EHS Timeline
Translation for above timeline graphic
- January - March, 2016: Design Development
- Ext. set 4/7/16
- Final Design Development 4/30/16
- April - June, 2016: 1000 Building Bid
- April - October, 2016: construction Documents
- August - December, 2016: 1000 Building Remodel Construction
- September - October, 2016: Bid
- Issue bid set 9/16/16
- Open bids 10/27/16
- January - June/July, 2017: Building Construction - Phase 1 (New classrooms and PE area remodel)
- Start construction 1/2/17
- Move-in June/July, 2018
- September, 2018: School Begins
- July, 2018 - June/July, 2019: Building Construction - Phase 2 (includes Music and Wrestling Room)
- July, 2019: Move in
- June/July, 2019: Site Construction Parking