EHS Timeline

Translation for above timeline graphic

  • January - March, 2016: Design Development
    • Ext. set 4/7/16
    • Final Design Development 4/30/16
  • April - June, 2016: 1000 Building Bid
  • April - October, 2016: construction Documents
    • Issue permit set 7/14/16
  • August - December, 2016: 1000 Building Remodel Construction
  • September - October, 2016: Bid
    • Issue bid set 9/16/16
    • Open bids 10/27/16
  • January - June/July, 2017: Building Construction - Phase 1 (New classrooms and PE area remodel)
    • Start construction 1/2/17
    • Move-in June/July, 2018 
  • September, 2018: School Begins
  • July, 2018 - June/July, 2019: Building Construction - Phase 2 (includes Music and Wrestling Room)
  • July, 2019: Move in
  • June/July, 2019: Site Construction Parking
    • Complete 12/2019