complete.
2nd Floor Framing/Sheathing and Wall Plating has begun and is ongoing.

October 2 - October 6

  • October 2 -6 EHS construction
  • October 2 -6 EHS construction
  • October 2 -6 EHS construction
  • October 2 -6 EHS construction
  • October 2 -6 EHS construction
  • October 2 -6 EHS construction

Phase 1A: Gymnasium, Men’s Lockers, Gym Hallway and Lobby Addition
Phase 1: New Construction Classroom Wings

Phase 1A/Gymnasium (Area 9):
Switchover to permanent power is scheduled for week of October 9th – 13th

Gym Lobby Addition
Week of October 9th - 13th
Installation of Display Cases, Glass Shelving for completion.

Athletic Offices
Completion of Casework is scheduled for October 16th and 17th.

Lobby Exterior Wall
Week of October 9th - 13th
Flashing installation.
Complete Building Wrap over CMU.
Siding Installation begins.
Installation of Gutters and Downspouts

Phase 1/New Construction:
Deliveries:
Area 2 - Level 2 HVAC Duct
Fall Protection Anchors

Area 2
Fall protection anchors installed.
Fire Sprinkler Rough-In - Level 2 was completed.
Electrical Rough-In of second floor/mezzanine areas are ongoing.
Electrical Rough-In of first floor is complete.
Early Wall Rough-In as available.
Roofing - Low roof/High roof has begun and is ongoing.
Sound Insulation/Pre-Rock has begun and is ongoing.
Building Wrap was completed.

Next Week:
Spray Insulation and Batting Insulation - Level 3 Mezzanine.
Spray Insulation and Batting Insulation - Fire Sprinkler Riser.
Completion of Spray Insulation at Level 2.
GWB - Hang/Tape/Finish Level 3 Mezzanine Walls and Fire Sprinkler Riser Room.

Area 3
2nd Floor Framing/Sheathing/Erecting is ongoing.
Early Wall Rough-In as available.

Next Week:
Roof Framing/Sheathing.
Wall/Header Framing and NLB/Pick-up.

Area 4-A
Wall Framing/Sheathing of 1st Floor is ongoing.
Erection of Red-Iron and GLBs is ongoing.
2nd Floor Framing/Sheathing is ongoing.
Fire Sprinkler Rough-In at Level 1 is ongoing.

Area 4-B
Wall Framing and Sheathing of 1st floor is ongoing.
Erection of Red-Iron and GluLam Beams is ongoing.

Next Week:
2nd Floor Framing/Sheathing Begins.

September 18 - September 22

  • September 18 - September 22 EHS construction
  • September 18 - September 22 EHS construction
  • September 18 - September 22 EHS construction
  • September 18 - September 22 EHS construction
  • September 18 - September 22 EHS construction

Phase 1A: Gymnasium, Men's Lockers, Gym Hallway and Lobby Addition
Phase 1: New Construction Classroom Wings

Phase 1A/Gymnasium (Area 9):
Men’s Locker Room
1. Metal Locker Ends were delivered and installed.

Gym Lobby Addition
1. MDF staining was completed.

Lobby/Main Gym Exterior Wall
Next Week:
Flashing installation.
Complete Building Wrap over CMU.
Siding Installation begins.
Installation of Gutters and Downspouts
Horizontal Furring and Rigid Insulation.

Phase 1/New Construction:
Deliveries:
Area 2 - Level 2 HVAC Duct

Area 2
Early Wall Rough-In is ongoing.
2nd Floor Framing and Sheathing is ongoing.
Electrical Rough-In Level 1 is ongoing.
Low Roof Framing/Sheathing/Parapet Walls is ongoing.
Mechanical Mezzanine Wall Framing has begun and is ongoing.
Sound Insulation/Pre-Rock has begun and is ongoing.
Plumbing/Fire Sprinkler Rough-In at Level 2 has begun and is ongoing.
Spray Insulation has begun and is ongoing.

Next Week:
Building Wrap.
Hi Roof Framing/Sheathing.

Area 3
2nd Floor Framing/Sheathing and Wall Plating is ongoing.
Early Wall Rough-In as available.

Next Week:
Roof Framing/Sheathing.
HVAC Rough-In at Level 1.

Area 4-A
Wall Framing/Sheathing of 1st Floor is ongoing.

Next Week:
Erection of Red-Iron and GluLam Beams.
2nd Floor Framing/Sheathing Begins.

Area 4-B
Wall Framing and Sheathing of 1st floor is ongoing.

Next Week:
Erection of Red-Iron and GluLam Beams.
2nd Floor Framing/Sheathing Begins.

September 11 - September 15

  • September 11 - September 15 EHS construction
  • September 11 - September 15 EHS construction
  • September 11 - September 15 EHS construction
  • September 11 - September 15 EHS construction
  • September 11 - September 15 EHS construction

Phase 1A: Gymnasium: Boys Locker and Athletic Offices Phase 1: New Construction Classroom Wings

Phase 1A/Gymnasium:

Main Gym Interior
Divider Curtain installation is scheduled for completion by Friday, September 15th.

Men’s Locker Room
Lockers have been installed.
Metal locks for lockers are scheduled for installation by Thursday, September 14th.

Gym Lobby Addition
Display Cases are scheduled to be installed by Friday, September 15th.

New Gym Hallway
Completed for Student Access to Gym Door 901.

Next Week:
Lobby and Gym Exterior Walls will be wrapped; Furring, Rigid Insulation and Siding Installation will begin.

Phase 1/New Construction:
Deliveries:
V-Lux Skylights

Area 2
Early Wall Rough-In is ongoing.
2nd Floor Framing and Sheathing is ongoing.
Electrical Rough-In Level 1 is ongoing.
Low Roof Framing/Sheathing/Parapet Walls is ongoing.
Mechanical Mezzanine Wall Framing has begun and is ongoing.

Next Week:
2nd Floor Wall Framing, NLB/Pickup.
Sound Insulation/Pre-Rock.
Plumbing/Fire Sprinkler Rough-In at Level 2.

Area 3
2nd Floor Framing/Sheathing and Wall Plating is ongoing.

Area 4-A
Wall Framing/Sheathing of 1st Floor is ongoing.

Area 4-B
Wall Framing and Sheathing of 1st floor is ongoing.

September 4 - September 8

  • September 4 - September 8 EHS construction
  • September 4 - September 8 EHS construction
  • September 4 - September 8 EHS construction
  • September 4 - September 8 EHS construction
  • September 4 - September 8 EHS construction

Phase 1A: Gymnasium: Boys Locker and Athletic Offices Phase 1: New Construction Classroom Wings

Phase 1A/Gymnasium:
Main Gym Interior
The Main Gymnasium Interior is complete.

Men’s Locker Room
Lockers are scheduled to be installed the weekend of September 9th - 10th.
Benches, Doors/Hardware and painting are complete.

Staff Bathroom 903J and North Locker
Staff Bathroom 903J and North Lockers are complete.

Gym Lobby Addition
Gym Lobby is complete.

New Gym Hallway
Completed for Student Access to Gym Door 901.

Phase 1/New Construction:
Deliveries:
AHUs 201 - 206 have been delivered.

Area 2
Early Wall Rough-In is ongoing.
2nd Floor Framing and Sheathing is ongoing.
Plumbing/Piping Rough-In is complete.
Mechanical Platform Framing/Sheathing is complete.
Low Roof Framing/Sheathing/Parapet Walls is ongoing; scheduled to be completed by September 15th.

Next Week:
Mechanical Mezzanine Wall Framing Begins.

Area 3
2nd Floor Framing/Sheathing and Wall Plating is ongoing.

Area 4-A
Wall Framing/Sheathing of 1st Floor is ongoing.

Area 4-B
Wall Framing and Sheathing of 1st floor has begun and is ongoing.

August 21 - August 25

 

  • August 21 - 25  EHS construction
  • August 21 - 25  EHS construction
  • August 21 - 25  EHS construction
  • August 21 - 25  EHS construction
  • August 21 - 25  EHS construction
  • August 21 - 25  EHS construction
  • August 21 - 25  EHS construction
  • August 21 - 25  EHS construction

Phase 1A: Gymnasium: Boys Lockers and Athletic Offices
Phase 1: New Construction Classroom Wings
Phase 1A/Gymnasium:
Main Gym Interior
The Main Gymnasium Interior is nearly complete.
Bleachers are installed and operational!
Divider Curtain is scheduled to be delivered on September 14th, and installed on September 15th.
Exterior Infill Framing/Sheathing is ongoing.

Men’s Locker Room
Epoxy flooring has been poured and cured.
Doors and hardware scheduled to be installed and painted by August 29th.
Metal Lockers are scheduled to be delivered on Wednesday, August 30th.
Exterior Infill Framing/Sheathing is ongoing.
Rooftop Units (HVAC) are set and operational.

Next Week:
Staff Bathroom 903J and North Lockers
Owner occupancy is scheduled for Friday, September 1st!

Gym Lobby Addition
Lobby addition is nearly complete, with Back Punch scheduled for completion on Tuesday.
Exterior wall is wrapped!

New Gym Hallway
Work to be complete for Student Access to Gym Door 901 on Friday, September 1st!

Phase 1/New Construction:
Area 2
Early Wall Rough-In is ongoing.
2nd Floor Framing and Sheathing is ongoing.
Plumbing/Piping Rough-In is ongoing.
Pre-Rock Sound Insulation and Fire Tape installed as needed.
HVAC and Electrical Rough-Ins has begun and is ongoing.
Roof Framing/Sheathing began on Friday, August 25th, and is ongoing.

Area 3
Core Board Fire Separation Walls complete.
Erection of Red Iron/GLBs is complete.
2nd Floor Framing/Sheathing and Wall Plating is ongoing.

Area 4-A
Wall Framing/Sheathing of 1st Floor has begun and is ongoing

August 14 - August 18

  • August 14 - 18  EHS construction
  • August 14 - 18  EHS construction
  • August 14 - 18  EHS construction
  • August 14 - 18  EHS construction
  • August 14 - 18  EHS construction

Phase 1A: Gymnasium: Boys Lockers and Athletic Offices
Phase 1: New Construction Classroom Wings
Phase 1A/Gymnasium:
Main Gym Interior
The Main Gymnasium Interior is nearly complete. Bleachers are scheduled to be installed beginning Thursday, August 24th, and the divider being installed on Friday, August 25th.
Exterior Infill Framing/Sheathing is ongoing.

Men’s Locker Room
Epoxy flooring pour is ongoing and scheduled to be completed no later than August 28th.
Fire Alarm Testing occurred today, August 18th.
Exterior Infill Framing/Sheathing is ongoing.

Next Week:
Rooftop Units (HVAC) to be set and operational.

Staff Bathroom 903J and North Lockers
Electrical Trim completed.
Fire Alarm installation completed.
Plumbing Fixtures/Trim installation completed.

Next Week:
Toilet accessories to be installed on Monday, August 21st and occupancy scheduled by August 23rd!

Gym Lobby Addition
Lobby addition is nearly complete, with Back Punch scheduled for completion on Tuesday.
Fire Alarm Testing and Inspection occurred today, August 18th.

Next Week:
Occupancy scheduled for Monday, August 21st!

New Gym Hallway
Dry In/Roofing was completed this week.

Phase 1/New Construction:
Area 2
Early Wall Rough-In is ongoing.
2nd Floor Framing and Sheathing is ongoing.
Plumbing/Piping Rough-In is ongoing.
Pre-Rock Sound Insulation and Fire Tape installed as needed.
HVAC and Electrical Rough-Ins has begun and is ongoing.

Area 3
1st Floor walls is ongoing.
Erection of Red Iron/GLBs is ongoing.
2nd Floor Framing/Sheathing and Wall Plating is ongoing.

Area 4-A

Wall Framing/Sheathing of 1st Floor has begun and is ongoing.

July 31 - August 4

  • July 31 - August 4  EHS construction
  • July 31 - August 4  EHS construction
  • July 31 - August 4  EHS construction
  • July 31 - August 4  EHS construction
  • July 31 - August 4  EHS construction
  • July 31 - August 4  EHS construction

Phase 1A: Gymnasium: Boys Lockers and Athletic Offices Phase 1 : New Construction Classroom Wings

Phase 1A/Gymnasium:
Main Gym Interior
GWB Hang/Tape/Finish is complete.
Acoustical F-Sorb Ceiling Panels installed.
Painting of exposed structure/Conduit/HVAC/GWB/Tectum completed.
Doors/Hardware installation is ongoing.
Electrical Wire/Termination and Panelwork is complete.
Light Fixtures installed.
Court insert placement and pour has begun and scheduled to be completed by August 8th.
HVAC Startup/Operational

Next Week:
Scoreboard Installation.
Installation of Wall Pads/Backstops/Hoops/Volleyball Poles/etc.
Floor protection will be removed on August 9th.
Final Cleaning is scheduled for August 11th!

Men’s Locker Room
Electrical/HVAC/Fire Sprinkler Rough-In/Trim at Ceiling grid completed.
AV/Systems Cabling and Terminations is complete.
Ceramic Floor/Wall Tile is ongoing.
Fire Alarm/HVAC Trim complete.

Staff Bathroom 903J and North Lockers
Ceramic Floor Tile Installation is ongoing.
Electrical Trim complete.
Fire Alarm install complete.

Gym Lobby Addition
Painting of Walls/Soffits is ongoing.
Electrical Trim/Fire Alarm/IDF 6 Buildout/AV/Systems Cabling and Terminations ongoing and scheduled to be completed by August 7th.

Next Week:
Final Cleaning!

Athletic Offices
GWB-Hang/Tape/Finish is complete.
Painting/VWC Walls complete.
Electrical/Trim, Fire Sprinkler Rough-In, Trim at ceiling is ongoing and scheduled to be completed by August 7th.
Casework installation is ongoing and scheduled to be completed by August 8th.
Flooring installation is ongoing and scheduled to be completed by August 8th.

Next Week:
Final cleaning!

New Gym Hallway
Pour/Strip Footings completed.
Form Stemwalls complete.
Placement of Anchor/HD Bolts in Stemwalls completed

Next Week:
Slab Prep/SOG Re-inforcing.
Placement of SOG and Finish
Pre-Fab wall installs
Erection of Walls and Red Steel

Phase 1/New Construction:

Area 2
Early Wall Rough-In is ongoing.
2nd Floor Framing and Sheathing is ongoing.
Plumbing/Piping Rough-In is ongoing.
Pre-Rock Sound Insulation and Fire Tape installed as needed.
HVAC and Electrical Rough-Ins has begun and is ongoing.

Area 3
1st Floor walls is ongoing.
Erection of Red Iron/GLBs is ongoing.
2nd Floor Framing/Sheathing and Wall Plating is ongoing.

Area 4-A
Wall Framing/Sheathing of 1st Floor has begun and is ongoing.

July 24 - July 28

  • July 24 - 28  EHS construction
  • July 24 - 28  EHS construction
  • July 24 - 28  EHS construction
  • July 24 - 28  EHS construction
  • July 24 - 28  EHS construction

Phase 1A: Gymnasium: Boys Lockers and Athletic Offices Phase 1 : New Construction Classroom Wings

Phase 1A/Gymnasium:
Deliveries:
Tectum and Remainder of F-Sorb.
Doors with Hardware Installed.
Bleachers

Main Gym Interior
Wood Flooring Curing Period completed on July 25th.
Installation for backing for Sports Equipment completed.
Acoustical F-Sorb Ceiling Panel installation.
Painting of exposed structure/Conduit/HVAC/GWB/Tectum began on Friday, July 28th.
Doors/Hardware installation began.
Electrical Wire/Termination and Panel work is ongoing through August 4th.

Next Week:
Electrical Trim and Fire Alarm installation.
Placement/Pour of New Court Inserts will begin.
HVAC Startup/Operational.

Men’s Locker Room
GWB Hang/Tape/Finish was completed.
Painting of walls and ceiling is ongoing.
AV/Systems Cabling and Terminations.
Resilient Floor Tile installed.
Ceramic Floor/Wall Tile installation.
Fire Alarm Installation has begun and is ongoing.
Epoxy Flooring placement is ongoing and scheduled to be completed by August 4th.

Next Week:
HVAC Trim.

Staff Bathroom 903J and North Lockers
GWB Hang/Tape/Finish is complete.
Painting of Walls and Ceiling is complete.
Casework & FRL Wall Panels has begun.

Next Week:
Ceramic Floor Tile Installation.
Plumbing Fixtures/Trim
Electrical Trim.
Fire Alarm Installation.

Gym Lobby Addition
Setting of HM Door Frames and Vinyl Windows completed.
Building Wrap completed.
GWB Hang/Tape/Finish is ongoing.
Acoustical Ceiling Grid installed.
Electrical Trim, Fire Alarm, IDF 6 Buildout ongoing.

Athletic Offices
GWB-Hang/Tape is ongoing.

Next Week:
Painting/VWC Walls.
Acoustical Ceiling Grid.
Electrical/HVAC/Fire Sprinkler Rough-In/Trim at Ceiling Grid.

New Gym Hallway
Next Week:
Pour/Strip Footings.
Form Stemwalls
Placement of Anchor/HD Bolts in Stemwalls

Phase 1/New Construction:
Hardscape/site element demo continues

Area 2
Early Wall Rough-In is ongoing.
2nd Floor Framing and Sheathing is ongoing.
Plumbing/Piping Rough-In is ongoing.
Pre-Rock Sound Insulation and Fire Tape installed as needed.
HVAC and Electrical Rough-Ins has begun and is ongoing.

Next Week:
Plumbing/Piping Rough-In at Grids E1 and E2
Fire Sprinkler Rough-In

Area 3
Core Board Fire Separation Walls was completed.
2nd Floor Framing/Sheathing and Wall Plating is ongoing and scheduled to be completed by August 4th.

Next Week:
2nd Floor Framing/Sheathing and Wall Plating.

Area 4-A
Place/Finish/Sofcut Control Joints, SOG/Cure completed on Friday, July 28th.

Next Week:
Erection of Red-Iron and Glulam Beam
Wall Framing/Sheathing of 1st Floor
Core Board Fire Separation Walls

July 10 - July 14

  • July 10 - 14 EHS construction
  • July 10 - 14 EHS construction
  • July 10 - 14 EHS construction
  • July 10 - 14 EHS construction
  • July 10 - 14 EHS construction
  • July 10 - 14 EHS construction

Phase 1A/Gymnasium:
Main Gym Interior
HM Door Jamb installation completed on July 11th.
Wood Floor installation is ongoing and is scheduled to be completed by July 17th.
Wood Floor Sand/Seal/Striping/Finish is ongoing through July 20th.
Floor Mural Painting began on July 13th and is ongoing through July 18th.

Next Week:
Wood Flooring Curing Period begins July 20th.

Men’s Locker Room
GWB Hang/Tape/Finish is ongoing through July 21st.
Mechanical Insulation and Cover Inspection was completed on July 11th.
Hardlid Framing was completed on July 11th.
HVAC Rough-In at Hardlid was completed on July 11th.
Electrical Rough-In at Hardlids and cover inspection occurred on July 14th.

Next Week:
Paint Walls and Ceiling.
Fire Alarm Installation (continuing through July 19th).
Acoustical Ceiling Grid placement.
Electrical/HVAC/Fire Sprinkler Rough-In/Trim @ceiling grid.
AV Systems Cabling and Terminations.

Staff Bathroom 903J and North Lockers
GWB Hang/Tape/Finish is ongoing through July 19th.
SOG placed July 13th.
Electrical Wall/Ceiling Rough-In completed on July 11th.

Next Week:
Painting of Walls and Ceiling.

Gym Lobby Addition
Pour/Strip Footings/Stemwalls completed on July 14th (pour on Jul 13th).
Re-Steel Inspection occurred on July 12th.
Perimeter Rigid Insulation install and Damproof Prep of Stemwalls completed on July 14th.
MEP Wall/Soffit Rough-In continues through July 20th.
Exterior/Interior Wall/Soffit Framing/Sheathing is ongoing through July 21st.

Next Week:
Setting of HM Door Frames and Vinyl Windows.
GWB Hang/Tape/Finish begins.

Athletic Offices
Wall Framing completed on July 12th.
MEP Rough-In completed on July 14th.
HM Door/Window Frames set on July 14th.

Next Week
GWB Hang/Tape.

New Gym Hallway
Over excavation of footings and structural fill to grade completed on July 11th.
Form Footings placed on July 13th.
Re-steel of Footings/Stemwalls.

Next Week:
Pour/Strip Footings.

Phase 1/New Construction:
Hardscape/site element demo continues

Area 2
Early Wall Rough-In is ongoing.
Erection of Red-Iron/GLBs completed on July 6th.
2nd Floor Framing and Sheathing is ongoing.
Plumbingh/Piping Rough-In is onging.
Core Board and Fire Walls at South side of 100 Bldg., Grid EA, completed on July 14th.
Wall infills/re-frame of South Wall of 100 Bldg. completed on July 5th.

Area 3
Framing of new openings in South Wall Commons completed.
Erection of Red Iron/GLBs completed.
Wall framing/sheathing of 1st floor continues through July 21st.

Next Week:
2nd Floor Framing/Sheathing and Wall Plating.

Area 4-A
Deliveries:
Area 4 GL Beams scheduled to be delivered.

Underslab Electrical completed.

Next Week:
SOG Reinforcing.
6” Cap Break placement.
Slab prep.

July 3 - July 7

  • July 3 - 7 EHS construction
  • July 3 - 7 EHS construction
  • July 3 - 7 EHS construction
  • July 3 - 7 EHS construction
  • July 3 - 7 EHS construction

Phase 1A/Gymnasium:
Deliveries:
Court Inserts scheduled to be delivered on July 10th
Toilet Partitions scheduled to be delivered on July 10th

Main Gym Interior
HM Door Jamb installation completed on July 5th.
GWB Hang/Tape/Finish behind bleachers completed on July 5th.
Electrical Trim is ongoing through July 14th.
Fire Alarm installation is ongoing through July 19th.
Wood Floor installation is ongoing and is scheduled to be completed by July 17th.

Next Week:
Wood Floor Sand/Seal/Striping/Finish (scheduled to be completed by July 20th)
Floor Mural Painting beginning on July 13th.

Men’s Locker Room
GWB Hang/Tape/Finish is ongoing through July 14th.

Next Week:
Installation of Doors and Hardware.
Fire Alarm Installation (continuing through July 19th).

Staff Bathroom 903J and North Lockers
GWB Hang/Tape/Finish is ongoing through July 13th.

Next Week:
Painting of Walls and Ceiling.

Gym Lobby Addition
Next Week:
GWB Hang/Tape/Finish begins and will be ongoing through July 18th.

Athletic Offices
HM Door/Window Frame setting completed on July 7th.
Paint/VWC Walls completed on July 7th.

Next Week:
Installation of Acoustic Ceiling Grid.
Electric/HVAC/Fire Sprinkler Rough-In/Trim at Ceiling Grid.
AV/Systems Cabling and Terminations.

New Gym Hallway
Next Week:
Over excavation of footings and structural fill to grade.
Re-steel of Footings/Stemwalls

Phase 1/New Construction:
Hardscape/site element demo continues

Area 2
Wall Framing/Sheathing of 1st floor completed on July 6th.
Early Wall Rough-In is ongoing.
Erection of Red-Iron/GLBs completed on July 6th.
2nd Floor Framing and Sheathing is ongoing.
Core Board and Fire Walls at South side of 100 Bldg., Grid EA, completed on July 7th.
Wall infills/re-frame of South Wall of 100 Bldg. completed on July 5th.

Area 3
Framing of new openings in South Wall Commons completed on July 6th.
Erection of Red Iron/GLBs completed on July 6th.
Wall framing/sheathing of 1st floor continues through July 14th.

Next Week:
2nd Floor Framing/Sheathing and Wall Plating.

Area 4-A
Deliveries:
Area 4 GL Beams scheduled to be delivered in July 10th.

1. Underslab Plumbing completed on July 3rd
2. Underslab Electrical completed on July 7th.

Next Week:
SOG Reinforcing.
Concrete (SOG) pour scheduled for Thursday, July 13th.

June 25 - June 30

  • June 25 - 30 EHS construction
  • June 25 - 30 EHS construction
  • June 25 - 30 EHS construction
  • June 25 - 30 EHS construction
  • June 25 - 30 EHS construction
  • June 25 - 30 EHS construction

Work Description: Please note: Activities may change and are weather dependent
Phase 1A: Gymnasium, Boys Lockers, Girls Lockers, and Athletic Offices

Phase 1: New Construction Classroom Wings

Phase 1A/Gymnasium:
Deliveries: Roof Top Units and Vinyl Windows delivered June 26th.
Toilet Accessories delivered on June 30th.

Main Gym Interior
Painting is scheduled to begin on July 13th.
Hardwood material is onsite.
Divider curtain will be delivered July 20th/21st.
Flooring finishes are expected to be completed by August 2nd.
Scoreboard installation will occur on July 31st.
Bleachers scheduled to be delivered on July 27th.
Wood floor sanding, finishing and painting will be done over the next two weeks.
Mural will ready July 13th for painting of court lines.
Structural Steel installed at New Drinking Fountain on June 29th.
New opening for Drinking Fountain was completed on June 30th.
Insulation at Tectum Wall panels occurred on June 26th.
HM Door Jamb installation began on June 30th and is scheduled to be completed by July 5th.
GWB Hang/Tape/Finish behind bleachers is ongoing through July 5th.
HVAC Diffusers installation completed on June 26th.
AV/Stems Cabling and Terminations was completed on June 30th.
Electrical Trim, Fire Alarm installation is ongoing.
Stock/Acclimation of Wood Flooring occurred on June 26th and 27th.
Wood Floor installation is ongoing and is scheduled to be completed by July 16th.

Men’s Locker Room
Mechanical, Plumbing, Electrical, HVAC, Fire Sprinkler rough in began June 26th and is ongoing.
Door jambs arrived and are ready for installation.
Insulation installed June 26th through June 28th.
Installation of HM Door Jambs began on 29th and is scheduled to be completed by July 5th.
GWB Hang/Tape/Finish began on June 27th and is scheduled to be completed by July 7th.
Fire Alarm installation is ongoing through July 19th.
Casework and benches installation will begin week of July 17th.

Staff Bathroom 903J and North Lockers
Sawcut and demolition of slab occurred on June 28th.
Selective Restroom demolition occurred on June 26th.
Underslab/Wall Plumbing Rough-In occurred June 26th through 30th.

Next Week:
Backfill/Prep for Slab On Grade
Placement and Finish of Slab On Grade (concrete pour)
Electrical Wall and Ceiling Rough-In
HVAC Rough-In
GWB Hang/Tape/Finish begins and is scheduled to be completed by July 13th.

Gym Lobby Addition
North Wall - Exterior Wall Framing/Sheathing occurred on June 26th and 27th.
West Wall - 2” H Stud Core Board Wall installed June 26th and 27th.
West Wall Frame/Sheet was completed on June 30th.
Setting of HM Door Frames and Vinyl Windows began on June 28th and is scheduled to be completed by July 6th.
Metal Roof Pan Deck installed on June 28th.
Interior Wall/Soffit Framing - IDF and AV ongoing through July 5th.
MEP Wall/Soffit Rough-In began June 30th and is scheduled to be completed by July 7th.
Excavation of remaining footings occurred on June 26th.
Re-steel of Footing and Stemwalls occurred on June 27th.
(Pour) 28th
Pour of Strip Footings and Stemwalls occurred on June 28th.
Perimiter Rigid Insulation installed June 29th.
12” Sub Base placement occurred June 29th.
6” Cap Break placement on June 29th.
Slab Prep and SOG reinforcement completed June 30th.
Place/Finish/Sofcut of control joints for SOG on 30th

Next Week:
Dampproofing of Stemwalls.
Exterior/Interior Wall/Soffit Framing/Sheathing.
Setting of HM Door Frames and Vinyl Windows.
MEP Wall/Soffit Rough-In.

Athletic Offices
GWB Hang/Tape completed on June 30th.

Next Week:
Setting of HM Door/Window Frames
Paint/VWC Walls - ongoing

Gym Hallway
Over excavation of footings and structural fill to grade completed on June 28th.
Form Footings completed on June 30th.
Re-steel of Footings/Stemwalls began on June 30th and scheduled to be completed by July 3rd.

Locker Room Roof
Parapet/2X Nailer/Framing/installation completed on June 26th.
Selective Siding Demolition on West Side completed on June 26th.
Roofing is ongoing.

Coaches’ Office Roof
Demolition completed on June 28th.
Parapet/2X Nailer/Fire Ply Framing/Installation completed on June 30th.
Dry in roof completed on June 30th.

Next Week:
Roofing scheduled to begin July 7th.

Phase 1/New Construction:
Deliveries:
Area 3 2nd floor bar joists delivered
Area 4 A/B structural steel delivered.

Hardscape/site element demo continues
Area 2 continuing framing of structural walls at the North side. Floor joints will be placed Friday. HVAC / Fire Sprinkler and plumbing rough will start July 10th.
Area 3/South wall of commons in progress. Doors will be removed and infilled. Wall in front will be constructed ongoing.
Sprinkler Riser Room will be stubbed up the first week of July.
4A slab is scheduled for July 13th.
4B concrete installed June 29th.
NE Corner Counseling is occurring June 26th. Windows will be removed and siding will be removed. The window will be removed and framed in tomorrow. It will be finished prior to August.
Trusses being delivered 6/28 for Area 2.
Truss additional delivery will be mid July.
FDC work outside of entry of HS work is ongoing. FDC re-route is underway.  Cold patch will be done immediately, concrete will ultimately be done prior to school starting.

Area 2
Concrete poured June 29th.
Wall framing/sheathing of 1st floor completed on June 28th.
Erection of Red Iron/GLBs completed on June 30th.
Floor Joints placed on June 30th.
2nd floor framing/sheathing and wall plating continues and is scheduled to be completed by 7/14.
Early wall Rough-In is continuing.
Core board fire walls of s side of bldg. 100 installed as ready beg on 6/29 stbcb 7/7
Select demolition at South Wall of 100 Bldg. completed on June 30th.
Wall infills and re-frame of South Wall of 100 Bldg. began June 29th and is scheduled to be completed by July 5th.

Next Week:
Framing of Sprinkler Riser Room.
HVAC/Fire Sprinkler and Plumbing Rough-In will begin July 10th.

Area 3
Framing of new openings at South Wall began on June 28th and continues through July 5th.
Wall framing/sheathing of 1st floor began on June 28th and should be completed by July 14th.

Next Week:
Erection of Red Iron and GLBs
Core Board Fire Separation Wall installation

Area 4-A
Pour/strip stemwalls and remainder of footings completed on June 26th.
Perimeter Rigid insulation install completed on June 27th.
12” Sub Base placement completed June 29th.
Underslab plumbing began June 28th and is scheduled to be completed by July 3rd.
Underslab electrical placement began June 28th and is scheduled to be completed by July 7th.
Preparation and damproofing of stemwalls was completed on June 27th.

Area 4-B
6” cap break placed on June 26th
SOG Reinforcing on June 28th.
Stemwalls prep and dampproofing completed on June 27th.

June 19 - June 23

  • June 19 - 23 EHS construction
  • June 19 - 23 EHS construction
  • June 19 - 23 EHS construction

Work Description: Please note: Activities may change and are weather dependent
Phase 1A: Gymnasium, Boys Lockers, Girls Lockers, and Athletic Offices

Phase 1: New Construction Classroom Wings
Sitework: Fire Department Connection (FDC) re-route will occur on June 26th in front of the school entryway. On Monday, June 26th, access to the HS Admin will be closed off and will be diverted to the Staff Lounge or another route.

South wall of Admin Counselor Offices scheduled for demo on June 26th.

Phase 1A/Gymnasium:
Main Gymnasium :
Painting is ongoing; painting of exposed trusses and ducts is complete.
South and East walls: Cover inspection cleared and completed.
North and West walls: GWB at the walls and the really high locations are being completed.
CMU infills were completed on Friday, June 23rd. Lobby framing will occur this week, including the AV and IDF. Formation of South Lobby footings begins after school is out.
Hardwood material is onsite. Hardwood install will occur the 27th. Sand, finish coats, painting lines occurring the seal coat (three days). Mural will be done at this time (27, 28th). Divider curtain being delivered July 20/21th. The flooring finishes are expected to be completed August 2nd.
Owner Furnished items coordinated July 26th/27th through the 30th. Scoreboard delivered on Thursday, June 22nd.
Roof stripped and being stocked and protected on June 21st.
Gym lobby slab on grade is partially completed; remaining areas will be constructed after June 26 (after school is out).

Locker Rooms:
Locker Room: Mechanical and fire sprinkler work is ongoing. Scaffolding was removed on June 21st to make way for the epoxy flooring prep.
Gym: Roof stripped/being stocked and protected today.

Phase 1/New Construction:
Area 2:
Science floor framing/floor sheathing begins this week. HVAC and Fire Sprinkler rough in will begin the week of July 10th.

Area 3:
South wall of commons in progress. New sheathing for existing wall in progress. Coreboard install at this wall will occur on July 5th.
Sprinkler Riser Room will be stubbed up the first week of July.

Area 4:

Area 4B inspection occurred on Friday, June 23rd.
Concrete pour will occur on Thursday, June 29th.
Area 4A stem walls and footings will be completed by Friday the 30th. This will complete the stem walls and footing concrete for Phase 1!
NE Corner Counseling is occurring June 26th. Counseling will move out. Windows will be removed and infilled.

Site Work:
Area 4B will be going to subgrade currently. Prep for pour on June 29th.
Sewer line extension. Locates began on the June 23rd.

June 12 - June 16

  • June 12 - 16 EHS construction
  • June 12 - 16 EHS construction
  • June 12 - 16 EHS construction
  • June 12 - 16 EHS construction
  • June 12 - 16 EHS construction

Work Description: Please note: Activities may change and are weather dependent
*Phase 1A: Gymnasium: Boys Lockers: Girls Lockers and Athletic Offices

* Phase 1: New Construction Classroom Wings
*
Sitework: Fire Department Connection (FDC) re-route - occur June 26h (after school). It will be in front of the entry of the school. South wall of Admin Counselor demo June 26th


 

 

 

 

 

 

Hardscape/Site Elements Demo is ongoing as needed.

Phase 1A/Gymnasium:
Painting of exposed Structural/Electrical Conduit/HVAC was completed.
Installation of Acoustical F-Sorb Ceiling Panels has begun and will continue through next week.
GWB Hanging, Taping and Finish is still ongoing; scheduled to be completed by June 20th.
Doors and Hardware installation began this week; scheduled to be completed by June 20th.

Next Week:
Installation of Acoustical Tectum Wall Panels.
Wall painting begins.
Installation of HVAC Diffusers
Installation of AV/Systems Cabling and Terminations begins.
Install of Electrical Trim, Fire Alarm
Acclimation of Wood Flooring scheduled to begin, as well.

Phase 1A/Gym Lobby Addition
2” H Stud Core, Board Wall, Framing and Sheet completed on West Wall.
Interior Wall/Soffit Framing and IDF completed.

Next week:
HM Door Frames and Vinyl Window installation.
MEP Wall/Soffit Rough-In scheduled.

Phase 1A/Athletic Offices
MEP Rough Wall Rough continues.

Phase 1/A Mens Locker Room
CMU Infills and new walls completed.
Plumbing, electrical and HVAC
Rough-In completed.
Fire Sprinkler Rough-In completed.
Insulation completed.
GWB Hanging/Taping/Finish began and is ongoing through next week.
Doors/Hardware installation began, scheduled to be completed by June 20th.

Phase 1/New Construction:
Contractor is continuing to excavate for footings and foundations. Pouring concrete in Area 4A approx. June 29th.
Area 2 is poured out. Area 3 pour is complete.
Framing of first floor continues in Area 2 and is nearly complete.
Red-Iron/GLBs erected in Area 2 and Area 3.
Strip Stem Walls poured in Areas 4A and 4B.
Rigid insulation around perimeter installed in Area 4B.
12” Sub Base placed in Area 4B

Next Week:
Underslab plumbing and electrical.
Additional Strip Stemwalls scheduled to be poured on June 21st, with rigid insulation for same to be installed thereafter.
Wall Framing/Sheathing of 1st floor in Area 3.

Site Work:
New FDC (fire department connection) at the NE corner of the building, (South side/near counselor office). This work service won’t be done until after school is out the week of the 26th.

June 2 - June 9

  • June 2 - 9 EHS CMU grouting
  • June 2 - 9 EHS area 4a forms
  • June 2 - 9 EHS gym interior
  • June 2 - 9 EHS gym lobby
  • June 2 - 9 EHS framing walls

Work Description: Please note: Activities may change and are weather dependent
*Phase 1A: Gymnasium: Boys Lockers: Girls Lockers and Athletic Offices

* Phase 1: New Construction Classroom Wings
*
Sitework: Fire Department Connection (FDC) re-route - occur June 26h (after school). It will be in front of the entry of the school. South wall of Admin Counselor demo June 26th

Phase 1A/Gymnasium
Fire Sprinkler Rough In was completed. Test of entire system will be done later, but testing of Gym occurring this week.
HVAC Rough In was completed.
GWB Hang/Tape/Finish is ongoing; should be completed by June 20th.
Plumbing and Electrical Rough In is ongoing; should be completed next week.
Painting is ongoing.
East and West walls: Framing is done, prepped for acoustical ceiling material.
Bleachers furring is occurring.
Locker Room: Roof stripped and protected today.
Gym: Roof stripped/being stocked and protected today.
Bleachers will be delivered July 20th. Hardwood install will occur the 27th. Sand, finish coats, painting lines occurring the seal coat (three days). Mural will be done at this time. The flooring finishes is expected to be completed August 2nd.
Owner Furnished items coordinated July 26th/27th through the 30th. Scoreboard is being delivered on Thursday.

Phase 1A/Gym Lobby Addition
North Wall - Exterior Wall Framing/Sheathing was completed.
Metal Roof Deck was completed.
Gym lobby slab on grade is scheduled to partially complete June 6th, remaining area will be constructed after June 26 (after school is out).

Phase 1A/Athletic Offices
Slab-On-Grade re-steel completed.
Vapor Barrier installed.
H-Stud Core Board Wall - Level 1 - is ongoing; should be completed next week.
Framing is complete
MEP Rough Wall Rough In began on June 8th and is ongoing through June 19th.
Structural slab and footing rebar being doweled in. Friday, June 9th, footings are scheduled to be poured.

Phase 1/A Mens Locker Room
Structural grout of CMU is ongoing.
Roof stripped and protected today.
Gym: Roof stripped/being stocked and protected today.
Gym lobby slab on grade is scheduled to partially complete June 6th, remaining area will be constructed after June 26 (after school is out).
Athletic office structural slab and footing rebar being doweled in. Friday, June 9th, footings are scheduled to be poured.

Phase 1/New Construction
Contractor is continuing to excavate for footings and foundations. Pouring concrete in Area 4A approx. June 29th.
Area 2 is poured out. Area 3 is almost complete for concrete pours.
Framing of first floor continues in Area 2.
Strip Stem Walls poured in Areas 4A and 4B.
North side of existing wall of Commons is underway for framing of the new openings.
Electrical duct bank is complete.

Site Work
New FDC (fire department connection) at the NE corner of the building, (South side/near counselor office). This work service won’t be done until after school is out the week of the 26th.

May 29 - June 2

  • May 22 - 26 EHS construction slab poured
  • May 22 - 26 EHS construction elevator pit dampproofed and backfilled
  • May 22 - 26 EHS construction gym hallway
  • May 22 - 26 EHS construction framing prep
  • May 22 - 26 EHS construction stem wall prep and duct bank placed

Work Description: Please note: Activities may change and are weather dependent

Phase 1A: Gymnasium: Boys Lockers: Girls Lockers and Athletic Offices

Phase 1A:
Court Inserts were delivered on Wednesday, May 31st.

Main Gymnasium:
CMU Infills completed this week.
Structural Steel install completed.
Framing and Furring of Walls and Ceiling completed.
Backing for equipment/bleachers/etc. installed.
New openings (demo) made
Electrical rough-in completed.
Fire Sprinkler and HVAC rough-in began on Tuesday, May 30th; should be completed by Friday, June 9th.
Insulation installed on Tuesday and Wednesday of this week.

Men’s Locker Room
Structural Framing Upgrades/GluLam Beam install began on May 29th, completed on Friday, June 2nd.
Red Iron installation completed.
Plumbing and Electrical rough-in completed at CMU wall locations.
Interior Wall Framing/Sheetrock prep completed.
CMU Infill and New Walls began May 30th; should be completed by Monday, June 12th.
Plumbing, Electrical, HVAC and Fire Sprinkler rough-in began on May 30th; should be completed by Monday, June 12th.
HM Door Dams installed.

Gym Lobby
Slab prep, Slab on Grade Reinforcing completed on Friday, June 2nd.

Athletic Offices
Existing MEP and Fire Sprinklers removed from West Side Wall.
Slab sawcut and removed for new footings.
Excavation for new footings/Slab on Grade completed.

Next Week:
Vapor Barrier install, Slab on Grade Placement and Finishing, Framing, and MEP rough-in in Athletic Offices.
Scoreboard scheduled to be delivered on June 5th!


Phase 1/New Construction:
Hardscape/Site Elements Demo is ongoing.

Area 2:
Wall Framing/Sheathing for first floor continues through June 16th.
Erection of Red Iron and GLBs began on June 1st.
Placement of forms for footings in 4A began this week and is ongoing. Pouring for these footings scheduled for approximately June 2nd.
Elevator pit and walls have been completed. Back fill is complete.
Damp proofing and footing drains are ongoing. All areas are being backfilled.

Area 4A/4B:
Placement of forms for footings began last week and should be completed by June 8th
Re-Steel of Footings and Stemwalls scheduled to be completed by June 7th.
Strip Footings were poured on Tuesday, June 30th.

Next Week:
Framing in Area 2 continues. Stemwalls in Area 4A scheduled for re-steeling on June 5th and 6th.

May 22 - May 26

  • May 22 - 26 EHS construction slab poured
  • May 22 - 26 EHS construction elevator pit dampproofed and backfilled
  • May 22 - 26 EHS construction gym hallway
  • May 22 - 26 EHS construction framing prep
  • May 22 - 26 EHS construction stem wall prep and duct bank placed

Work Description: Please note: Activities may change and are weather dependent

Phase 1A: Gymnasium: Boys Lockers: Girls Lockers and Athletic Offices
Phase 1: New Construction Classroom Wings
Phase 1A/Gymnasium:
Structural steel is ongoing.
Electrical and plumbing rough-in has begun.

Phase 1/New Construction:
Contractor is continuing to excavate for footings and foundations.
Slab pours occurred on May 22nd in Area 2.
Footings over-excavated and filled to grade.
Wall framing has begun in Area 2.
Electrical duct bank work is ongoing.
Placement of forms for footings in 4A began this week and is ongoing.
Pouring for these footings scheduled for approximately June 2nd.
Elevator pit and walls have been completed. Back fill is complete.
Damp proofing and footing drains are ongoing. All areas are being backfilled.

Next Week:
More over-excavation and fill, footings pour, and framing of first floor rooms!

May 23 - May 31

  • May 23 - 31 EHS construction
  • May 23 - 31 EHS construction
  • May 23 - 31 EHS construction
  • May 23 - 31 EHS construction
  • May 23 - 31 EHS construction
  • May 23 - 31 EHS construction
  • May 23 - 31 EHS construction

Work Description: Please note: Activities may change and are weather dependent

Phase 1A: Gymnasium: Boys Lockers: Girls Lockers and Athletic Offices
Phase 1: New Construction Classroom Wings

Phase 1A/Gymnasium:
Structural steel is ongoing. Mechanical work and the rooftop mechanical units scheduled after school starts.
Gym sheet rock is being installed. The furring strips are being placed on top of the existing tile and will have new acoustical tile on top of the furring strips.
Epoxy floor is scheduled for July 19th.
Fire Sprinkler work is starting May 30th.
Electrical and plumbing rough-in has begun.
Gym lobby slab on grade is scheduled to partially complete June 1st, remaining area will be constructed after June 26th (after school is out).
Gym floor is scheduled at the end of June 21st, to be delivered and installed on June 27th.
Owner furnished items June 26th - June 30th including new scoreboard, divider curtain, etc. Bleachers are scheduled to be installed on July 25th.
Technology install (i.e., projection screens) will be installed the end of July.

Phase 1/New Construction:
Contractor is continuing to excavate for footings and foundations.
Concrete pours are continuing to be scheduled. Slab pour in Area 2 occurred on Friday, May 19th and Monday, May 22nd.
Glulams (beams) for Area 2 have arrived. Area 3 Glulams will be following.
Wall framing has started at Area 2.
Electrical duct bank is ongoing.
Forming of the footings for 4A is ongoing. Pouring for these footings is scheduled for approximately June 2nd.
Elevator pit and walls have been completed. Back fill is complete.
Dampproofing and footing drains are ongoing. All areas are ready for backfill.

Site Work:
New FDC (fire department connection) at the NE corner of the building, (South side/near counselor office). This work service won’t be done until after school is out.
Water line has been cut and capped.
Storm work (South and East side) was completed. This will complete the access road at Area 2.

May 15 - May 19

  • May 15 - 19 EHS gym furring
  • May 15 - 19 May 15 - 19 EHS gym entryway
  • May 15 - 19 EHS locker room SOG poured
  • May 15 - 19 EHS elevator pit damp proofing
  • May 15 - 19 EHS excavation
  • May 15 - 19 EHS foundation

Work Description: Please note: Activities may change and are weather dependent

Phase 1A: Gymnasium: Boys Lockers: Girls Lockers and Athletic Offices
Phase 1: New Construction Classroom Wings

The construction access road along the West side of Area 4 has been completed.

Phase 1A/Gymnasium:Concrete/Seismic and Framing
Slab on grade completed in locker rooms.
Framing and furring along East and West walls is ongoing.
Seismic upgrades, including diaphragm blocking along East and West is occurring.
Electrical rough-in is being completed where possible. Electrical feeders to be planned the week after May 16th.
Lobby footings prep is nearly complete.
Structural steel delivered on May 15th.
CMU infills are nearly complete.

Phase 1/New Construction:
Contractor is excavating for footings and foundation.
Footings all drilled, ready for epoxy dowels.
Capillary break (6" Cap) placement on May 12th and 15th.
Additional concrete pours are scheduled for May 19th.
Footing pour on May 26th.
Additional slab on grade re-enforcement continues through May 18th

April 24 - April 28

  • April  24 - 28 men's locker room at EHS
  • April  24 - 28 SOG prep and locker bases at EHS
  • April  24 - 28 gym furring and framing at EHS
  • April  24 - 28 inderslab plumbing done in men's locker room at EHS
  • April  24 - 28 footings construction work at EHS
  • April  24 - 28 strip footings construction work at EHS
  • April  24 - 28 foundation construction work at EHS
  • April  24 - 28 excavation fill to grade footings construction work at EHS
  • April  24 - 28 foundation different angle construction work at EHS

Work Description:
Please note: Activities may change and are weather dependent

Phase 1A: Gymnasium: Boys Lockers: Girls Lockers and Athletic Offices

Phase 1: New Construction Classroom Wings

Demolition:
Demo of hardscape and site elements continues.

Phase 1A/Gymnasium:
Cutting of new roof openings is ongoing.
Preparation for slab-on-grade concrete continues through Monday, May 1st.
CMU infills continuing through the first two weeks of May.
Wall and Ceiling framing and furring is ongoing.
Roof Panel Blocking was completed.

Men's Locker Room:
Preparation and reinforcing for slab-on-grade concrete continues
CMU walls and infill is ongoing.

Gym Lobby Addition
Forms for footings were placed.
Re-steeling of stemwalls was completed.

Phase 1/New Construction:
Layout footings were poured.
Over-excavation of finished footings and fill to grade continues.
Underslab plumbing and electrical were installed.
12" sub-base was completed on Monday.
Wall pre-fabs began and will continue.
Additional strip footings were poured on Tuesday.
Stemwall re-steeling was completed.

Next Week:
Stemwall damproofing begins and installation of new water lines and hydrant.

April 17 - April 21

  • April  17 - April 21 construction work at EHS
  • April  17 - April 21 construction work at EHS
  • April  17 - April 21 construction work at EHS
  • April  17 - April 21 construction work at EHS
  • April  17 - April 21 construction work at EHS
  • April  17 - April 21 construction work at EHS
  • April  17 - April 21 construction work at EHS
  • April  17- April 21 construction work at EHS

Work Description:
Please note: Activities may change and are weather dependent

Phase 1A: Gymnasium: Boys Lockers: Girls Lockers and Athletic Offices

Phase 1: New Construction Classroom Wings

Demolition:
Demo of the old sanitary sewer and storm system is now continuing through next week.

Phase 1A/Gymnasium:
Backfill around footings and shotcrete walls is complete.
Cutting of new roof openings is ongoing.
Roof panel blocking was completed.
Saw cutting at the new exterior opening of the gym was completed.
Wall and Ceiling framing and furring is ongoing.
Walkway canopy has been removed.

Phase 1/New Construction
Underslab MEP was completed.
12" sub base was placed.
Additional footings and stem walls were poured on Thursday, April 20th.
New stem wall forms are being placed.
Finished footings were overexcavated and filled to grade.

April 10 - April 14

  • April  10 - April 14 construction work at EHS
  • April  10 - April 14 construction work at EHS
  • April  10 - April 14 construction work at EHS
  • April  10 - April 14 construction work at EHS
  • April  10 - April 14 construction work at EHS
  • April  10 - April 14 construction work at EHS
  • April  10 - April 14 construction work at EHS

Work Description:
Please note: Activities may change and are weather dependent

Phase 1A: Gymnasium: Boys Lockers: Girls Lockers and Athletic Offices

Phase 1: New Construction Classroom Wings

Overall:
With the heavy rains over the last week, Forma has done an excellent job of keeping the construction site safe and dry, with grading and moisture control.

Demolition:
Demo of the old sanitary sewer and storm system is scheduled to be completed by Friday, April 14th.

Phase 1A/Gymnasium:
Footing Prep/Concrete
Forms for interior footings (shear walls) were completed in the Gym and Athletic Locker areas, with rebar/steel placed. Concrete was poured on Tuesday, April 4th.
* Shotcrete Stemwalls were poured
* Strip footings poured.
* CMU infills were completed.
* Excavation for underslab plumbing continues.
* Wall, ceiling framing and wood stud furring has begun.

Phase 1/New Construction:
Storm system installation continues through next week. Underslab MEP continues.

April 3 - April 7

  • April  3 - April 7 batter board construction work at EHS
  • April  3 - April 7 sewer demo construction work at EHS
  • April  3 - April 7 staging area 2construction work at EHS
  • April  3 - April 7 staging area 3construction work at EHS
  • April  3 - April 7 staging area construction work at EHS
  • April  3 - April 7 strip footings construction work at EHS
  • April  3 - April 7 steeling shear wall construction work at EHS

Work Description:
Please note: Activities may change and are weather dependent

Phase 1A: Gymnasium: Boys Lockers: Girls Lockers and Athletic Offices

Phase 1: New Construction Classroom Wings

Demolition:
Demo of the old sanitary sewer and storm system is scheduled to be completed by Friday, April 14th.

AG Bathrooms:
The AG bathrooms are nearing completion.
Toilet accessories have been installed.
The final mechanical and building inspections occurred this week, and the temporary fence near the AG building is being removed shortly.
The partitions between the stalls are scheduled to be delivered in two weeks. In lieu of placing a temporary partition, we will wait to open the AG Bathrooms after the final one is delivered and installed.

Phase 1A/Gymnasium:
Footing Prep/Concrete:
Forms for interior footings (shear walls) were completed in the Gym and Athletic Locker areas, with rebar/steel placed. Concrete was poured on Tuesday, April 4th.
Shotcrete wall was re-steeled.
CMU infills should be completed by April 14th.
Excavation for underslab plumbing began on Thursday, April 6th.
Wall, ceiling framing and wood stud furring begins next week.

Phase 1/New Construction:
The staging/laydown area was completed this week.
The re-route of the sanitary sewer will be completed today.
Storm system installation continues through next week.
Strip footings were poured on Tuesday, with footings for stem walls being poured on Friday.
Underslab MEP began on Wednesday.
The building Pre-Fab Deck will be finished by Tuesday, April 11th.
The batter boards go up today!
Next week: Pre-Fab wall installation begins.

March 27 - March 31

  • March  27 - March 31 construction work at EHS
  • March  27 - March 31 construction work at EHS
  • March  27 - March 31 construction work at EHS
  • March  27 - March 31 construction work at EHS

Work Description:
Please note: Activities may change and are weather dependent

Phase 1A: Gymnasium: Boys Lockers: Girls Lockers and Athletic Offices
Phase 1: New Construction Classroom Wings

Demolition:
The majority of the exterior demolition is complete. There are smaller areas that will continue including some of the outdoor canopies as project progresses.

AG Bathrooms:
The AG bathrooms are nearing completion. Tile complete. Wall FRP will be installed Monday next week. Toilet partitions will have temporary partitions installed until the final partitions will be delivered. Toilet partitions are a long lead time. It will be open for use in mid-April !

Phase 1A/Gymnasium:
Demolition:
Roof work will be coordinated with demolition at the roof. Cleanup of gymnasium demolition is complete. Men’s locker room is complete. Saw cutting complete in locker room.

Footing Prep:
Gym and Athletic Locker Area interior footings are being excavated for shear walls.
Rebar/steel placement is ongoing. Concrete is tentatively scheduled to be placed March 24th.

Concrete:
Resteel delivery is expected on Friday.
Glue Lams will be delivered April 10th.
Shotcrete placement for many of the interior walls will start to occur first week in April.

Phase 1/New Construction
Removal of hardscape is complete. Contractor is excavating for footings and foundation. Footings all drilled, ready for epoxy dowels. Concrete placement is scheduled for the week of March 27 through 31st. Concrete shotcrete is planned for April 10th.
Forma will start excavating for utility work.
CMU wall infills scheduled for week of March 27th through 31st.
Walls will start to be framed horizontally starting mid May. Shortly thereafter, they will be vertical.

March 24 - April 7

  • March 24 - April 7 construction work at EHS

  • March 24 - April 7 construction work at EHS
  • March 24 - April 7 construction work at EHS
  • March 24 - April 7 construction work at EHS
  • March 24 - April 7 construction work at EHS
  • March 24 - April 7 construction work at EHS

Work Description:
Please note: Activities may change and are weather dependent

Phase 1A: Gymnasium, Boys Lockers, Girls Lockers and Athletic Offices

Phase 1: New Construction Classroom Wings

Demolition:
Some of the exterior canopies are still to be demolished as project progresses.

AG Bathroom: Almost complete! Planning on be open the week of April 10th!

Phase 1A/Gymnasium:
Main Gymnasium:
Ceiling Demo completed. Old roof framing has been removed and reframed to match the existing roof framing. Concrete floor has been sawcut for new court inserts.

Men's Locker Room:
The lockers and selected walls have been removed from the Men's Locker Room. Concrete has been removed and preparation for new footings and underslab for plumbing has begun.

Gym Lobby and Hallway:
Selected demolition has been completed in this area. Excavation done and forms for new wall footings have been laid.

Phase 1/New Construction:
The contractor has been busy placing footing forms and rebar placed.
Footing and foundation concrete was poured Friday!!

Phase 0/Closeout:
Flooring has been completed along the Cyclorama Wall in the video editing area (Green Room).
HVAC motor has been replaced and balancing of the system ongoing.
Ongoing work is needed for the controls for lighting and heat.

March 1 - March 31

  • March 1 - 30 construction work at EHS

  • March 1 - 30 construction work at EHS
  • March 1 - 30 construction work at EHS
  • March 1 - 30 construction work at EHS

Work Description:
Please note: Activities may change and are weather dependent


Phase 1A: Gymnasium: Boys Lockers: Girls Lockers and Athletic Offices

Phase 1: New Construction Classroom Wings

Site Set Up:
Forma Construction has done a great job keeping the construction area safe, secure and separate from kids. We know the construction is an impact and the students, staff and community have been amazing!

Demolition:
The majority of the exterior demolition is complete. There are smaller areas that will continue including some of the outdoor canopies as project progresses.

AG Bathrooms:
The AG bathrooms are nearing completion. We are expecting lighting to arrive at the end of the month and remaining finishes. The District invested in a long-term solution to support the kids in the future. In lieu of providing temporary bathrooms, the District invested in upgrading the existing bathrooms in the AG. It will be open for use in mid-April!

Phase 1A/Gymnasium:
* Demolition
Gym interior demolition is complete. Interior Locker Room demolition is ongoing. The District Technology Staff and Forma Construction have done a great job to disengage existing systems from the demolition work. It is a process for a large campus which is fully occupied! Nice job Forma.

* Footing Prep
Gym and Athletic Locker Area interior footings are being excavated for shear walls. Rebar/steel placement is ongoing. Concrete is tentatively scheduled to be placed March 24th.

* Concrete
Shotcrete placement for many of the interior walls will start to occur first week in April.

Phase 1/New Construction
Removal of hardscape is complete. Contractor is excavating for footings and foundation. The week of the 27th, Forma is tentatively planning for utility prep / underground electrical and plumbing.

January 20 - February 6

  • January 20 - February 6 construction work at EHS
  • January 20 - February 6 construction work at EHS
  • January 20 - February 6 construction work at EHS
  • January 20 - February 6 construction work at EHS
  • January 20 - February 6 construction work at EHS
  • January 20 - February 6 construction work at EHS
  • January 20 - February 6 construction work at EHS

High School Phase 0 (Portables and Building 1000)
Work Description by Neeley Construction
Move In and Continuing:
Thank you for your patience! We can’t thank staff and faculty enough for their patience.

Culinary Arts Room is wrapping up and we start this week to provide inspections from all of the related departments and jurisdictions.

Punchlist is ongoing and a very detailed and specific list of items has been sent to the General Contractor to be fixed. It will take time, but each item will be addressed properly.

Controls:
The automatic controls of the lighting and heat. It is controllable currently, but the automatic DDC based controls is up and working and we are fine tuning it currently.

High School Renovation and Addition
Work Description by Forma Construction:
Schedule:
Construction trailers are set up, furnished, power, stairs and connected to internet. Vault work is completed. Phase 1 demo has started. Phase 1A will start mid-February. More detail on Phase 1A schedule next week.

AG building bathroom improvements the District has been planning. Temporary bathrooms have been set up to support the AG building remodel. We will start the bathroom improvements on the 30th. Temporary bathrooms will be ongoing until end of February.

Commons space:
Thursday after school at 3pm additional work at the commons wall.

Demo:
Monday! Building 100 will be removed on Monday. Typically, the demo and haul off of the material takes a week. Starting the following Monday, February 6th, building 200 will commence demolition. Building 300 will follow as well. Demo for the courtyard area is tentatively scheduled for February 13th.

Abatement:
Building 300 ongoing.

Systems Work Ongoing:

  • Trench work and data/fiber installation ongoing.
  • Fire Alarm work is being coordinated. It is being rerouted so that the Buildings 100, 200 and 300 are taken off line. That work has been ongoing this week in preparation for Monday’s demolition.

January 6 - January 20

  • January 6 - 20. classroom move in work at EHS
  • January 6 - 20. classroom move in work at EHS
  • January 6 - 20. classroom move in work at EHS
  • January 6 - 20. classroom move in work at EHS

High School Phase 0 (Portables and Building 1000)
Work Description by Neeley Construction
Move In:
We have moved in to all areas except for the Culinary Arts and Cyclorama Green Room. Thank you for your patience! We could not have done it without the dedication of the entire high school staff - especially of Jill Burnes, Pete French and the entire Technology Team. Thank you!

Controls:
The lighting and mechanical control work will be set up and commissioned starting Monday January 16th. It will take another few weeks to completely tie in with all of the controls.

Continuing Work:
Culinary hood coordination is the most intensive with multiple trades involved.

High School Renovation and Addition
Work Description by Forma Construction
Schedule:
As you can see, fencing is up, construction trailers are up and prep for abatement and demolition of the 100, 200 buildings is starting!

The largest impact to the high school is the construction wall to be constructed in the commons. It will be completed in sections, with the largest section to be constructed on January 16th. This will be an exciting time for everyone and will be a transition!

Next Thursday and Friday, there will be an auger drill between the existing portables and North of the AG Building. It will have fencing around it and will be removed Friday. It is the infiltration monitoring used for the project.

Work ongoing:
Trench work and data/fiber installation ongoing. Fire Alarm work is being coordinated.

December 15 - January 2, 2017

  • photo of November 18 - December 2 work at EHS
  • photo November 18 - December 2  work at EHS
  • photo of November 18 - December 2 work construction work at EHS
  • photo of November 18 - December 2  work construction work at EHS

Work Description by Neeley Construction
Finishes:
Casework install complete in many of the classrooms. Flooring complete in Photo Classroom 1005. Flooring scheduled for remaining spaces. Culinary Room, Video, Sound Classroom has casework installed. Paint ongoing. Ceiling tiles scheduled over break.

Site/Underground Work:
Prep for sidewalks not complete. Temperature has been too low for asphalt install.

Portables:
Power is up on the portables! Data connections are being scheduled.

Move In:
Contractor cleanup is occurring. Various classrooms are moving over break starting on December 21st - January 2nd.
Transition:
Neeley Construction will be completing their scope of the High School remodel work in December. Over December break, Enumclaw School District will be partnering with with Forma Construction for the overall High School Expansion and Renovation.

High School Renovation and Addition
Construction Activities for December

Work Description by Forma Construction:
Move Schedule:
December 19th evening movers will commence in the Admin area.
December 21st and 22nd and 23rd movers will continue and expect to be completed.

Forma Construction:
Forma is on campus starting Wednesday, December 21st. We are extremely excited to be working closely with Forma Construction who has extensive school experience on an occupied campus.

Work during December:
Trench work and data/fiber installation

EHS trench plan smaller size

EHS site plan smaller

November 18 - December 2

  • photo of November 18 - December 2 work at EHS
  • photo November 18 - December 2  work at EHS
  • photo of November 18 - December 2 work construction work at EHS
  • photo of November 18 - December 2  work construction work at EHS

Work Description:
Framing:
Interior wall framing is complete.
Insulation and gypsum board is ongoing.
Mechanical equipment is ongoing.
Casework mock up complete.

Site/Underground Work:
Completing the electrical and vault work is weather dependent.
Path for sidewalks are complete.

Overall Schedule:
West side of 1000 to be complete at the end of November.
Culinary Room will be complete in December.

Transformers:
Transformers arrived. Install to include a shut down over a weekend. To be scheduled.

Panel Replacement:
November 22/23 are the tentative switch over dates.


High School Renovation and Addition
Construction Activities for November and December

Move Schedule:
Staff Packing is ongoing currently. Boxes have arrived!
December 19th evening movers will commence in the Admin area.
December 21st - 23rd movers will continue and expect to be completed.

More scheduling information will be updated as we start working closely with Forma Construction. Forma will start work including fencing and courtyard infrastructure work December 21st. Forma will mobilize January 9th, 2017!

November 10 - November 23

  • photo of November 10 - 12 work at EHS
  • photo of November 10 - 12 work work at EHS
  • photo of November 10 - 12 work construction work at EHS
  • photo of November10 - 12 work construction work at EHS
  • photo of November 10 - 12 work construction work at EHS

Work Description:
Framing
Interior wall framing is complete.
Insulation in the walls is ongoing.
Gypsum board (except Culinary Room) is ongoing. (West side).
Mechanical equipment is ongoing.
Casework mock up complete.

Site/Underground Work
Completing the electrical and vault work is weather dependent.
Transformer delivery is expected any day.
Contractor will place the transformer over a weekend or a no school day.
Path for sidewalks is complete.

Overall Schedule
West side of 1000 to be complete at the end of November.
Culinary Room will be complete in December.

High School Renovation and Addition
Construction Activities for November

Welcome Forma Construction! We are happy to have Forma Construction partnering with Enumclaw School District for the High School Renovation and Addition. www.formacc.com

More scheduling information will be updated as we start working closely with Forma.

November 3 - November 17

  • photo of November 3 - 17 portable work at EHS
  • photo of November 3 - 17 portable work at EHS
  • photo of November 3 - 17 construction work at EHS
  • photo of November 3 - 17 construction work at EHS
  • photo of November 3 - 17 construction work at EHS
  • photo of November 3 - 17 construction work at EHS

High School Phase 0
Work Description:
Framing
Rough in in the framing for electrical and plumbing is ongoing.
Insulation in the walls has started.
Gypsum Board will begin to be hung (West side).
Mechanical equipment is ongoing.

Site/Underground Work
Electrical vault and replacement is ongoing.
Completing the electrical and vault work is weather dependent.
Prep for sidewalks are completed for the portables pathways.
Asphalt is scheduled in two weeks and weather dependant.

October 13 - October 21

  • photo of October 13 - 21 construction work at EHS
  • photo of October 13 - 21 construction work at EHS
  • photo of October 13 - 21 construction work at EHS
  • photo of October 13 - 21 construction work at EHS
  • photo of October 13 - 21 construction work at EHS
  • photo of October 13 - 21 construction work at EHS

High School Phase 0
Work Description:
Site
Asphalt work complete.
Fire lane work and access (for electrical vault and conduit placement) is ongoing.

Framing
Framing is near complete.
Rough in in the framing for electrical and plumbing has started. Insulation will start after rough in complete.
Gypsum Board will begin to be hung (West side).
Beams will be replaced at mezzanine.
Truss joist replacement for the mechanical mezzanine/equipment is ongoing.

Site/Underground Work
Electrical vault and replacement is ongoing. Vaults will be placed this week.

October 6 - October 13

  • photo of October 6 - 13 construction work at EHS
  • photo of October 6 - 13 construction work at EHS
  • photo of October 6 - 13 construction work at EHS
  • photo of October 6 - 13 construction work at EHS
  • photo of October 6 - 13 construction work at EHS

High School Phase 0
Work Description:

Site/Grease Interceptor:
Asphalt around the road work this week.

Fire lane work and access will be complete by the end of the October.

Concrete/Framing:
Concrete pour complete October 5th - Great milestone!

Shear wall and hold down inspection complete.

Framing inspection is ready.

Gypsum Board will begin to be hung next week (West side).

Shoring occurring next week for mezzanine floor. Beams will be replaced.

Truss joist replacement for the mechanical mezzanine/equipment over the next two weeks.

Site/Underground Work:
Electrical vault and replacement is ongoing. Vaults will be placed this week.

September 28 - October 6

  • photo of September-October 6 construction work at EHS
  • photo of September-October 6 construction work at EHS
  • photo of September-October 6 construction work at EHS
  • photo of September-October 6 construction work at EHS
  • photo of September-October 6 construction work at EHS

High School Phase 0
Work Description:

Grease Interceptor:
Commencing this week. Inspection next week. Concrete sidewalk will be replaced in approx. 10 days. North access will be open by September 30th.

Portables near Tennis Courts:
To be placed on September 29th/30th.

Culinary Arts/1000:

     * Concrete slab infill occurring next week.

     * Wall framing will be complete September 27th and insulation placement will commence after. Hollow metal door frames will be placed September 28th.

Mezzanine:
Structural upgrades will commence the 28th for the mezzanine floors.

September 14 - September 30

  • photo of September work at EHS 1000 building construction
  • photo of September work at EHS 1000 building construction
  • photo of September work at EHS 1000 building construction
  • photo of September work at EHS 1000 building construction

 

Grease Interceptor:
Commencing during this time frame and inspection will also occur. Concrete sidewalk will be replaced. Access to the north will be open by September 30th.

Portables near Admin:
Portables to be placed and jointed September 29th-30th.

Portables near Tennis Courts:
To be placed on September 29th-30th.

Culinary Arts/1000:
Concrete slab infill occurring during this time frame, starting approximately September 21st. Wall framing will be complete September 27th and insulation placement will commence after. Hollow metal door frames will be placed September 28th.

Mezzanine:
Structural upgrades will commence the 28th for the mezzanine floors.

Badges:
Neeley Construction has created lanyards with names to indicate construction crew on campus.


September 9 - September 16

Enumclaw High School - Phase 0

Work Description:

Sitework and Portables:
Final placement of the North portables will be placed the week of the 19th
The trenching from the North to the South will commence this month. This will take approx. three weeks for trenching/conduit placement and backfill.

Building 1000:
Footings and underfloor plumbing ongoing. Rebar is being placed to prep for concrete placement.
Grease Interceptor work will be ongoing for three weeks (at North entry).
Electrical underground work ongoing.
CMU infill is completed.

Parking & Access:
Parking around the fire lane will be continued to be closed off.

August 24 - September 7, 2016

  • photo of prep work for portables behind District Office
  • photo of portables in EHS parking lot
  • photo of underfloor work at EHS 1000 building
  • photo of underfloor work at EHS 1000 building
  • photo of relocation of structural walls at EHS 1000 building
  • photo of relocation of structural walls at EHS 1000 building

High School Phase 0

Work Description:

Work is focused on the site work for the southern portables.

Portables stored in the SE gravel parking lot
South portables will be placed the first week of school and likely be ready for use in October
Other portables will be placed but some will remain in the parking area for a few weeks

Interior Work

Footings and underfloor plumbing still being installed.
Structural walls are being relocated with temporary support.

Parking & Access

Parking for the Autoshop caged area will not be available
Parking around the fire lane will be closed off
Parking will be routed to the overflow Gravel Parking next to the tennis courts

July 18 - July 29, 2016

  • EHS demolition
  • EHS demolition
  • EHS demolition
  • EHS demolition
  • EHS demolition
  • EHS demolition

High School Phase 0

Thank you for your patience while we clarify access for safety and security!

Work Description:

* Demolition is nearing completion

* Slab removal is ongoing and almost ready for underground rough in

* Erosion control will start soon

* Electrical, Mechanical, Plumbing and Fire Sprinkler rough in and framing will start next week

* Utility trenching will start the 27th and access will be impacted

Changes to Access:

* Parking for the Autoshop caged area will not be available

* Parking around the Fire Lane will be closed off

* Parking will be routed to the Overflow Gravel Parking next to the tennis courts

June 28, 2016

  • BDE portable moves to EHS

  • BDE portable placed at EHS

Enumclaw High School Phase 0

In preparation of the remodel and additions at the High School campus, we are completing some utility and upgrades inside and outside.

Neeley Construction is onsite helping complete the work that includes: utility trenching, mechanical upgrades, electrical upgrades, renovation of Building 1000, and the placement of all of the portables. The portables will provide temporary classrooms for students during the Construction Project at the High School.

The portables will be set and ready for student occupancy at the beginning of the 2016-2017 school year. The remodeled 1000 Building will be ready for student use after October 31st.


Enumclaw High School Phase 1 and 2

NAC Architects are continuing the design, permitting and planning required for the High School Addition and Modernization.

Architectural Renderings

Virtual Tour - Most devices and computers will work for viewing; however we recommend you view it using the Google Chrome browser because it didn’t work using Internet Explorer 11 on a couple computers we tested. Use your mouse to scroll through or a mobile device to view in virtual reality (FYI - the opening image may be the floor so move your mouse or phone up).