BDE Timeline
Translation for above timeline graphic
- July, 2015 - December, 2015: Schematic Design with Value Analysis in November.
- December, 2015 - February, 2016: Design Development
- Staff space review meetings in December
- Site review permit 1/1/16
- February, 2016 - May, 2016: Construction Documents
- Issue permit set 3/16/16
- Building bid
- June, 2016 - August, 2016
- Demolition 6/20/16 - 8/30/16
- August, 2016: Construction begins. Open Fall 2017